A structured process for the fuzzy front-end of complex projects

&
Received 04 Sep 2023, Accepted 12 Feb 2024, Published online: 11 Apr 2024

Abstract

The front-end stage of projects, which covers the period from inception through to project approval, is not well understood in the literature and is considered ‘fuzzy’. Therefore, the objective of this paper is to develop a structured process for the project front-end stage of complex projects. In this study, the rigorous and protracted front-end process followed by Australian Defence acquisition and development projects is analysed. Findings propose a front-end process that consists of the following four steps: (1) project trigger identification, (2) project idea generation, (3) business case development, and (4) business case appraisal. We further detail the activities included in each step and propose practical implications for operations managers and the organisation. By structuring the front-end process, our research contributes to the operations management literature by clarifying roles, responsibilities, and activities in the management of the front-end of complex projects and their alignment with the operations’ environment.

1. Introduction

Organisations increasingly invest in projects to enhance operations performance (Zwikael and Meredith Citation2018). Examples of such projects include the introduction of a new manufacturing line and re-engineering the supply chain network. However, these projects are becoming more complex, as they: increasingly rely on distributed and networked teams (Ojiako et al. Citation2023); need to coordinate under time pressure (Ju and Ning Citation2023); are often conducted by multiple organisations (Klakegg, Williams, and Shiferaw Citation2016; Liedtka and Locatelli Citation2023); commonly have more diverse team members, higher technology risks, ambiguous scope, an unreliable supply chain, and more external stakeholders (Haaskjold, Andersen, and Langlo Citation2023).

The front-end stage of these complex projects is considered most important (Klakegg, Williams, and Shiferaw Citation2016; McDonald Citation2017). During this stage, managers select the best potential project from various proposals, define the project goals and scope, and ensure the project’s alignment and effective coordination with the operations environment (Zwikael and Smyrk Citation2019). The front-end is concluded when the project is funded and focus shifts to delivering the expected outputs (Williams et al. Citation2019).

The front-end shapes the project and, if done well, reduces its risk level and enhances its likelihood of success (Chenger and Woiceshyn Citation2021; Edkins et al. Citation2013; Kolltveit, Karlsen, and Grønhaug Citation2004; Morris Citation2013; Pinto and Winch Citation2016; Testorelli, Ferreira de Araújo Lima, and Verbano Citation2022). Conversely, an ineffective front-end process may end with unclear goals and scope and contribute to a poor project selection decision. As a result, Samset and Volden (Citation2016, 301) argue project failure can often be ‘traced back to decisions in the earliest stages, when the initial idea was conceived and developed’.

Yet, following a systematic literature review on the front-end of projects, Williams et al. (Citation2019, 1137) concludes that despite the front-end being critical for project success, it is still ‘not well understand’. More specifically, there is no agreement in the literature as to what constitutes an effective front-end process (Edkins et al. Citation2013). This may be a result of the literature focusing for many years on the planning and execution stages of projects, while overlooking the front-end stage. For example, there has been much emphasis on project contracting and planning, but less on the process of making a quality decision regarding which projects to fund (Mitchell Citation2018; Xiong et al. Citation2022).

This lack of clarity regarding the project front-end stage creates a significant research gap. This research gap is important because it raises ambiguity in processes, roles, accountabilities, and decision-making that have the potential to hinder project and operations performance. It is important that operations managers better utilise their role in steering the front-end of projects before the responsibility temporarily transfers to a project manager for delivering its outputs. In particular, a clear front-end process can help managers in the operations environment to generate effective project ideas to resolve critical operations problems, set effective project goals, and develop a high-quality business case to enhance project investment decision making. Following this research gap and the growing importance of effective management of the project front-end stage in operations management research and practice, we raise the following research question: How can the front-end stage in complex projects be improved?

Our research aims to reduce the ‘fuzziness’ of the front-end stage by identifying delineated and structured steps to support existing processes (Alimadadi Citation2022; Chenger and Woiceshyn Citation2021). This aim is supported by the fact that the literature has found multiple advantages for a structured process. For example, a structured front-end process of complex projects can assist managers to overcome ‘bounded rationality’ whereby their capacity to operate within and make sense out of the environment is limited (March and Simon Citation1958). Further, a structured process can help in better navigating the organisational environment as the repetitive, administrative components of the decision are completed for them, leaving them free to use their cognitive capacity to focus on the unknown elements of the decision. The purpose of organisational formal processes ‘is not to micromanage and control’ but to foster learning and innovation, and ‘provide the conditions and resources to enable project effectiveness’ (Kenny Citation2003, 53). Finally, in the context of the project front-end stage, a longitudinal study found formal organisational processes have a positive impact on the setting of project goals (Zwikael and Meredith Citation2019). However, there are also disadvantages of a structured organisational process, such as it impedes innovations and increases duration and cost (Christensen Citation2013; Reilly and Tushman Citation2004).

