A practical approach to the re-estimation of the economic internal rate of return of agricultural projects in project completion reports

&
Pages 91-94 | Published online: 17 Feb 2012
 

Abstract

Techniques for re-estimating the economic internal rate of return of agricultural projects in Project Completion Reports are not well known. Firstly a base year for the re-estimation must be selected. Project cost andrevenue streams fallinto historical and projected data. For economic analysis, and to eliminate the effects of devaluation, historical data should be recalculated into current US dollar terms, using shadow exchange rates. The data may then be changed into constant base year terms using appropriate indices.

Projected costs are calculated in constant base year US dollars using a shadow exchange rate. The projected revenue stream should be calculated in current US dollars, the values being changed into constant base year terms using an appropriate index. Ignoring terminal values the historical and projected parts of the net benefit stream may be combined to derive the economic internal rate of return.

Reprints and Corporate Permissions

Please note: Selecting permissions does not provide access to the full text of the article, please see our help page How do I view content?

To request a reprint or corporate permissions for this article, please click on the relevant link below:

Academic Permissions

Please note: Selecting permissions does not provide access to the full text of the article, please see our help page How do I view content?

Obtain permissions instantly via Rightslink by clicking on the button below:

If you are unable to obtain permissions via Rightslink, please complete and submit this Permissions form. For more information, please visit our Permissions help page.