1,897
Views
14
CrossRef citations to date
0
Altmetric
Special Issue: Health in impact Assessment

Investigating the effectiveness of mandatory integration of health impact assessment within environmental impact assessment (EIA): a case study of Thailand

&
Pages 16-31 | Received 01 Dec 2016, Accepted 05 May 2017, Published online: 06 Nov 2017

Abstract

The effectiveness of the integration of health impact assessment (HIA) and environmental impact assessment (creating an environmental and health impact assessment’ (EHIA) process) is investigated, drawing on an example of a mandatory requirement in the power plant project sector in Thailand. The analytical framework is based on that outlined in by the authors in 2013, focusing on procedural, substantive, transactive and normative effectiveness criteria, and the evaluation served also to critique this framework in practice. Using documentary analysis and interviews, it was found that a sample of EHIAs are partially effective from the four perspectives of effectiveness. The findings suggest that integrating HIA and EIA still has a long way to go to achieve effective practice. Insufficient resources have been allocated to deliver the level of public participation expected in the regulations, or a sufficient standard of EHIA practice and monitoring. The existing analytical framework was found to be inadequate for transactive effectiveness, and a new criterion added: T5Availability of human resource in EHIA practice. Recommendations are provided to support the practical integration of HIA into EIA practice in Thailand.

1. Introduction

Health impact assessment has been mandatorily integrated into the environmental impact assessment (EIA) process in Thailand since 2009 (Ministry of Natural Resources and Environment Citation2009). The term ‘environmental and health impact assessment (EHIA)’ has been used in the Thai context since 11 project types were listed as being subject to EHIA (Ministry of Natural Resources and Environment Citation2010a, 2010b), before rising to 12 project types in 2015 (Ministry of Natural Resources and Environment Citation2015). Of these, thermal power plant project developments are one of the project types that have required EHIA.

The HIA concept was firstly introduced in Thailand in 2001 by the Health System Research Institute (HSRI) (Phoolcharoen et al. Citation2003), and then it was added to the National Health Act B.E.2550 (2007). It was still considered a new tool in the Thai context, particularly to EIA practitioners and authorities, when EHIA was first implemented legally in Thailand in 2009 (Ministry of Industry Citation2009; Ministry of Natural Resources and Environment Citation2009). Accordingly, it was suggested that more knowledge and understanding in HIA practice should be developed among relevant stakeholders and practitioners (Chanchitpricha Citation2012).

Siwaraksa et al. (Citation2004) had previously raised concerns that there are shortcomings in the ability of some authorities to implement HIA requirements, and an absence of strategy for resolving this. It is considered challenging to include health in EIA as it connects with a broader set of skills among actors and authorities (Harris and Haigh Citation2015). A common knowledge base among relevant institutions is also a crucial success factor for integrating HIA in impact assessment (Morgan Citation2011; Carmichael et al. Citation2012). Terminology is used inconsistently in existing literature, where ‘health in EIA’, ‘HIA in IA’ and ‘HIA in EIA’ are often used interchangeably. We regard HIA and EIA as being separate processes, and EHIA to represent a process where the scope of assessment is expanded to include health as well as the environment. The advent of EHIA as a new process implemented as part of decision-making processes thus requires the development of appropriate capacity to implement the statutory obligations. Therefore, in order to shed light on how well and how effectively EHIA has been implemented in the Thai context, this paper examines the procedural, substantive, transactive and normative effectiveness of the first four completed EHIAs of power plant projects developed by the Electricity Generating Authority of Thailand (EGAT).

2. Effectiveness perspectives in impact assessment (IA) practice

Defining the effectiveness of impact assessment practice is problematic given it varies by context (Chanchitpricha Citation2012). Identifying effectiveness categories is considered a practical means of breaking down our understanding of effectiveness into measurable components (Theophilou et al. Citation2010). When the effectiveness of environmental assessment was first investigated systematically, Sadler (Citation1996) classified it into three dimensions: procedural; substantive; and transactive effectiveness. Later on, a normative aspect was added by Baker and McLelland (Citation2003); an approach subsequently supported by other scholars in this area (e.g. Cashmore et al. Citation2004; Bina Citation2007; Arts et al. Citation2012; Bond and Morrison-Saunders Citation2013; Chanchitpricha and Bond Citation2013) as a result of an understanding that changes in context, i.e. organisations, philosophy and culture, lead to changes in attitudes/decision-making/norms when implementing IA tools.

Chanchitpricha and Bond (Citation2013) synthesised an evaluation framework from the literature encompassing procedural, substantive, transactive and normative aspects with a set of criteria for each category. After initial testing on a single case study (Chanchitpricha Citation2012), they suggested broader testing of IA practice in different contexts to further refine the framework, a task already started through a minor amendment (Chanchitpricha and Bond Citation2015). This paper is a contribution to that broader testing.

The four effectiveness categories are:

  • Procedural effectiveness of IA is considered based on principles, procedures and robustness of information applied and provided in the IA process (Sadler Citation1996; Bina Citation2007; Therivel Citation2010).

  • Substantive effectiveness is achieved when the implementation of an IA tool leads to changes or adjustments of the proposed plan or project (Sadler Citation1996; Baker and McLelland Citation2003; Christensen et al. Citation2005; Theophilou et al. Citation2010; Arts et al. Citation2012; Phylip-Jones and Fischer Citation2013).

  • Transactive effectiveness is achieved where resources, e.g. cost, time, human resource skills, are invested efficiently in IA practice (Sadler Citation1996; Theophilou et al. Citation2010).

  • Normative effectiveness is achieved where the outcome meets attitudes/individual expectations through application of IA processes (van Buuren and Nooteboom Citation2009; Stoeglehner et al. Citation2009).

The effectiveness framework criteria adapted for this research are presented in Section 4.2.

3. Legal requirements for EHIA of power plants in Thailand

The decision-making process involving EHIA in Thailand was promulgated by the notification of the Ministry of Natural Resource and Environment (Citation2009) which lead to legislation that approval from the government cabinet will be required for any project development conducted by the government, or government authority cooperating with the private sector. Power plant developments requiring EHIA in Thailand are listed in Table separated into categories dependent on fuel source.

Table 1. Power plant project development mandatorily requiring EHIA in Thailand.

The Electricity Generating Authority of Thailand (EGAT) is controlled by the Ministry of Energy, and has a power generation capacity of approximately 15,500 MW (as of December 2015) (EGAT Citation2017). Any power plant project developed by EGAT requiring EHIA would require a final decision to be made by the government cabinet. The involved authorities and parties to the EHIA practice as well as decision-making process are: project developer (EGAT), EHIA practitioner (licenced consultant), Office of Natural Resources and Environment (ONEP), expert panel (appointed by ONEP), Independent Commission on Environment and Health (ICEH), regulator authority (Energy Regulatory Commission: ERC), National Environment Board (NEB) and other relevant local authorities i.e. health organisations, experts, the public and the government cabinet. Figure demonstrates the connection between EHIA practice, public participation processes and the decision-making process of relevant authorities/panels which set the context for this study. Apart from the Natural Resource and Environment Ministerial Notification (2009), the regulation of the Prime Minister’s Office on public consultation B.E. 2548 is also applied as a public participation guideline in the EHIA process (Public Service Centre: Office of the Permanent Secretary Citation2009, p. 17), and ICEH’s role is defined by The Prime Minister’s Office regulation (Citation2010).