As knowledge on the project front-end is led by practice, where literature is lagging behind, we study the front-end process of complex Defence acquisition and development projects. These Defence processes are rigorous, protracted and outperform similar-size private sector processes (Cook and Unewisse Citation2020). Through an in-depth document analysis and an illustrative case, we develop a structured process for the fuzzy front-end stage of complex projects. We contribute to the Operations Management literature by extending our knowledge of the front-end process from best practice. We next review the literature on the front-end of complex projects, before discussing our methodology. We then present our findings and conclude with a discussion of their theoretical and practical implications for operations managers.

2. Literature review

This section analyzes the project front-end literature. For this purpose, we used the Scopus database to analyse the literature, using the keywords ‘front-end’ or ‘initiation’ (as these are the two terms most commonly used interchangeably), and ‘project management’. The search for our keywords was constrained to the articles’ title, abstract or keywords only for articles published from 2009. We did not limit the search to journals from a particular discipline, to allow us to capture diverse views from different literatures, e.g. operations management, strategy management, project management, innovation, and Defence. The articles returned through the search were then carefully examined to identify the most relevant ones to be included in the literature review based on their focus on effective front-end processes in complex projects. Using this approach, we reduced the number of articles from 183 to 32 key references.

2.1. The front-end of complex projects

Projects have become a major part of organisational activity to enhance operations performance (Hall, Kutsch, and Partington Citation2012; Zwikael et al. Citation2022). However, projects have also become increasingly complex to manage, as they are long in duration and are often conducted by multiple organisations (Klakegg, Williams, and Shiferaw Citation2016). Further, Patanakul et al. (Citation2016) analysed the main reasons for the high complexity of government projects and found: (1) they pursue non-financial target goals, (2) they have a long product service life, (3) they deal with multiple stakeholders, (4) they are large in size, (5) they are susceptible to the political environment and dynamics, and (6) they follow a mandated project management process.

The front-end stage of complex projects aims to support an informed investment decision made by the organisation, where a project business case is developed and evaluated before funding for a new project is either granted or rejected. Therefore, the costs associated with the front-end stage are mainly transaction costs, as they are the result of planning the project, rather than the activities related to producing the deliverables from the project (Haaskjold, Andersen, and Langlo Citation2023).

As quality decision-making regarding the selection of a project for funding is a strategic outcome of the front-end process, we follow the well-known decision-making process developed by Mintzberg, Raisinghani, and Theoret (Citation1976) that consists of three steps: (1) Opportunity/problem identification, (2) Solution development, and (3) Selection. In we tailor these three decision-making steps to the context of the project front-end stage (e.g. Williams et al. Citation2019; Zwikael and Smyrk Citation2019).

Table 1. Project front-end steps.

Our analysis in shows that these three decision-making steps can be tailored into the project front-end decision steps proposed in the project management literature. We conclude that as the main objective of the project front-end stage is to make a quality investment decision, this stage could consist of the following four high-level steps: (1) Project trigger identification, where the problem or opportunity that triggers the project is identified, (2) Project idea generation, where the idea to respond to the project trigger is generated, (3) Business case development, where a project business case is developed and packaged for submission and/or presentation to secure approval and funding, and (4) Business case appraisal, where the project is approved and the responsibility for its execution is moved from the operations manager to the project manager. These steps will be discussed in detail next.

2.2. The structure of the front-end of complex projects

Below, we provide a detailed literature analysis of each of the four project front-end steps identified in : (1) Project trigger identification; (2) Project idea generation; (3) Business case development, and (4) Business case appraisal.

2.2.1. Step 1 – Project trigger identification

New projects are triggered by either a problem, such as low customer satisfaction, or an opportunity, such as a new technology (Williams et al. Citation2019). We have named this first step ‘project trigger identification’. According to Williams and Samset (Citation2010), the project trigger should align with the organisation’s strategy. This supports Kock, Heising, and Gemünden (Citation2015) who noted poor alignment between a project and an organisation’s strategy is associated with poor project outcomes. Although Zwikael and Smyrk (Citation2019) note that it is important for a project to be in alignment with organisational strategy, not every project that an organisation chooses to fund will arise from their strategic vision, e.g. a project initiated only to comply with a new industry regulation.

When the trigger for a project and the desired effects are known, it is easier to produce and rank a selection of project ideas, assess alignment between project goals and the organisation’s objectives, and determine the project’s expected value, defined as the ‘net worth of a project to its funding organization and its key stakeholders’ (Zwikael and Huemann Citation2023, 2). Although Hill, Schilling, and Jones (Citation2019) discuss internal and external strategic analysis of the organisation’s operating environment, the literature does not detail how an organisation can effectively identify project triggers. According to Chenger and Woiceshyn (Citation2021) this may be because to identify high-risk and high-reward opportunities, the unknown and highly uncertain needs should be explored. Another reason for this gap in the literature may be the lack of understanding of the implications of an imposed project that is not in alignment with the organisation’s strategy.

