Heuristics for resource-constrained schedulingFootnote

&
Pages 299-310 | Received 01 Jan 1985, Published online: 22 Oct 2007
 

SUMMARY

In this paper we present two heuristics (TIMROS and TIMGEN) for allocating resources to activities of projects under single-resource constraints. The heuristics are based on criteria which utilize the duration and resources required for each activity. Allocation of resources is then performed according to the priority ranking of the activities with respect to the developed criteria.

†This research was conducted while Nasr was at Rutgers.

Notes

†This research was conducted while Nasr was at Rutgers.

Reprints and Corporate Permissions

Please note: Selecting permissions does not provide access to the full text of the article, please see our help page How do I view content?

To request a reprint or corporate permissions for this article, please click on the relevant link below:

Academic Permissions

Please note: Selecting permissions does not provide access to the full text of the article, please see our help page How do I view content?

Obtain permissions instantly via Rightslink by clicking on the button below:

If you are unable to obtain permissions via Rightslink, please complete and submit this Permissions form. For more information, please visit our Permissions help page.