Figure 1. Decision-making flows of EHIA approval and project development for power plant projects proposed by Electricity Generation Authority of Thailand (EGAT).

Source: adapted based on Natural Resource and Environment Ministerial Notification (2009), Office of Natural Resources and Environment Policy and Planning (Citation2013, p. 45) and The Prime Minister’s Office (Citation2010).
Figure 1. Decision-making flows of EHIA approval and project development for power plant projects proposed by Electricity Generation Authority of Thailand (EGAT).

Public participation processes are particularly frequent in EHIA practice. The regulation and guideline (Environmental Impact Evaluation Bureau: Office of Natural Resources and Environment Policy and Planning (ONEP) Citation2014) requires public participation at the scoping, impact assessment and at the draft EHIA report review stages. The guideline indicates that a public meeting should be conducted for at least 2 h during EHIA scoping as PP1; a public opinion survey is required during the impact assessment stage (PP2) via one or more of: interview, focus group, workshop, stakeholder representative meeting or remote communication i.e. telephone, post, email and the Internet. Finally, a public meeting is required for the draft EHIA report review as PP3.

Referring to Figure , after submission to ONEP, if the expert panel approves the EHIA, they summarise the key issues and communicate them to the Independent Commission on Environment and Health (ICEH) (The Prime Minister’s Office Citation2010) and the regulator, the Energy Regulatory Commission (ERC), for power plant projects. At this stage, ICEH publishes the EHIA online via its website informing the general public that are interested in taking part in a public consultation of advisory comments provided by the committee. This is public participation stage PP4. The public comments are subsequently summarised and communicated to ERC and ONEP. This is not directly compulsory as written in The Prime Minister’s Office (Citation2010), but ICEH conducts PP4 in line with its own internal procedures.

Additionally, the regulator (ERC) must conduct public consultation (PP5) according to the legal regulation on EHIA practice (Ministry of Natural Resources and Environment Citation2009) as presented in Figure prior to providing comments for ONEP. Comments from both ICEH and ERC are collected and summarised by ONEP for the National Environment Board (NEB). NEB then synthesise the relevant findings from the IA process and provide additional opinion to the government cabinet which makes the final decision where the project developer is state-owned. For power plant projects developed by the private sector, approval and a licence permit is granted, if appropriate, by the regulator (ERC). In these cases the PP4 and PP5 summary reports conducted by ICEH and ERC, respectively, are posted online via the authority websites.

As of May 2017, four completed EHIA reports submitted by EGAT have been published online (Table ). The first two power plant EHIAs in the table were previously assessed for procedural effectiveness in Chanchitpricha and Bond (Citation2015). Prior to the implementation of EHIA as a legal requirement in 2010, the EIA reports of the two power plants (Nos. 1 & 2) were already approved by decision-makers. However, as the projects spanned the period between changing legal regulations and approval of their EIAs, the project developers were advised to conduct EHIA additionally. This meant that the final decision-making process leading to EHIA approval, for Case Nos. 1 & 2, was different to that in the subsequent cases developed by EGAT. As such, the reports for Case Nos. 1 & 2 were proposed for approval by ERC instead of NEB and the government cabinet (SECOT Co.ltd Citation2013; Team Consulting Engineering and Management Co. Ltd Citation2014).

Table 2. Completed EGAT EHIAs approved by ONEP and processed by ICEH and regulator (ERC).

4. Methodology and effectiveness analytical framework

4.1. Research design and methods

A qualitative research methodology is applied in order to evaluate the effectiveness of this decision-making tool. A qualitative approach can lead to increased understanding based on data collection via analysing words, documents and points of views (Chadwick et al. Citation1984; Denzin and Lincoln Citation2000; Creswell Citation2007).

The scope of EHIA to be investigated in this paper draws on a sample of four completed EHIAs (see Table ) of power plant projects developed by the Electricity Generating Authority of Thailand (EGAT) out of the total population of six EHIA reports, approved by the statutory consultation authority (Office of Environmental Policy and Planning: ONEP).

4.1.1. Accessibility of EIA and EHIA information in Thailand

In terms of power plant project development, completed EHIA reports, approved by the ONEP expert panel between 2011 and 2016, are provided for public accessibility on ICEH’s website (www.iceh.or.th/v1) and ERC’s website (app04.erc.or.th/EHIA/) (as of May 2017). The EHIA project status is updated on ERC’s website as well as ONEP’s website. The public provision of EIA and EHIA reports online helps meet the rights of public access to information as specified in Thailand’s Official Information Act B.E. 2540 (1997). However, it was noted that collaboration between key relevant authorities could have been improved in terms of sharing information as EHIA resources (NGO #1); this is because some stakeholders have limited access to the Internet. Appropriate communication and ways of delivering information should be compatible with the audience (Reg #1, NGO #1).

As presented in Table , data collection was conducted based on documentary reviews (16 reports) along with purposive sampling of key informants, drawn from the stakeholders of power plant project development, for in-depth interviews, prior to thematic analysis facilitating triangulation of sources (Miles and Huberman Citation1994; Maxwell Citation2005; Creswell Citation2007).

Table 3. Relevant documents of the four power plant EHIA cases and key informants as sources of data collected in this study.

4.1.2. Interviewed key informants

The response for the invitations to be interviewed was generally very positive, albeit there were some inevitable challenges associated with postponements or a lack of response. Letters requesting the interviews were officially delivered to 17 authorities/key informants using a purposive sampling method based upon their roles in the four cases. Responses were obtained from the project developer (EGAT), EHIA practitioners, environment and health authorities (ONEP and Department of Health), independent organisation (ICEH), Non-governmental organisations (NGO) and the regulator (ERC) as presented in Table .

Table 4. Key informants having been involved with power plant EHIA cases contacted and interviewed.

All key informants responded based on their involvement in the 4 case studies, except for the consultants who either continually postponed, did not respond or failed to find time to agree transcripts as required under the ethical procedure. As a result, as a surrogate viewpoint, four practitioners who have been involved in other EHIA cases (Practitioner #1, #2, #3, #4) were interviewed to get their general views on the process. This remains one area of weakness in the approach, but one that could not be avoided. Table indicates the interview process and lists the successful interview numbers.

4.2. Effectiveness framework

The analytical framework on EHIA effectiveness in this study (see Table ) relies on Chanchitpricha and Bond (Citation2013) as amended by Chanchitpricha and Bond (Citation2015).

Table 5. EHIA effectiveness analytical framework.