2.2.2. Step 2 – Project idea generation

The concept of ‘ideation’ (Kock, Heising, and Gemünden Citation2015) refers to the managerial practices that support the generation of valuable and relevant projects. Triggering excellent project ideas is especially critical in a complex environment as such ideas can enhance the quality of business cases, their evaluation, likelihood of being accepted, and impact on the organisation (Zwikael and Huemann Citation2023). A project idea can emerge ‘from many different quarters such as a prospective funder, a business unit manager, a services department, an employee, an external consultant or even a supplier’ (Zwikael and Smyrk Citation2019, p.194). Knowledge of this important front-end step is lacking in the project management and new product development literatures (Joachim and Spieth Citation2020; Kock, Heising, and Gemünden Citation2015; Pinto and Winch Citation2016). It is necessary to understand the project idea generation process because it has been linked to project failure and initial project ideas have a tendency to persist through the front-end stage irrespective of how poorly conceived they may be (Edkins et al. Citation2013; Kock, Heising, and Gemünden Citation2015; Samset and Volden Citation2016). Finally, this knowledge can help situate the project in its wider context through an understanding of how the project came to be (Pinto and Winch Citation2016).

Another reason that an effective project idea generation step is valuable is the tendency for poor project ideas to receive funding. Sleesman et al. (Citation2012) found escalation of commitment to a losing course of action (such as continued investment in a poor project idea) may occur for several reasons including: project-related reasons, such as opportunity cost; psychological reasons, such as ego threats; social reasons, such as resistance to other’s decisions; and, structural reasons, such as agency problems. As a result, this step raises new ideas for totally different projects. For example, to achieve the outcome of reduced number of car accidents, different projects ideas such as a tunnel, bridge, a traffic light system, and a safety education campaign can be raised.

2.2.3. Step 3 – Business case development

The third step is where the business case (aka a project proposal) is being developed. Project funders use the business case to assess whether a project is worth the investment and the risk (Zwikael and Meredith Citation2019). The business case should align to the organisation’s strategy and objectives (Einhorn, Meredith, and Marnewick Citation2022, 38). It contains information about the expected project deliverables, duration, cost, risks, governance, and benefits. According to Zwikael and Meredith (Citation2018) when setting project benefits in the business case they should have three characteristics: Specificity, e.g. a specific target value; Attainability, e.g. the organisation has the capacity to realise them; and, Comprehensiveness, e.g. they reflect the views of key stakeholders.

2.2.4. Step 4 – Business case appraisal

‘Business case appraisal’ is the last step in the project front-end. When the business case is complete it is given to the potential project funder who considers it and either (1) accepts it and funds the project, (2) returns the business case for further work and resubmission, or (3) rejects the business case. When reviewing a business case, the project funder considers whether the trade-off between risk and return is acceptable, and how the project compares with other project proposals also seeking funding (Zwikael and Smyrk Citation2019). Williams et al. (Citation2019) suggest that while trying to avoid ‘analysis paralysis’, there is a set of analyses and quality assurance activities project funders can engage in before making a final decision regarding the business case. These activities include: (1) Scenario analysis and planning, (2) Real option analysis, (3) Feasibility study, and (4) Concept analysis. Finally, an analysis of the organisation’s internal and external operating environment (Hill, Schilling, and Jones Citation2019) can also be used to evaluate the businesses case.

3. Methods

3.1. Research design

We study the project front-end using qualitative methods. Qualitative methods are particularly appropriate when investigating a research topic, which is relatively new and/or not well understood. We adopt a critical realism ontological perspective whereby an entity can be studied indirectly through the impact it has on other variables rather than being observed directly (Danermark et al. Citation2002; Fleetwood Citation2005). Other researchers have investigated the front-end stage using various qualitative approaches, such as interviews, literature reviews and cases studies (Edkins et al. Citation2013; Samset and Volden Citation2016; Williams et al. Citation2019). This paper uses a different qualitative approach, where we study the front-end process using document and content analysis (Bowen Citation2009). This research design triangulates previous studies and provides rich empirical and reliable data.

3.2. Data collection and analysis

To develop a comprehensive understanding of this complex phenomena, we collected data on the detailed front-end process of complex acquisition and development projects in the Australian government’s Department of Defence (Defence thereafter). We selected Defence acquisition and development projects because they are particularly large and complex, and delivered in a sophisticated project environment. We studied the Defence front-end stage by analysing documents published on the Defence website and suggested to us by Defence members who specialise in this area. Specifically, we examined the following documentation: The First Principles Review (Department of Defence Citation2015), Annual Report 16-17 (Department of Defence Citation2017), Risk Management Framework (Department of Defence Citation2019), Capability Lifecycle Manual (Department of Defence (Australia)), 2020a), Defence Strategic Update (Department of Defence (Australia)) Citation2020b), ID Risk Glossary (Department of Defence Citation2021a), Australian Contingency Context Scenarios (Department of Defence Citation2021b), and the Capability Life Cycle Management Course documents (Ryan and Soutberg Citation2020).

We applied content analysis to each of the documents to gather information about the steps in the front-end stage of a Defence project (Bowen Citation2009). Specifically, we focused on information related to the early stages of Defence capability development as it is most relevant to the project front-end stage. Each of the documents was read and, where required, the Defence language was interpreted using Defence glossaries, which were included in a number of the documents. The information contained in the documents was then organised into categories relating to each of the distinct steps in the lifecycle of a Defence capability. The categories and the linkages between them then formed the basis for this research. We then used a hypothetical illustrative Defence case to present the front-end process in context. Last, the Defence front-end process was compared and contrasted with the four steps retrieved from the literature analysis.

