Permutation flow shops with exact time lags to minimise maximum lateness

, , &
Pages 6759-6775 | Received 06 Sep 2007, Accepted 21 Feb 2008, Published online: 13 Oct 2009
 

Abstract

In this paper we investigate the m-machine permutation flow shop scheduling problem where exact time lags are defined between consecutive operations of every job. This generic model can be used for the study and analysis of various real situations that may arise, for instance, in the food-producing, pharmaceutical and steel industries. The objective is to minimise the maximum lateness. We study polynomial special cases and provide a dominance relation. We derive lower and upper bounds that are integrated in a branch-and-bound procedure to solve the problem. Three branching schemes are proposed and compared. We perform a computational analysis to evaluate the efficiency of the developed method.

Acknowledgement

The authors would like to thank the anonymous referees for their valuable comments that helped to improve the quality of this paper.

Reprints and Corporate Permissions

Please note: Selecting permissions does not provide access to the full text of the article, please see our help page How do I view content?

To request a reprint or corporate permissions for this article, please click on the relevant link below:

Academic Permissions

Please note: Selecting permissions does not provide access to the full text of the article, please see our help page How do I view content?

Obtain permissions instantly via Rightslink by clicking on the button below:

If you are unable to obtain permissions via Rightslink, please complete and submit this Permissions form. For more information, please visit our Permissions help page.