Scheduling on a proportionate flowshop to minimise total late work

, ORCID Icon &
Pages 531-543 | Received 05 Feb 2017, Accepted 09 Mar 2018, Published online: 03 Apr 2018
 

Abstract

We study a scheduling problem to minimise total late work, i.e. each job is penalised according to the duration of its parts scheduled after its due-date. The machine setting is an m-machine proportionate flow shop. Two versions of the problem are studied: (i) the case that total late work refers to the last operation of the job (i.e. the operation performed on the last machine of the flow shop); (ii) the case that total late work refers to all the operations (on all machines). Both versions are known to be NP-hard. We prove a crucial property of an optimal schedule, and consequently introduce efficient pseudo-polynomial dynamic programming algorithms for the two versions. The dynamic programming algorithms are tested numerically and proved to perform well on large size instances.

Additional information

Funding

This work was supported by the Israel Science Foundation [grant number 1286/14].

Reprints and Corporate Permissions

Please note: Selecting permissions does not provide access to the full text of the article, please see our help page How do I view content?

To request a reprint or corporate permissions for this article, please click on the relevant link below:

Academic Permissions

Please note: Selecting permissions does not provide access to the full text of the article, please see our help page How do I view content?

Obtain permissions instantly via Rightslink by clicking on the button below:

If you are unable to obtain permissions via Rightslink, please complete and submit this Permissions form. For more information, please visit our Permissions help page.