5. Effectiveness of power plant EHIA

5.1. Procedural effectiveness

Although the four EGAT EHIAs have been approved by the statutory authorities and considered to have achieved procedural effectiveness based on documentary analysis; it was found that not all the EHIA cases of power plant projects fully meet the procedural criteria when interview findings are taken into account. Overall, the four EHIAs meet five procedural effectiveness criteria (P1, P3, P4, P5 and P7), whereas Cases 2 & 3 partially meet P2 and P6, Case 1 partially meets P6 and does not achieve P8, while Case 4 partially meets P6 (Table ).

Table 6. Effectiveness overview of power plant EHIAs based on documentary analysis and interviews.

The findings suggest that the relevant policy framework and procedures (P1) are in place from the top to bottom level (EGATrep #1, GOrg #1, #2, #3, #4, Reg #1, #2, ICEHrep #1). However, EHIA practitioners argued that existing EHIA guidelines need to be clearer on how to conduct the EHIA process (Practitioner #1, #2, #3, #4). Research scholars also recommend that clear guidance and adequate guidelines are essential factors influencing effective inclusion of health in impact assessment (Harris et al. Citation2009; Fischer et al. Citation2010; Tamburrini et al. Citation2011).

As the legislation is enforced, it allows institutional roles, collaborations & infrastructure (P2) to be clearer for all relevant stakeholders and authorities (EGATrep #1, GOrg #1, #2, Reg #1, #2, ICEHrep #1). However, it was found that area context is influential in creating networks to work together i.e. establishing monitoring network systems on environment quality and health (Reg #1, #2). According to documentary analysis and interviews, EHIA Cases 1 & 4 meet the P2 criterion fully, whereas Cases 2 & 3 meet it partially. Basically, EGAT provides a Continuous Emission Monitoring System (CEMS) onsite as well as maintaining an environmental monitoring network with relevant organisations i.e. Pollution Control Department (PCD) and the Department of Fisheries (if the project is located near a river/ watercourse) for all of its power plants (EGATrep #1) (SECOT Co. Ltd Citation2013; SECOT Co. Ltd Citation2016a, 2016b). The local authorities in Chachoengsao province, where Case 1 and Case 4 are to be located, used the Chachoengsao Provincial Decree No.2391/2554 and No.16671/2557 to establish the local committee and subcommittee. This suggests that the local governance context could shape the line of collaboration between project developers and community differently, and is related to the key point that the political/administrative system is a contextual factor in relation to the effectiveness of impact assessment (Kolhoff et al. Citation2009).

Six-month monitoring reports of operating power plants are routinely submitted to ONEP (EGATrep #1) and it was agreed that the majority of power plant project developers are likely to follow monitoring measures (GOrg #2). It was argued that the project developer should share environmental monitoring information with the health authority so that it can be combined with the health impact investigation (GOrg #4), while it was suggested that data sharing between organisations requires improvement (NGO #1) which aligns with Jha-Thakur and Fischer (Citation2016) who noted that monitoring is a challenging element to achieve.

It is considered crucial that planning at the national level can lead to influential changes on health determinants (Bond et al. Citation2013), a point covered by criterion P3 concerning the extent to which the EHIA is integrated in the planning process, EGAT has integrated the concept of environmental and social responsibility in the planning process of the national energy development policy framework as well as the organisation policy (EGATrep #1, EGAT Citation2010). As EGAT is state owned, it is required that issues on environmental, health and social impact are taken into account (EGATrep #1, GOrg #2); however, concerns about the gap between government policy and impacts affecting stakeholders have been raised (ICEHrep #1). This could reflect the lack of EHIA of national development policy, an area where assessment is becoming more prevalent (Adelle and Weiland Citation2012).

For Identification of financial funds (P4) supporting the EHIA process, the project developer is mainly responsible for providing a budget for the EHIA process (as implicitly suggested in Ministry of Natural Resources and Environment (Citation2009)). It was noted by Practitioner #3 and NGO #1 that the financial fund for public consultation should be co-supported by the government. Although PP5 is already arranged by the regulator which is responsible for the cost at that stage, more financial support from government authorities was felt to be warranted (Practitioner #3). It was also pointed out that the EHIA process includes environmental and health impact monitoring and that financial resources for this practice should be provided explicitly in the long term (GOrg #4). In addition, the changing of national legislation and political context i.e. the termination of the Thai Constitution B.E. 2550, which enforced EHIA, has caused uncertainty for the future of relevant organisations involved in the EHIA process, i.e. for ICEH, the Thai Constitution B.E. 2550 stated in clause No. 12 of Section 1 that the Department of Environmental Quality Promotion (DEQP) has to financially support practice conducted by the ICEH committee (The Prime Minister’s Office’s Citation2010). As the constitution was cancelled, it is unclear what the future financial source of public consultation conducted by ICEH might be (GOrg #1, ICEHrep #1). However, regarding the four cases, financial sources for EHIA still met the P4 criterion at the time the EHIAs were undertaken, as the results demonstrate in Table .

In terms of Involvement of stakeholders (P5), the EHIA regulation weighs public consultation as a priority in the EHIA process as indicated in Section 2 (Figure ). As it is mandatory, public participation processes were conducted in the four EHIA cases. Thus all the cases meet the P5 criterion. However, it was noted that the public consultation methods suggested in the guideline (Ministry of Natural Resource and Environment Citation2010a, Citation2010b) are sometimes too fixed e.g. the minimum time required and public meeting patterns as specified for PP1 (Practitioner #1, #2, #4). It was argued, for example, that stakeholder analysis should be conducted based on social context (NGO #1). This may suggest that the roles of public participation should be investigated (Glucker et al. Citation2013) in the Thai context as should the stakeholder roles (McCallum et al. Citation2015) in the EHIA process.

Capacity of EHIA in presenting as a sound and clear, understandable evidence for decision-making process (P6): the reports satisfy the P6 criterion based on approval awarded by the ONEP expert panel. However, referring to documentary analysis of the EHIA reports in terms of content coherence, as well as ICEH comment reports (ICEH Citation2014), coupled with interviews (ICEHrep #1, Practitioner #1); it can be argued that P6 is partially met by the four EHIA cases. The documentary reviews in this study suggested that the project developer and EHIA practitioners have tried hard to prepare EHIA documents leading to plenty of technical information required for project operation; however, considering the size of the EHIA main reports, varying between 970 and 2121 pages excluding the summary report and appendices, minor inconsistencies are common e.g. incorrect lists of contents and variable format of page numbers. EHIA summary reports were also large in size i.e. Case Nos. 2, 3 and 4 were 370, 411 and 531 pages long, respectively, such that there is a second summary version of EHIAs provided by ICEH, to reduce the volume sizes to 35, 38 and 34 pages, respectively. Nor were the non-technical summaries presented along with the main reports as this is not demanded explicitly in the ONEP guideline associated with the legislation.

