Figures & data
Figure 1. Development of project activity – the project activity was developed from stage 1 to stage 4 (for this to happen intermediate stage 2 and stage 3 occurred).
![Figure 1. Development of project activity – the project activity was developed from stage 1 to stage 4 (for this to happen intermediate stage 2 and stage 3 occurred).](/cms/asset/7fd11b17-e39c-4a30-9bf0-bae380150d50/tcim_a_1992665_f0001_oc.jpg)
Table 1. List of chosen team members and their characteristics
Table 2. List of chosen activities and their characteristics – performed by one of the design team members
Table 3. Analysis of hydraulic system supporting gear shifting activity and its structure
Table 4. Example metamorphoses of activity analysis of hydraulic system supporting gear shifting
Figure 2. Development of the activity presented in in iterative terms and expansion of the area under consideration and the definition of key parameters in these areas.
![Figure 2. Development of the activity presented in Figure 1 in iterative terms and expansion of the area under consideration and the definition of key parameters in these areas.](/cms/asset/93479f11-91b2-474a-bdea-b203677d5746/tcim_a_1992665_f0002_oc.jpg)
Figure 3. Multi-discipline decision making task applied to the components of the design process presented in previous figures.
![Figure 3. Multi-discipline decision making task applied to the components of the design process presented in previous figures.](/cms/asset/e415802d-8bcf-4094-8aaa-ab5a0ca1afd9/tcim_a_1992665_f0003_oc.jpg)
Figure 4. Activity change modelling – an example of a field describing activity versions and key activity problems and their status.
![Figure 4. Activity change modelling – an example of a field describing activity versions and key activity problems and their status.](/cms/asset/053b7fa3-3287-409e-bd10-2fc66ba33182/tcim_a_1992665_f0004_oc.jpg)
Table 5. The selected basic structure of knowledge resources describing the project and activities
Figure 7. Example of representation of the activity and description of its development with use of the discussed supporting tool.
![Figure 7. Example of representation of the activity and description of its development with use of the discussed supporting tool.](/cms/asset/63f48b2e-3ab5-486d-aa4f-9886ea598772/tcim_a_1992665_f0007_oc.jpg)
Figure 8. Example of a representation of the problem related to the activity and description of its potential future evolution with the use of the discussed supporting tool.
![Figure 8. Example of a representation of the problem related to the activity and description of its potential future evolution with the use of the discussed supporting tool.](/cms/asset/535e8ad9-7072-48e3-a730-1c7ec145befe/tcim_a_1992665_f0008_oc.jpg)