4. Findings

In this section, we analyse each of the steps Defence follows during a project front-end stage. Each of the steps in the Defence front-end process is then linked to the four front-end steps we developed in .

4.1. The front-end stage a Defence project

The Defence front-end stage supports Defence’s strategic objectives, which are to ‘shape Australia’s strategic environment; to deter actions against Australia’s interests; and to respond with credible military force, when required’ (Department of Defence (Australia)) Citation2020b, p.1). The Capability Life Cycle (CLC) is the process used by Defence as the overall framework to link ‘strategic direction, developing concepts, defining requirements, acquisition, introduction into service, sustainment, upgrade and disposal of major capital assets (equipment, facilities and ICT)’ (Department of Defence (Australia)) Citation2020a, 3). There are four stages in the CLC: (1) Strategy and concepts, (2) Risk mitigation and requirements setting, (3) Acquisition, and (4) In-service and disposal. The first two stages form the Defence front-end while the third stage involves project execution, and the fourth stage involves operations. Our analysis of stages 1 and 2 indicates that the Defence front-end commences with a strategy and concepts discussion and concludes once government approval to begin the project has been received. A Defence project is defined as ‘a unique, transient endeavor, undertaken to achieve planned objectives’ (Department of Defence (Australia)) Citation2020a, A-7).

A large Defence project must be approved in three different gates (two gates for smaller project): Gate 0 occurs at the end of the first ‘Strategy and concepts’ stage for Defence Investment Committee approval; Gate 1 occurs in the middle of the second ‘Risk mitigation and requirements setting’ stage for government consideration and guidance (not required for smaller projects); and Gate 2 occurs at the end of the second CLC stage for government approval. If a project exceeds $20 million, it must receive approval from the government to proceed.

The first two stages of the CLC (the front-end of a Defence project) consist of 11 interdependent steps: (1) Identify change, (2) Qualify risk, (3) Prioritise risk, (4) Develop options, (5) Test options, (6) Identify offsets, (7) Test portfolio options, (8) SMART buyer framework, (9) Contestability framework, (10) Risk mitigation and requirements setting, and (11) Additional risk mitigation and requirements setting. The project management literature refers to the Defence term ‘options’ as ‘ideas’ or ‘alternatives’. The first nine steps make up the ‘Strategy and Concepts’ stage of the CLC (stage 1) while steps 10 and 11 constitute the ‘Risk mitigation and requirements setting’ stage of the CLC (stage 2).

Next, we present a summary of the 11 steps included in the Defence front-end process (see Zwikael and Gilchrist Citation2022 for a full description of the Defence front-end process). A hypothetical case labelled the ‘Fighter Aircraft Project’ is also used in to illustrate each step. We have reduced Defence terminology as much as possible and generalised our analysis to ensure our findings and conclusions are applicable to complex projects in the operations environment.

Table 2. The 11 front-end steps of a Defence project.

4.2 A Comparison of the Defence process with the literature

This section compares the front-end process used in Defence with the literature. For this reason, in we map the 11 Defence steps (detailed above) into the four front-end steps we identified in the literature (see ). We further add a description of each step that ‘translates’ the Defence terminology into a language that is more common in the Operations Management discipline.

Table 3. The proposed front-end process for complex projects.

Our analysis in shows that the detailed Defence process is well aligned with the front-end process identified in the literature, though it is more mature and detailed. As a result, the Defence process provides an expansion (e.g. 11 versus four steps) and enrichment of each step in the project front-end literature. For example, Step 1 in the literature calls to identify triggers for a project, whereas the Defence process clarifies how this can be better achieved through a proactive search of the external environment for changes and risks. Further, Defence suggests the project management step of business case development is managed in a portfolio approach where exiting projects are also analysed to see if their cancellation can make room for more attractive projects. The preferred projects then go through a stage-gate approach where their business case is evaluated continuously throughout the front-end process.

5. Discussion

Similar to the strategy formulation process, the front-end of a complex project also ‘commences with the identification of a stimulus for action and ends with the specific commitment to action’ (Mintzberg, Raisinghani, and Theoret Citation1976, 246). However, the literature on the front-end is relatively immature and the process is still considered fuzzy and poorly understood (Chenger and Woiceshyn Citation2021; Williams et al. Citation2019). Research has identified a lack of a structured framework, unclear definition of roles, responsibilities, and steps, and ineffective communication channels as major challenges facing the front-end process (Oh et al. Citation2016). This paper contributes to the operations management literature by mapping the front-end process of complex projects and providing guidance as to which steps could occur and when to ensure the front-end is efficient and effective.

To construct a more structured process for the complex project front-end, this research complemented the literature with lessons learned from the rigorous process of initiating Defence projects. We employed a qualitative investigation to show the front-end stage of complex projects and used an illustrative case to present our findings. Finally, we compared knowledge of the front-end project stage from the operations and project management literatures with the Defence front-end project stage.