In terms of alternative analysis presented in the EHIA reports, Case 1 does not present this section whereas Case 2 identified project development options and the preferred option; Case 3 does not present alternatives but explains the proposed project option and Case 4 also summarised the proposed project option. This suggests that different consultants vary in their interpretation of this part of the regulations. The main reports were provided in line with the legislative guideline, but it has been found that environmental and health impact assessments are reported separately in different chapters as an EIA chapter and a HIA chapter, suggesting that they were conducted in isolation from each other within the EHIA process, rather than as an integrated whole as inferred in Figure . This means connections between impact assessment processes i.e. scoping and impact assessment are not clearly demonstrated according to the chapters in the reports. Additional supervisory comments from the ICEH committee also raised this point (Independent Commission on Environment and Health (ICEH) Citation2014). Bond et al. (Citation2013) suggested that practitioners and professionals in both fields should learn to collaborate, as well as facilitate knowledge training in order to ensure sufficient capacity in areas outside their immediate areas of expertise. Interviewees also noted that integration between the environment and health fields is challenging (Practitioner #1, GOrg #1) as ‘expectation and target set from different perspectives are unlikely to present the same picture’ (Practitioner #1). Connections between chapters are not sufficiently clear; whereas the power plant expert panel had tried to point out that the connections between environment and health aspects are essential (GOrg #2).

Whilst it is compulsory that an EHIA scoping report is submitted to ONEP (Ministry of Natural Resources and Environment Citation2009), the findings from EHIA scoping are required to be more integrated in the main reports, and to include cumulative impacts arising from existing and planned developments. In addition, based on a site visit by the ICEH team, it was suggested that information provided by the project developer and the EHIA consultant should be linked better to reduce the time taken in rechecking for correctness of information (ICEHrep #1).

While the non-mandatory power plant EHIA guideline (Health Impact Assessment Division Citation2012) has been additionally established and applied in the EHIA process by consultants; in-depth understanding of the guideline has not been achieved when practitioners conduct EHIAs (GOrg #3). This suggests that further capacity building and institutional support is needed as recommended by Fischer et al. (Citation2010) and Morgan (Citation2011).

Concerning delivering the findings of report to participating stakeholders (P7), the findings of the EHIAs and the reports are delivered to participating stakeholders via local organisations, for example, district/sub district offices (Reg #2) and via the public review stage (EGATrep #1, Practitioner #3) alongside disclosing the reports online (Reg #1, #2, ICEHrep #1) such that the four EHIA cases achieved the P7 criterion. Nevertheless, it was suggested that risk communication should be promoted and the government should disclose impact monitoring information to the public (NGO #1); communication language delivered should be simplified and stakeholders should be informed using suitable techniques/patterns (GOrg #4).

Finally, Time enforcement for EHIA process (P8) was not achieved given that, because of the EIA legislation changing in 2009–2010, Case 1, which was previously granted EIA approval, was required to produce an EHIA after construction had already begun. This suggests that the consequences of regulation changes could affect the procedural effectiveness of impact assessment in terms of practice conducted by relevant stakeholders/actors. Hence, guidelines on how to deal with such changes would need to be published by the relevant authorities in advance.

5.2. Substantive effectiveness

As the results presented in Table suggest, the four EGAT’s EHIAs meet four substantive effectiveness criteria (S1, S3S5), while S2 and S6S10 are unlikely to be achieved fully.

As the regulatory framework for implementing EHIA in decision-making (S1) came into force in Thailand in 2009, statutory consultation authorities, regulators and relevant decision-makers are required to take EHIA findings into account as stated in a Ministry of Natural Resources and Environment (Citation2010a) notification. It was emphasised that the EHIA process is applied as part of decision-making to support national power development policy to ensure that appropriate measures are provided once power plant projects are developed (GOrg #4, EGATrep #1, Reg #1, #2). The availability of regulatory requirements for EHIA could be a sign that practice is progressing (Tamburrini et al. Citation2011), while ‘formal application’ of legislation is argued to influence decision-making by resulting in project modifications (Christensen et al. Citation2005, p. 393).

In terms of incorporation of proposed changes (S2), findings from the EHIAs were taken into account in the project development by the relevant authorities as presented in final EHIA reports and it suggests that the four cases are likely to meet this criterion. However, it is noted that the proposed changes are prioritised based on legislative requirements in favour of issues raised by the public (Practitioner #3). In general, although the EHIA findings are considered as part of decision-making, it was felt by some that the anxieties of those people against the project development had not been sufficiently investigated (GOrg #4).

Informed decision-making (S3) of the four cases are presented via relevant evidence, for example, in the initial parts of EHIA main reports, authorities’ websites i.e. ONEP, ICEH and ERC; however, updating relevant information regularly is required. The decisions are also informed to the community located within 5 km of the project site at the local administration office (Reg #2).

For close collaboration (S4), EGAT and EHIA practitioners work together during EHIA processes (Reg #2, EGATrep #1, Practitioner #3) such that this criterion is achieved in all four cases. Good communication is essential between project developers and EHIA practitioners (Reg #2), while they work as a team in conducting EHIA (Practitioner #3). GOrg #4 commented that the project developer could approve and/or influence how the EHIA practitioner delivers findings in the EHIA report; however, it was argued that the expert panel appointed by ONEP is a balance which can ensure EHIA correctness and reliability (GOrg #2). As it is state owned, EGATRep #1 emphasises that there are authority procurement regulations on how to select qualified EHIA practitioners.

In terms of parallel development (S5), the EHIA processes of the four cases were developed in parallel with power plant project development (EGATrep #1, GOrg #4).

While the early start (S6) criterion seems easy to achieve if EHIA is implemented early before the construction phase assuming it has been well planned at the feasibility and detailed design stages, three EHIAs do not meet this criterion fully. Case 1 fails to satisfy this criterion as it was affected by the timing of changes in EIA legislation such that EHIA was required and commenced after the construction phase started. The 2nd version of Case 4 EHIA was submitted for the approval process after the first version was approved by the ONEP expert panel; this second version was necessary because of technology changes leading to a higher power generating capacity than that identified in the first version of the EHIA when procurement was performed (SECOT Co. Ltd Citation2016b). Case 2 EHIA has encountered the same problem as Case 4 (EGATrep #1). Thus only Case 3 meets the S6 criterion.

In terms of institutional and other benefits (S7) that EHIA outcomes bring about; local power funds have been established under ERC power fund regulations No. 18 Re: Establishment of power fund for local development and restoration in affected area resulting from power plant operation B.E. 2553. The power funds are run by an appointed committee in each particular area. It was suggested that financial support from the power plant fund should be granted for health impact monitoring (GOr #4) as well as research related to local/ community health impact and health follow-up (ICEH #1). In Bang Pakong, the power plant authority has granted research funds for community health impact assessment to promote health and environment over a 0–2-km radius from the power plant location (EGAT #1). However, the support is varied regarding location and community context as well as local power fund management (Reg #1, Reg #2, EGAT #1). Overall, the EHIAs meet this S7 criterion partially.

