A new model of resource planning for optimal project scheduling

Pages 255-266 | Received 01 Oct 2006, Published online: 14 Oct 2010
 

Abstract

It is well known that not only the classical model of PERT/CPM but its later improvements treat a resource planning in the project scheduling in a very limited way. Using them it is possible to calculate the optimum amount of resources taken from outside or financial expenses for separate operations but it is quite impossible to share internal resources between parallel operations. Instead of these models a new one is introduced. It combines relationships concerning sharing resources‐capacities and works dynamics and perhaps other ones that express the use of materials and funds, inventory control and so on. Non‐strict work precedence conditions may be used as well. The model as a whole slightly differs from the model of resource planning in complex industrial systems proposed by the author and retains its general properties, notably the form of optimality conditions. A decomposition method of the project optimum fulfillment is proposed.

Reprints and Corporate Permissions

Please note: Selecting permissions does not provide access to the full text of the article, please see our help page How do I view content?

To request a reprint or corporate permissions for this article, please click on the relevant link below:

Academic Permissions

Please note: Selecting permissions does not provide access to the full text of the article, please see our help page How do I view content?

Obtain permissions instantly via Rightslink by clicking on the button below:

If you are unable to obtain permissions via Rightslink, please complete and submit this Permissions form. For more information, please visit our Permissions help page.