5.1. Theoretical contribution

This research enhances the Operations Management literature by developing a comprehensive front-end process for complex projects. The proposed process (see the right-hand column in ) expands each of the four front-end steps identified in the literature: (1) Project trigger identification; (2) Project idea generation, (3) Business case development, and (4) Business case appraisal. To complement these four high-level steps, based on the results of our study. This table identifies specific project activities and quality assurance gates during the front-end stage.

The proposed front-end process for complex projects contributes to the Operations Management literature as it: (1) includes two businesses cases – an initial business case and a detailed business case – rather than one as is discussed in the literature. This allows the operations manager to first test the level of interest with the project idea before resources are devoted for the major and expensive task of developing a detailed business case, (2) includes two approval gates – a conceptual approval gate (following the initial business case) and a funding approval gate (following the detailed business case). This enhanced consideration may improve decision making of approving complex projects and reduce the chance of unnecessary projects being executed, (3) provides a clear process for two front-end steps that are relatively vague in the literature - the project trigger identification process and the project idea generation process. The proposed process also enhances decision-making during the project front-end as it helps to ensure several alternative options are generated and tested, each option is linked to the project trigger, motivated by a qualitative and quantitative understanding of the risk to the operations environment, have been prioritised and their fit within an organisation’s wider project portfolio has been considered, and (4) analyzes the project front-end holistically with relation to the entire organisational portfolio. This contributes to the literature, which often analyzes the project front-end in isolation.

Further, this paper advances the Operations Management literature by identifying triggers for projects and generating effective ideas to enhance the performance of the operations environment. The existing literature states that the front-end of a project is triggered when the project funder identifies a problem or an opportunity (e.g. Zwikael and Smyrk Citation2019). However, how to identify the trigger is unclear in the Operations Management literature. We propose that managers first identify project triggers through an assessment of change in the operations environment. This environment consists of all internal and external inputs, such as changes in strategic direction, technology, industry, and budget, as well as threats and opportunities (Hill, Schilling, and Jones Citation2019). The anticipated effect can then guide the new project idea rather than the present undesired situation (Williams and Samset Citation2010).

The proposed process may also reduce the likelihood of cognitive factors impacting project idea generation, such as bias and political pressure (Flyvbjerg Citation2021) by ensuring the project trigger is well aligned with the operation’s strategic objectives and provides clear evidence of the project’s value. This could support project investment decision quality and therefore, project success and operations performance. In other words, the proposed process views the project-operations interface through the lenses of systems theory, which views an organisation like a mechanical system, where feedback loops seek to optimise performance to a desired equilibrium (Alexander, Walker, and Delabre Citation2022).

Finally, we propose quality assurance checks (Samset and Volden Citation2016), to be conducted by an independent group so linkages between the project trigger, strategic objectives and proposed project solution are clearly defined and evidence based. This may occur before the initial and detailed business cases are submitted for consideration (at Gates 0 and 1 respectively). Whereas the project owner (or champion, if the owner has not yet been appointed) is responsible to lead all the front-end steps, the project funder is the final decision-maker who then approves the business case and thus, the project funding (Zwikael and Meredith Citation2018). As a result, it is crucial these key senior roles possess relevant project management knowledge.

5.2. Practical implications

Not all complex projects can afford a front-end process that is as detailed, lengthy, and expensive as the one conducted by Defence projects. To allow some generalisation of the process we propose in , this section discusses how it can be further simplified and effectively implemented. Therefore, presents several implications on how operations managers can implement the proposed model effectively in other contexts of complex projects executed in an operations environment. This table provides the front-end steps, limitations in operations practice associated with each step, and implications of the proposed front-end process for operations managers.

Table 4. Practical implications for operations managers.

The proposed front-end process can also advance practice by reducing cases where the most obvious solution (which is not necessarily the best solution) is hastily selected for a project. For example, if usage is exceeding capacity, the most obvious solution is to initiate a project to increase the capacity (e.g. build a new manufacturing line). The proposed front-end process supports linkages between the trigger for the project, strategic objectives, and the approved project. Specifically, these linkages are supported by following a defined process that ensures each step of a project’s development is logically connected to the preceding ones. This ensures the solution can be directly linked to the problem and operations objectives, which will support regular assessment of its suitability as the project matures and evolves. In addition, the process also includes a step for the development of alternative project ideas. Options can then be explored by a group of experts with project management knowledge, and a firm understanding of the organisation’s project portfolio and its operations objectives, as well as the broader political and financial landscape.

6. Conclusion

Literature agrees that an effective front-end stage leads to better project selection, improved project success and enhanced operations performance (e.g. Kolltveit, Karlsen, and Grønhaug Citation2004; Morris Citation2013; Pinto and Winch Citation2016; Testorelli, Ferreira de Araújo Lima, and Verbano Citation2022; Williams et al. Citation2019; Zwikael and Smyrk Citation2019). However, the front-end stage in complex projects is still viewed as unclear or ‘fuzzy’. Therefore, little is known in the literature about the process operations managers can follow when proposing complex projects to achieve their objectives.