Referring to successful statutory consultation (S8) considered along with satisfactory/understanding/comments in using EHIA in the decision-making process (S10), the findings suggest that the statutory consultation authorities (ONEP, the expert panel appointed by ONEP, ICEH and ERC) have conducted their roles diligently. In the EHIA review process, it was questioned if the panel actually conducted the site inspections or not (NGO #1), with the response by GOrg #2 that the panel would do so at least one time for each particular project. The comments given by the expert panel are considered useful for the regulator in proceeding in making a decision or providing comments for ONEP and NEB, whereas it was noted that ICEH committee’s comments (ICEH Citation2014) tend to be unhelpful in allowing the regulator to reach a decision regarding the project proposal, particularly when promoted by private enterprise (Reg #1, #2). Meanwhile, it was argued that ICEH comments are provided additionally for the regulator to consider, and are not an official obligation (ICEHrep #1). However, the observation made by the regulator could relate to the pattern and structure of the ICEH supervisory comment reports which present the individual committee’s comments without critically concluding all ideas in one place. Therefore, the four EHIA cases could partially achieve the S8 and S10 criteria.

Successful public consultation (S9) remains unclear for EHIA Case 2, Mae moh power plant unit 4–7 replacement, as the documentary reviews and interviews suggested different viewpoints from different groups of stakeholders participating in public consultation conducted at different times by the project developer (PP1–3), ICEH (PP4) and ERC (PP5) (ERC Stakeholder Public Consultation Committee Citation2014; ICEH Citation2014; Team Consulting Engineering and Management Co. Ltd Citation2014).

It was emphasised that area contexts could determine how the community and project developer build their relationships (EGATrep #1). This is linked with arguments raised by Schaeffer and Smits (Citation2015) that ‘places’ and people in such places are key factors influencing environmental movements. Nevertheless, other factors could influence the level of success in building good relationships between people and achieve successful public consultation according to the project development consequences experienced among stakeholders. For example, coal power plant operation may cause more public anxiety leading them to take action differently according to where they live i.e. whether in a sensitive area or remote zone. In terms of the EHIA reports for Cases 1, 3 and 4; they have achieved the S9 criterion partially.

Investigating the pros and cons of public consultation in the EHIA process, it was found that additional public consultation (i.e. PP4 and PP5) in the EHIA process could lead to added value where new useful information was obtained in addition to the findings already learned from PP1 to PP3 (Reg #1, Reg #2). The EHIA legislation also provides an opportunity for the public to take part in this process (GOrg #4, Practitioner #3, NGO #1) as well as the regulator and decision-makers taking this into account in connection with their roles (Practitioner #3, Reg #1, #2). The findings gained from the process could help relevant authorities solve problems regarding project operation as well as providing evidence for the decision-making process (GOrg #4). Nevertheless, it is recognised as a challenge to ensure that all stakeholders recognise the need for, and value of, public consultation (Reg #2).

In terms of barriers to frequent public consultation processes conducted by different organisations, concerns have been raised that the strict time frame and fixed methods mean that practice is not cost effective (Reg #2, Practitioner #2, GOrg #4) and sometimes, stakeholders are paid to take part in the process and present a particular view (Practitioner #2, #3). It was noticed that public consultation time is expected to be used to negotiate for benefits from the established power fund in some areas; however, ONEP is in the process of developing a public consultation guideline (Reg #2). It was also added that, participants taking part in public consultation share their views based on their attitudes towards the project rather than scientific information (Practitioner #3, NGO #1) which could lead to controversy. It was pointed out that too much of the contents of EHIAs are uninteresting for some groups of stakeholders to read (Practitioner #2). It is recognised that different expectations of various groups of stakeholders are challenging to achieve when more of them take part, in line with the findings of Glucker et al. (Citation2013).

5.3. Transactive effectiveness

It was found that the transactive effectiveness could not be achieved fully according to resources invested and allocated in any of the four EHIA cases.

Regarding the first criterion of time invested in the EHIA process, the results showed that Case 1 performed poorly in relation to this criterion as it took 5 years to complete the process of EIA and EHIA (EGATrep #1). As presented in Table , the EIA was approved by NEB leading to the commencement of project construction prior to the change in legislative requirements. This forced the project developer to start the EHIA process to ensure that the project operation complies with the legislation. Cases 2 and 4 are questioned in terms of time effectiveness because additional assessments were conducted as a result of a technology change due to procurement choices subsequent to EHIA approval. As the time frame of EHIA decision-making is not set in fixed terms for the whole process (GOrg #4, EGATrep #1), it is unlikely to match with the power plant facility procurement process effectively (EGATrep #1). This leads to inefficiencies in terms of time for the EHIA process according to Chanchitpricha and Bond (Citation2013) and Theophilou et al. (Citation2010). Therefore, it is likely only that Case 3 met the T1 criterion partially for transactive effectiveness of EHIA (Table ).

Concerning financial resources (T2) operated in the EHIA process, sources of the funds are mainly from the project developer. DEQP supports public consultation conducted by ICEH (for PP4). ERC covers cost for public consultation (for PP5) prior to re-charging the project developer at the permission approval stage (Reg #1, 2). The amount of budget invested in the EHIA process depends on the area context and public consultation frequency/ requirement (EGATrep #1, ICEHrep #1), for example, in Mae Moh, Lampang for Case 2 it was approximately 1.5 million Thai Baht ($40,200), whereas in Bang Pakong for Case 4 it was approximately 500,000–600,000 Thai Baht (ICEHrep #1)($14,300–$17,100). Similarly, the public consultation cost invested is estimated to be 1.5–2 million Thai Baht ($40,200–$57,000) in each public meeting for PP5 (Reg #2). Thus it can be calculated approximately that in a project EHIA process, the total cost invested in public consultation varies between 2.5 and 8.75 million Thai Baht (~$71,000–$250,000) depending on project location/description and number of stakeholders. However, these data are not officially disclosed to the public and it could not be tracked into each individual project.

In summary, the project developer sees this as a worthwhile investment in order to communicate with the stakeholders

I see this is the way that we can communicate with stakeholders, assuming that 400 people living surrounding project location, they gather in one time to take part in public meeting, this is worthwhile as they can be informed about the project development. (EGATrep #1)

Nevertheless, the point of view was also shared that the budget is invested inefficiently in public consultation when compared with the outcomes gained (Practitioner #3). Therefore, EHIA Cases 3 and 4 meet this criterion partially; whereas Case 1 conducted impact assessment twice and fails to meet the criterion. Case 2 is conducting an additional EHIA for project capacity expansion due to technology change and is also unlikely to meet this criterion.

