A dispatching algorithm for parallel machines with rework processes

, &
Pages 144-155 | Received 01 Apr 2008, Accepted 01 Sep 2008, Published online: 21 Dec 2017
 

Abstract

This paper presents a parallel machine scheduling problem with rework probabilities, due-dates and sequence-dependent setup times. It is assumed that rework probability for each job on a machine can be given through historical data acquisition. Since the problem is NP-hard in the strong sense, a heuristic algorithm is presented, which finds good solutions. The dispatching algorithm named MRPD (minimum rework probability with due-dates) is proposed in this paper focusing on the rework processes. The performance of MRPD is measured by the six diagnostic indicators: total tardiness, maximum lateness, mean flow-time, mean lateness, the number of reworks and the number of tardy jobs. A large number of test problems are randomly generated to evaluate the performance of the proposed algorithm. Computational results show that the proposed algorithm is significantly superior to existing dispatching algorithms for the test problems.

Reprints and Corporate Permissions

Please note: Selecting permissions does not provide access to the full text of the article, please see our help page How do I view content?

To request a reprint or corporate permissions for this article, please click on the relevant link below:

Academic Permissions

Please note: Selecting permissions does not provide access to the full text of the article, please see our help page How do I view content?

Obtain permissions instantly via Rightslink by clicking on the button below:

If you are unable to obtain permissions via Rightslink, please complete and submit this Permissions form. For more information, please visit our Permissions help page.