To address this research gap, we conducted a qualitative study into the front-end of Defence projects in the Australian government. We used an illustrative case to present our findings and compared the Defence project front-end with the literature to enhance research knowledge in this area. We presented a front-end process, as well as implications for practice when initiating complex projects.

This research contributes to operations management knowledge by detailing how an effective front-end stage can be constructed by considering the context that the complex project has been ‘idealized, validated, and shaped’ within (Pinto and Winch Citation2016, 238). In particular, the paper integrates the concept of ‘ideation’ - the managerial practices that support the generation of valuable and relevant ideas (Kock, Heising, and Gemünden Citation2015) - into the front-end stage of complex projects. Triggering excellent project ideas can then enhance the quality of business cases, their evaluation, likelihood of being accepted and contribution to the organisation. Pending validation, our research can assist with the reduction of the following: (1) uncertainty and complexity that are typically associated with the front-end stage of projects (Kolltveit, Karlsen, and Grønhaug Citation2004); (2) unnecessary investment of time and resources; and (3) the risk of overlooking the front-end completely and instead locking in early to a project that may not be the best project (Kolltveit, Karlsen, and Grønhaug Citation2004; Morgan Citation1987). This contribution is valuable as an effective front-end process typically enhances project success and hence operations performance (Zwikael and Meredith Citation2018).

Finally, limitations of this research include the generalisation of learnings from Defence projects to other types of complex projects that may not have the same amount of resources to invest in a lengthy and expensive front-end process. Whereas we acknowledge that the proposed structured process may be more attractive for large-scale projects where the front-end stage can take months, the proposed process can be tailored and simplified as required. Future research can further develop a simplified front-end process for small-scale complex projects that do not require such a comprehensive process, for example they may have only one business case and quality assurance gate rather than the two proposed in our proposed process. Our research design is limited by a reliance on document analysis as a single method of data collection. We recommend future researchers involving the front-end process also draw on additional methods of data collection to triangulate and strengthen their findings. Last, this research provides opportunities for further research integrating the front-end of projects with operations management, as well as the ‘back-end’ of projects. For example, research on project handover to operations can also enhance project implementation and the positive impact operations management can make on the operations environment.

Disclosure statement

No potential conflict of interest was reported by the author(s).

Additional information

Notes on contributors

Ofer Zwikael

Ofer Zwikael is a Professor of Project Management at the Australian National University. His five books and more than 250 scholarly peer-reviewed papers have been recognised through research awards from the Academy of Management, British Academy of Management, Project Management Institute, International Project Management Association, Emerald, and the Australian Institute of Project Management. Professor Zwikael was named by Stanford University and Elsevier to be among the top 2% of international scientists in Business and Management. His research on project benefits management has been funded by major organisations, including the Australian Department of Defence and the Project Management Institute (US). He has held leadership roles including Head of School and Associate Dean and is currently an Associate Editor for the International Journal of Project Management.

Alicia Gilchrist

Alicia Gilchrist is a Lecturer of Project Management at the Australian National University. Her research areas include social alignment, stakeholder relationships and the project front-end. Dr Gilchrist has published in leading journals, including the International Journal of Project Management and Communications of the ACM. Alicia has also held registration as a psychologist.