In terms of skills and personnel (T3) required in EHIA practice as well as specification of roles of people involved in the EHIA process (T4), EHIA practitioners conducting power plant projects are considered as professional firms with staff who can do the job (GOrg #2), while assigned staff conducting public consultation for PP5 are considered to be operating at a ‘good’ to ‘very good’ level (Reg #2). EHIA practitioners as consultants are able to approach the community better than in the past in the public consultation process; however, local authorities may face limitations in terms of financial support for staff capacity building to strengthen their roles relevant to the EHIA process (NGO #1). It is noted that the EHIA consultants are, in general, recognised to have variable levels of skills, experience and expertise (Practitioner #3). Nevertheless, it has been cautioned by respondent ICEH #1 that the knowledge and skills required in conducting EHIA are high due to the combination of ‘environment’ and ‘health’ aspects from both professions; as a result ‘knowledge controversy’ has sometimes been experienced among the committee when reviewing EHIA reports. It has been noted as an individual point of view that ‘environment’ and ‘health’ aspects in EHIA should be approved separately by two sets of committees from the Ministry of Natural Resource and the Ministry of Public Health (ICEHrep #1, GOrg #1). This reflects that working outside your field of expertise is considered to be a barrier between practitioners (Carmichael et al. Citation2012; Bond et al. Citation2013; Harris and Haigh Citation2015). Regarding perspectives on the skills of people involved in the EHIA process, it can be summarised that the four cases of EHIAs have achieved the T3 and T4 criteria partially (Table ).

According to the interviews, a key issue with the lack of availability of human resources was raised based on limited expertise in this field. This ties in with Glucker et al.’s (Citation2013) claim that IA human resources are not sufficient in developing countries. The findings suggested that all people involved in the EHIA process work hard in reviewing documents (EGATrep #1, ICEHrep #1, GOrg #2, NGO #1) in addition to those who conduct scientific and field work in technical assessment/monitoring and non-technical tasks i.e. data collection and public consultation (Practitioner #1, #4). Knowledge shared among disciplines is essential in this field such that availability of human resources is necessary and should be added as an additional T5 criterion in measuring the effectiveness of EHIA or other relevant impact assessment.

5.4. Normative effectiveness

With regard to adjustment of relevant policy framework concerning the normative goal achieved in terms of changes of views (N1), the four EHIAs achieve this criterion as, later on, EGAT prioritises the significance of sustainable development in its policy (EGAT Citation2010). It was suggested that legislation is a key instrument for shifting norms in authorities involved in the EHIA process, particularly state-owned enterprises (EGATrep #1), and it allows stakeholders to access information and take part in the EHIA process (NGO #1). As a result of policy adjustment, environmentally friendly power plant technologies are taken into account more when designing power plant project development (EGATrep #1, GOrg #1). This reflects incremental changes experienced within the authority where EHIA legislation is a key influence on decision-making (Chanchitpricha and Bond Citation2013).

Learning process, perception and lessons learnt (N2) from the EHIA process suggested that all relevant authorities can learn to adjust themselves and their working styles through their roles in this process where communication skills are essential (GOrg #4). It is noted that people complain without providing good evidence, and also that people discuss issues based on a different set of evidence to that presented in the EHIA, and this is considered a problem in the EHIA process (NGO #1). This suggests that barriers to learning exist (Fischer et al. Citation2009) as well as suggesting knowledge management issues (Bond et al. Citation2010). EHIA Cases 1, 3 & 4 achieve this criterion fully, while Case 2 partially achieves it.

In terms of development or changes in relevant institutional policies and policy choices (N3), it is agreed that findings from the EHIA process can support decision-making in approving licences as well as providing conditions that the project developer should apply in project operation (Reg #2). It is demonstrated that EGAT power plant projects have been improved in terms of applying mitigation measures, and also that community members help by informing the monitoring authority when environmental quality is not monitored (GOrg #2). This suggests that EHIA cases conducted by EGAT could achieve the N3 criterion partially.

Concerning improvement of health outcomes and quality of life (N4), it is noted that it is hard to indicate whether this criterion has been achieved among the four cases as factors influencing health impact could vary (Reg #2, Practitioner #3, GOrg #2). However, it was suggested that community mental health should be in a better state as people have been informed of what is happening in their community (GOrg #1, Practitioner #3) and it is evident that mitigation measures are implemented and fewer complaints raised after project operation commenced compared with complaints received at the earlier phase. Therefore, it could be argued that the EHIAs might achieve this criterion partially and observation on this normative change in the longer term is required.

6. Conclusion

Based on the findings in this research, focused on four power plant EHIA cases established by EGAT between 2011 and 2016, it can be concluded that procedural effectiveness and area context together control the levels of achievement in substantive, transactive and normative effectiveness. This is consistent with observations made by other authors in relation to consideration of the effectiveness of environmental assessment (i.e. SEA, EIA) in the past. Statistical analysis previously conducted by Fischer (Citation2002, p. 225) proved that the level of success in applying SEA and EIA is correlated with how procedural elements (i.e. legislation, methods and public involvement) were applied and conducted. Better impact assessment practices are likely to lead to better understanding as well as better decisions (Åkerskog Citation2006; Christensen et al. Citation2005; Phylip-Jones and Fischer Citation2013; Wende Citation2002). Thus, mandatory impact assessment can shape the extent to which effectiveness is achieved provided that the practice is performed based on ‘transparency and positive attitudes’ (Arts et al. Citation2012). Concerning the Thai context in this study, as EHIA is obligatory, project developers and decision-makers implement EHIA as part of their practice. This legislation opens doors to all relevant stakeholders to take part in the EHIA process in five stages; however, this could be considered as either a strength or weakness of the Thailand EHIA system. Although public involvement is applied in the EHIA process, the level of successful public consultation is questionable in terms of how fruitful the outcomes are. Trust issue between stakeholders/authorities is one concern that has been highlighted. We suggest that the purposes and roles of public participation in the Thai context should be clarified so that it can be applied in the EHIA process meaningfully and efficiently.

Although it was demonstrated that the cases have not achieved all four categories of effectiveness, the findings suggest good progress in EHIA practice in Thailand based on the analytical framework used. In addition, the application of this framework highlighted the need for a new criterion; T5: availability of human resources, to better reflect the full suite of elements underpinning effective practice.

To raise the level of effectiveness, EHIA guideline revision to strengthen procedural effectiveness based on integration of lessons learned, professional experience sharing and documentary analysis would be a good starting point and is recommended. This should be a collaboration among academics, ONEP and EHIA practitioners. In addition, institutional capacity building needs for EHIA/ EIA authorities is recommended, to identify how human resources/institutional roles can be strengthened and contribute to enhanced effectiveness. Last but not least, national policy impact assessment should be considered so that public policy, which links with national environmental and health outcomes, can be developed more sustainably.

Funding

This work was supported by Coordinating Center for Thai Government Science and Technology Scholarship Students (CSTS), National Science and Technology Development Agency, A New Researcher Scholarship of CSTS, MOST.

Acknowledgement

We would like to thank all key informants in this research and anonymous reviewers for their contributions in this paper.