References

  • Alexander, A., H. Walker, and I. Delabre. 2022. “A Decision Theory Perspective on Wicked Problems, SDGs and Stakeholders: The Case of Deforestation.” Journal of Business Ethics 180 (4): 975–995. https://doi.org/10.1007/s10551-022-05198-8
  • Alimadadi, S. 2022. “A Pragmatist Perspective on Front-End Project Organizing: The Case of Refurbishment of the Palace of Westminster.” International Journal of Project Management 40 (7): 763–777. https://doi.org/10.1016/j.ijproman.2022.08.008
  • Bowen, G. A. 2009. “Document Analysis as a Qualitative Research Method.” Qualitative Research Journal 9 (2): 27–40. https://doi.org/10.3316/QRJ0902027
  • Chenger, D., and J. Woiceshyn. 2021. “Executives’ Decision Processes at the Front End of Major Projects: The Role of Context and Experience in Value Creation.” Project Management Journal 52 (2): 176–191. https://doi.org/10.1177/8756972820977225
  • Christensen, C. M. 2013. The Innovator’s Dilemma: When New Technologies Cause Great Firms to Fail. Boston, MA: Harvard Business Review Press.
  • Cook, S. C., and M. H. Unewisse. 2020. “A Capability Engineering Lifecycle Framework Based on Insights from Australian Defence.” INCOSE International Symposium 30 (1): 886–901. https://doi.org/10.1002/j.2334-5837.2020.00761.x
  • Danermark, B., M. Ekström, L. Jakobsen, and J. C. Karlsson. 2002. Explaining Society: Critical Realism in the Social Sciences. London: Routledge.
  • Department of Defence. 2015. First Principles Review. Retrieved February 25, 2021, from https://www.defence.gov.au/publications/reviews/firstprinciples/Docs/FirstPrinciplesReviewB.pdf
  • Department of Defence. 2017. Annual Report 16-17. Retrieved March 22, 2021, from https://www.defence.gov.au/annualreports/16-17/Downloads/DAR_2016-17_Complete.pdf
  • Department of Defence. 2019. Risk Management Framework. Retrieved March 22, 2021, from https://defence.gov.au/estatemanagement/governance/Risk/docs/SDD%20Risk%20Management%20Framework.pdf
  • Department of Defence (Australia). 2020a. Capability Lifecycle Manual (Version 2.0). Available from: https://www.dica.org.au/wp-content/uploads/2020/10/Capability-Life-Cycle-Manual-v2-1.pdf
  • Department of Defence (Australia). 2020b. Defence Strategic Update. Available from: https://www.defence.gov.au/about/strategic-planning/2020-defence-strategic-update#main-content
  • Department of Defence. 2021a. ID Risk Glossary. Retrieved March 22, 2021, from https://www.defence.gov.au/estatemanagement/Governance/Risk/Tools.asp
  • Department of Defence. 2021b. Australian Contingency Context Scenarios. Retrieved March 27, 2021, from https://www.dst.defence.gov.au/projects/australian-contingency-context-scenarios
  • Edkins, A., J. Geraldi, P. Morris, and A. Smith. 2013. “Exploring the Front End of Project Management.” Engineering Project Organization Journal 3 (2): 71–85. https://doi.org/10.1080/21573727.2013.775942
  • Einhorn, F. D., J. Meredith, and C. Marnewick. 2022. “A Model to Guide the Effective Use of a Business Case for IT Projects.” International Journal of Managing Projects in Business 15 (1): 36–57. https://doi.org/10.1108/IJMPB-03-2021-0076
  • Fleetwood, S. 2005. “Ontology in Organization and Management Studies: A Critical Realist Perspective.” Organization 12 (2): 197–222. https://doi.org/10.1177/1350508405051188
  • Flyvbjerg, B. 2021. “Top Ten Behavioural Biases in Project Management: An Overview.” Project Management Journal 52 (6): 531–546. https://doi.org/10.1177/87569728211049046
  • Haaskjold, H., B. Andersen, and J. A. Langlo. 2023. “Dissecting the Project Anatomy: Understanding the Cost of Managing Construction Projects.” Production Planning & Control 34 (2): 117–138. https://doi.org/10.1080/09537287.2021.1891480
  • Hall, M., E. Kutsch, and D. Partington. 2012. “Removing the Cultural and Managerial Barriers in Project-to-Project Learning: A Case from the UK Public Sector.” Public Administration 90 (3): 664–684. https://doi.org/10.1111/j.1467-9299.2011.01980.x
  • Hill, C. W., M. A. Schilling, and G. R. Jones. 2019. Strategic Management: Theory and Cases: An Integrated Approach. 13th ed. Mason, OH: Cengage Learning.
  • Joachim, V., and P. Spieth. 2020. “What Does Front-End Research Build on? A Cocitation Analysis of the Intellectual Background and Potential Future Research Avenues.” IEEE Transactions on Engineering Management 67 (1): 105–121. https://doi.org/10.1109/TEM.2018.2865496
  • Ju, C., and Y. Ning. 2023. “Time Pressure and Coordinating Project Design in Inter-Functional Teams: A Configurational Approach.” Production Planning & Control 34 (4): 391–402. https://doi.org/10.1080/09537287.2021.1926567
  • Kenny, J. 2003. “Effective Project Management for Strategic Innovation and Change in an Organizational Context.” Project Management Journal 34 (1): 43–53. https://doi.org/10.1177/875697280303400106
  • Klakegg, O. J., T. Williams, and A. T. Shiferaw. 2016. “Taming the ‘Trolls’: Major Public Projects in the Making.” International Journal of Project Management 34 (2): 282–296. https://doi.org/10.1016/j.ijproman.2015.03.008
  • Kock, A., W. Heising, and H. G. Gemünden. 2015. “How Ideation Portfolio Management Influences Front‐End Success.” Journal of Product Innovation Management 32 (4): 539–555. https://doi.org/10.1111/jpim.12217