References

  • Adelle C, Weiland S. 2012. Policy assessment: the state of the art. Impact Assess Project Appraisal. 30:25–33.10.1080/14615517.2012.663256
  • Åkerskog A. 2006. Outputs from implementing impact assessment in Swedish comprehensive plan 1996–2002. Bio technology. Research report number 2006:03.
  • Arts J, Runhaar HAC, Fischer TB, Jha-Thakur U, Van Laerhoven F, Driessen PPJ, Onyango V. 2012. The effectiveness of EIA as an instrument for environmental governance: reflecting on 25 years of EIA practice in the Netherlands and the UK. J Environ Assess Policy Manage 14:1–40.
  • Baker DC, McLelland JN. 2003. Evaluating the effectiveness of British Columbia’s environmental assessment process for first nations’ participation in mining development. Environ Impact Assess Rev. 23:581–603.
  • Bina O. 2007. A critical review of the dominant lines of argumentation on the need for strategic environmental assessment. Environ Impact Assess Rev. 27:585–606.10.1016/j.eiar.2007.05.003
  • Bond A, Cave B, Ballantyne R. 2013. Who plans for health improvement? SEA, HIA and the separation of spatial planning and health planning. Environ Impact Assess Rev. 42:67–73.10.1016/j.eiar.2012.10.002
  • Bond A, Morrison-Saunders A. 2013. Challenges in determining the effectiveness of sustainability assessment. In: Sustainability assessment: pluralism, practice and progress (Natural and Built Environment Series). London: Routledge; p. 37–50. ISBN-10: 0415598494.
  • Bond AJ, Viegas CV, Coelho CCdSR, Selig PM. 2010. Informal knowledge processes: the underpinning for sustainability outcomes in EIA? J Cleaner Prod. 18:6–13.10.1016/j.jclepro.2009.09.002
  • van Buuren A, Nooteboom S. 2009. Evaluating strategic environmental assessment in The Netherlands: content, process and procedure as indissoluble criteria for effectiveness. Impact Assess Project Appraisal. 27:145–154.10.3152/146155109X454311
  • Carmichael L, Barton H, Gray S, Lease H, Pilkington P. 2012. Integration of health into urban spatial planning through impact assessment: identifying governance and policy barriers and facilitators. Environ Impact Assess Rev. 32:187–194.10.1016/j.eiar.2011.08.003
  • Cashmore M, Gwilliam R, Morgan R, Cobb D, Bond A. 2004. Effectiveness of EIA: the interminable issue of effectiveness: substantive purposes, outcomes and research challenges in the advancement of environmental impact assessment theory. Impact Assess Project Appraisal. 22: 295–310.10.3152/147154604781765860
  • Chadwick BA, Bahr HM, Albrecht SL. 1984. Social science research methods. London: Prentice-Hall.
  • Chanchitpricha C. 2012. Effectiveness of Health Impact Assessment (HIA) in Thailand: a case study of a Potash mine HIA in Udon Thani. Norwich: University of East Anglia.
  • Chanchitpricha C, Bond A. 2013. Conceptualising the effectiveness of impact assessment processes. Environ Impact Assess Rev. 43:65–72.10.1016/j.eiar.2013.05.006
  • Chanchitpricha C, Bond A. 2015. Procedural effectiveness of the new environmental health impact assessment (EHIA) process applied to power plant projects in Thailand. Impact Assessment in the Digital Era 35th Annual Conference of the International Association for Impact Assessment.
  • Christensen P, Kørnøv L, Nielsen EH. 2005. EIA as regulation: Does it work? J Environ Plan Manage. 48:393–412.10.1080/09640560500067491
  • Creswell JW. 2007. Qualitative inquiry & research design choosing among five approaches. London: Sage.
  • Denzin NK, Lincoln YS. 2000. The discipline and practice of qualitative research. In: Handbook of qualitative research. 2nd ed. London: Sage; p. 1–29.
  • DIW & ERC Stakeholder Public Consultation Committee. 2014. DIW & ERC stakeholder public consultation report on EGAT Bang Pakong combined cycle power plant block 5 (in Thai). Bangkok.
  • EGAT. 2010. Electric generating authority of Thailand notification No. 15/2553 Re: EGAT environmental policy.
  • EGAT. c2013. Profile [Internet]; Nonthaburi; [accessed 2017 Feb 2]. https://www.egat.co.th
  • Environmental Impact Evaluation Bureau: Office of Natural Resources and Environment Policy and Planning (ONEP). 2014. Environmental impact assessment in Thailand (in Thai). Bangkok.
  • ERC Stakeholder Public Consultation Committee. 2014. ERC stakeholder public consultation report on EGAT Mae Moh power plant unit 4–5 replacement (in Thai). Bangkok.
  • ERC Stakeholder Public Consultation Committee. 2016a. EGAT Bang Pakong Combined cycle power plant unit 1–2 replacement. Bangkok.
  • ERC Stakeholder Public Consultation Committee. 2016b. ERC stakeholder public consultation report on EGAT South Bangkok (Phra Nakorn Tai) power plant replacement phase 1 (in Thai). Bangkok.
  • Fischer TB. 2002. Strategic environmental assessment in transport and land use planning. London: Earthscan.
  • Fischer TB, Kidd S, Jha-Thakur U, Gazzola P, Peel D. 2009. Learning through EC directive based SEA in spatial planning? Evidence from the Brunswick region in Germany. Environ Impact Assess Rev. 29:421–428.10.1016/j.eiar.2009.03.001
  • Fischer TB, Matuzzi M, Nowacki J. 2010. The consideration of health in strategic environmental assessment (SEA). Environ Impact Assess Rev. 30:200–210.10.1016/j.eiar.2009.10.005
  • Glucker AN, Driessen PP, Kolhoff AJ, Runhaar HA. 2013. Public participation in environmental impact assessment: why, who and how? Environ Impact Assess Rev. 43:104–111.10.1016/j.eiar.2013.06.003
  • Harris PJ, Haigh F. 2015. Including health in environmental impact assessments: is an institutional approach useful for practice? Impact Assess Project Appraisal. 33:135–141.10.1080/14615517.2015.1006417
  • Harris PJ, Harris E, Thompson S, Harris-Roxas B, Kemp L. 2009. Human health and wellbeing in environmental impact assessment in New South Wales, Australia: auditing health impacts within environmental assessments of major projects. Environ Impact Assess Rev. 29:310–318.10.1016/j.eiar.2009.02.002
  • Health Impact Assessment Division. 2012. Health impact assessment guideline for power plant development project (in Thai). Nonthaburi: Ministry of Health.
  • ICEH. 2013. ICEH comments on EGAT Bang Pakong combined cycle power plant block 5 project EHIA (in Thai). Bangkok.
  • ICEH. 2014. ICEH comments on EGAT Mae Moh power plant unit 4–7 replacement project EHIA (in Thai). Bangkok.
  • ICEH. 2016a. ICEH comments on EGAT Bang Pakong combined cycle power plant unit 1–2 replacement project EHIA (in Thai). Bangkok.
  • ICEH. 2016b. ICEH comments on EGAT South Bangkok (Phra Nakorn Tai) power plant replacement phase 1 project EHIA (in Thai). Bangkok.
  • Independent Commission on Environment and Health (ICEH). 2014. Supervisory comment on project development which may cause serious adverse impact on environment and health: Mae Moh power plant unit 4–7 replacement project (in Thai). Bangkok.
  • Jha-Thakur U, Fischer TB. 2016. 25 years of the UK EIA system: strengths, weaknesses, opportunities and threats. Environ Impact Assess Rev. 61:19–26.10.1016/j.eiar.2016.06.005