  • Kolltveit, B. J., J. T. Karlsen, and K. Grønhaug. 2004. “Exploiting Opportunities in Uncertainty during the Early Project Stage.” Journal of Management in Engineering 20 (4): 134–140. https://doi.org/10.1061/(ASCE)0742-597X(2004)20:4(134)
  • Liedtka, J., and G. Locatelli. 2023. “Humanising Complex Projects through Design Thinking and Its Effects.” International Journal of Project Management 41 (4): 102483. https://doi.org/10.1016/j.ijproman.2023.102483
  • March, J. G., and H. A. Simon. 1958. Organizations. New York: Wiley.
  • McDonald, B. 2017. Measuring the Fiscal Health of Municipalities. Cambridge, MA: Lincoln Institute of Land Policy.
  • Mintzberg, H., D. Raisinghani, and A. Theoret. 1976. “The Structure of" Unstructured" Decision Processes.” Administrative Science Quarterly 21 (2): 246–275. https://doi.org/10.2307/2392045
  • Mitchell, D. 2018. “To Monitor or Intervene? City Managers and the Implementation of Strategic Initiatives.” Public Administration 96 (1): 200–217. https://doi.org/10.1111/padm.12381
  • Morgan, B. V. 1987. “Benefits of Project Management at the Front End.” International Journal of Project Management 5 (2): 102–119. https://doi.org/10.1016/0263-7863(87)90036-6
  • Morris, P. W. G. 2013. Reconstructing Project Management. Chichester: Wiley-Blackwell.
  • Oh, E. H., N. Naderpajouh, M. Hastak, and S. Gokhale. 2016. “Integration of the Construction Knowledge and Expertise in Front End Planning.” Journal of Construction Engineering and Management 142 (2): 04015067. https://doi.org/10.1061/(ASCE)CO.1943-7862.0001050
  • Ojiako, U., Y. Petro, A. Marshall, and T. Williams. 2023. “The Impact of Project Portfolio Management Practices on the Relationship between Organizational Ambidexterity and Project Performance Success.” Production Planning & Control 34 (3): 260–274. https://doi.org/10.1080/09537287.2021.1909168
  • Patanakul, P., Y. H. Kwak, O. Zwikael, and M. Liu. 2016. “What Impacts the Performance of Large-Scale Government Projects?” International Journal of Project Management 34 (3): 452–466. https://doi.org/10.1016/j.ijproman.2015.12.001
  • Pinto, J. K., and G. Winch. 2016. “The Unsettling of “Settled Science:” the past and Future of the Management of Projects.” International Journal of Project Management 34 (2): 237–245. https://doi.org/10.1016/j.ijproman.2015.07.011
  • Reilly, O., and M. L. Tushman. 2004. “The Ambidextrous Organization.” Harvard Business Review 82 (4): 74–83.
  • Ryan, M., and S. Soutberg. 2020. Capability Life Cycle (CLC) Management. UNSW. Retrieved March 27, 2021 from https://www.unsw.adfa.edu.au/conferences/sites/conferences/files/uploads/CLC%20Course%202020–6-a-side.pdf
  • Samset, K., and G. H. Volden. 2016. “Front-End Definition of Projects: Ten Paradoxes and Some Reflections regarding Project Management and Project Governance.” International Journal of Project Management 34 (2): 297–313. https://doi.org/10.1016/j.ijproman.2015.01.014
  • Sleesman, D. J., D. E. Conlon, G. McNamara, and J. E. Miles. 2012. “Cleaning up the Big Muddy: A Meta-Analytic Review of the Determinants of Escalation of Commitment.” Academy of Management Journal 55 (3): 541–562. https://doi.org/10.5465/amj.2010.0696
  • Testorelli, R., Priscila Ferreira de Araújo Lima, and C. Verbano. 2022. “Fostering Project Risk Management in SMEs: An Emergent Framework from a Literature Review.” Production Planning & Control 33 (13): 1304–1318. https://doi.org/10.1080/09537287.2020.1859633
  • Williams, T., and K. Samset. 2010. “Issues in Front-End Decision-Making on Projects.” Project Management Journal 41 (2): 38–49. https://doi.org/10.1002/pmj.20160
  • Williams, T., H. Vo, K. Samset, and A. Edkins. 2019. “The Front End of Projects: A Systematic Literature Review and Structuring.” Production Planning & Control 30 (14): 1137–1169. https://doi.org/10.1080/09537287.2019.1594429
  • Xiong, W., N. Zhong, F. Wang, M. Zhang, and B. Chen. 2022. “Political Opportunism and Transaction Costs in Contractual Choice of Public–Private Partnerships.” Public Administration 100 (4): 1125–1144. https://doi.org/10.1111/padm.12760
  • Zwikael, O., and A. Gilchrist. 2022. “The Logic of the Project Front-End.” In The Front-End of Large Public Projects, edited by T. Williams, K. Samset, & G. Volden, 43–68. New York: Routledge.
  • Zwikael, O., and J. R. Meredith. 2018. “Who’s Who in the Project Zoo? The Ten Core Project Roles.” International Journal of Operations & Production Management 38 (2): 474–492. https://doi.org/10.1108/IJOPM-05-2017-0274
  • Zwikael, O., and J. R. Meredith. 2019. “Effective Organizational Support Practices for Setting Target Benefits in the Project Front End.” International Journal of Project Management 37 (7): 930–939. https://doi.org/10.1016/j.ijproman.2019.08.001
  • Zwikael, O., and J. R. Smyrk. 2019. Project Management: A Benefit Realisation Approach. Cham: Springer.
  • Zwikael, O., R. D. Pathak, F. Ling, S. Titov, Z. Husain, L. Yang, B. Sharma, C. Y. Tay, and D. Samson. 2022. “Variation in Project Management Practices across Borders.” Production Planning & Control 33 (13): 1270–1282. https://doi.org/10.1080/09537287.2020.1858362
  • Zwikael, O., and M. Huemann. 2023. “Project Benefits Management: Making an Impact on Organizations and Society through Projects and Programs.” International Journal of Project Management 41 (8): 102538. https://doi.org/10.1016/j.ijproman.2023.102538