  • Kolhoff AJ, Runhaar HA, Driessen PP. 2009. The contribution of capacities and context to EIA system performance and effectiveness in developing countries: towards a better understanding. Impact Assess Project Appraisal. 27:271–282.10.3152/146155109X479459
  • Maxwell JA. 2005. Qualitative research design: an interactive approach. London: Sage.
  • McCallum LC, Ollson CA, Stefanovic IL. 2015. Advancing the practice of health impact assessment in Canada: obstacles and opportunities. Environ Impact Assess Rev. 55:98–109.10.1016/j.eiar.2015.07.007
  • Miles MB, Huberman MA. 1994. Qualitative data analysis. 2nd ed. London: Sage.
  • Ministry of Industry. 2009. Notification of the Ministry of Industry Re: projects or activities which may seriously affect community with respect to quality of environment, natural resources and health, 30 October B.E. 2552 (2009). Vol. 126, Part 159d.
  • Ministry of Natural Resources and Environment. 2009. Notification of the Ministry of Natural Resources and Environment Re: rule, procedure, method and guideline for preparation of the environmental impact assessment report or activity which may seriously affect community with respect to quality of environment, natural resources and health 29 December 2009. V. The Thai Government Gazette, Part 188d. In.
  • Ministry of Natural Resources and Environment. 2010a. Notification of Ministry of Natural Resources and Environment Re: specification of project types, scales, and regulations for activities which may cause severe effects on health, environment and natural resources No.2, 29 November 2010 (in Thai). Vol. 127, Special Part 137d. p. 8–9.
  • Ministry of Natural Resources and Environment. 2010b. Notification of Ministry of Natural Resources and Environment Re: specification of project types, scales, and regulations for activities which may cause severe effects on health, environment and natural resources B.E.2553, 31 August 2010 (in Thai). Vol. 127, Special Part 104d. Thailand; p. 34–35.
  • Ministry of Natural Resources and Environment. 2015. Natural Resources and Environment Ministerial Notification Re: specification of project types, scales, and regulations which may cause severe effects on health, environment and natural resources B.E.2558 No. 2. Vol. 132, Part 300d. Thailand: Thai Government Gazette.
  • Morgan RK. 2011. Health and impact assessment: Are we seeing closer integration? Environ Impact Assess Rev. 31:404–411.10.1016/j.eiar.2010.03.009
  • Office of Natural Resources and Environment Policy and Planning. 2013. Guideline for Health Impact Assessment in EIA report in Thailand (in Thai). Bangkok: ONEP.
  • Phoolcharoen W, Sukkumnoed D, Kessomboon P. 2003. Development of health impact assessment in Thailand: recent experiences and challenges. Bull World Health Org. 81:465–467.
  • Phylip-Jones J, Fischer TB. 2013. EIA for wind farms in the United Kingdom and Germany. J Environ Assess Policy Manage. 15:30.
  • Public Service Centre: Office of the Permanent Secretary. 2009. Public participation guideline upon the regulation of the Prime Minister Office on public consultation B.E. 2548 (in Thai). Bangkok.
  • Sadler B. 1996. International study of the effectiveness of environmental assessment. Ottawa: Final report.
  • Schaeffer C, Smits M. 2015. From matters of fact to places of concern? Energy, environmental movements and place-making in Chile and Thailand. Geoforum. 65:146–157.10.1016/j.geoforum.2015.07.021
  • SECOT Co. Ltd. 2013. Environmental and health impact assessment (main report): Bang Pakong combined cycle power plant block 5 project (in Thai).
  • SECOT Co. Ltd. 2016a. Environmental and health impact assessment (main report): South Bangkok (Phra Nakorn Tai) power plant replacement phase 1(in Thai). Bangkok.
  • SECOT Co. Ltd. 2016b. Environmental and health impact assessment (main report): Bang Pakong Power Plant Unit 1-2 Replacement Project (updated project description-version) (in Thai). Bangkok.
  • Siwaraksa P, Rojjanaphaiwong S, Liamsungnoen S, Watanachiwanopakorn W, Kankamphod T. 2004. Healthy public policy and health impact assessment (HPP-HIA) (in Thai) Nonthaburi. Thailand: Health System Research Institute (HSRI).
  • Stoeglehner G, Brown AL, Kørnøv LB. 2009. SEA and planning: ‘ownership’ of strategic environmental assessment by the planners is the key to its effectiveness. Impact Assess Project Appraisal. 27:111–120.10.3152/146155109X438742
  • Tamburrini A-L, Gilhuly K, Harris-Roxas B. 2011. Enhancing benefits in health impact assessment through stakeholder consultation. Impact Assess Project Appraisal. 29:195–204.10.3152/146155111X12959673796281
  • Team Consulting Engineering and Management Co. Ltd. 2014. Environmental and health impact assessment (main report): Mae Moh power plant unit 4–7 replacement project (in Thai).
  • The Prime Minister’s Office. 2010. The Prime Minister Office Regulation Re: coordination for establishing comments made by independent commission on environment and health regarding the development of projects which may cause extreme adverse impact towards community B.E. 2553 (in Thai). Thai Government Gazette No. 127 special section 4 d 12 January BE 2553. Bangkok.
  • The Prime Minister’s Office. 2011. Policy Statement of the Council of Ministers. Prime Minister Yingluck Shinawatra to the National Assembly. 23 August B.E. 2554 (in Thai). Bangkok: Cabinet and Royal Gazette Publishing Office.
  • The Prime Minister’s Office. 2014. Policy statement of the Council of Ministers. Prime Minister Prayuth Chan-o-cha. Delivered to National Assembly. 12 September B.E. 2557 (20014) (in Thai). Bangkok. Cabinet and Royal Gazette Publishing Office.
  • Theophilou V, Bond A, Cashmore M. 2010. Application of the SEA directive to EU structural funds: perspectives on effectiveness. Environ Impact Assess Rev. 30:136–144.10.1016/j.eiar.2009.08.001
  • Therivel R. 2010. Strategic environmental assessment in action. London: Earthscan.
  • Wende W. 2002. EIA research in Germany evaluation of the effectiveness and quality of environmental impact assessment in the Federal Republic of Germany. Impact Assess Project Appraisal. 20:93–99.

Reprints and Corporate Permissions

Please note: Selecting permissions does not provide access to the full text of the article, please see our help page How do I view content?

To request a reprint or corporate permissions for this article, please click on the relevant link below:

Academic Permissions

Please note: Selecting permissions does not provide access to the full text of the article, please see our help page How do I view content?

Obtain permissions instantly via Rightslink by clicking on the button below:

If you are unable to obtain permissions via Rightslink, please complete and submit this Permissions form. For more information, please visit our Permissions help page.