109
Views
0
CrossRef citations to date
0
Altmetric
Research Article

Exploring the economic prospects of wind energy in Zambia

, , , &
Pages 30-45 | Received 21 Feb 2024, Accepted 19 Jun 2024, Published online: 25 Jun 2024

Figures & data

Table 1. Adapted from World Bank. 2019. Wind resource mapping in Zambia: 24-month site resource report. Washington, DC, USA: World Bank. Renewable energy wind mapping for Zambia (Odoi-Yorke et al. Citation2022.).

Figure 1. Shows wind regime measurements conducted at eight meteorological (met) mast sites across the country.

Wind regime measurements were conducted at eight meteorological mast sites across Zambia.
Figure 1. Shows wind regime measurements conducted at eight meteorological (met) mast sites across the country.

Table 2. Proposed wind turbine model parameters (DNV Report Citation2023).

Table 3. Adapted from World Bank. 2019. Wind resource mapping in Zambia: 24 month site resource report. Washington, DC, USA: World Bank. Renewable energy wind mapping for Zambia.

Table 4. Adapted from World Bank. 2019. Wind resource mapping in Zambia: 24 month site resource report. Washington, DC: World Bank. Renewable energy wind mapping for Zambia.

Figure 2. Methodology flow chart used to evaluate the economic feasibility of the wind farms.

An economic evaluation methodology was developed to evaluate the economic feasibility using the present value of costs (PVC), simple payback period (SPP), internal rate of return (IRR), and levelized cost of electricity production (LCOE). Figure 2 shows the flowchart used in this study. The calculation of the economic result is based on the assumption of the price per kWh produced using the most likely price. This assumption is a critical factor for estimating the economic viability of a project. The developed model was analysed using MATLAB 2022. The electricity cost and sensitivity analysis results compared the current electricity cost for Zambia at 0.07 USD/kWh with the model results.
Figure 2. Methodology flow chart used to evaluate the economic feasibility of the wind farms.

Table 5. Summary of financial assumptions.

Table 6. Adapted from Techno-economic assessment of wind energy potential at three locations in South Korea using long-term measured wind data (Langer et al. Citation2022).

Table 7. Techno-economic parameters for the eight sites using electricity tariff of 0.07 USD/KWh.

Figure 3. Wind turbine economics at 0.07 USD/kWh electricity tariff for Choma site.

The results of the model showed negative NPV values for the 20 years. Towards the end of the turbine lifetime, the values approach a positive NPV, which can be explained by the negative payback period. The LCOE was at a minimum towards the end of the turbine lifetime.
Figure 3. Wind turbine economics at 0.07 USD/kWh electricity tariff for Choma site.

Figure 4. Average electricity tariff (0.07 USD/kWh) and (0.617 USD/kWh) sensitivity analysis for the Choma site.

shows the results of the sensitivity analysis for the Choma plant. The highest value of LCOE was 0.617 USD/kWh, and the lowest was 0.232 USD/kWh.
Figure 4. Average electricity tariff (0.07 USD/kWh) and (0.617 USD/kWh) sensitivity analysis for the Choma site.

Figure 5. Wind turbine economics at 0.07 USD/kWh electricity tariff for Mwinilunga site.

shows the techno-economic parameters at a 130 m hub height for the Mwinilunga site using Zambia’s average electricity tariff of 0.07 USD/kWh. The results of the model showed negative NPV values for the 20 years. The LCOE was at a minimum towards the end of the turbine lifetime.
Figure 5. Wind turbine economics at 0.07 USD/kWh electricity tariff for Mwinilunga site.

Figure 6. Average electricity tariff (0.07 USD/kWh) and (0.624 USD/kWh) sensitivity analysis for Mwinilunga.

shows the results of the sensitivity analysis for the Mwinilunga plant. The highest value of LCOE was 0.624 USD/kWh, and the lowest was 0.235 USD/kWh.
Figure 6. Average electricity tariff (0.07 USD/kWh) and (0.624 USD/kWh) sensitivity analysis for Mwinilunga.

Figure 7. Wind turbine economics at 0.07 USD/kWh electricity tariff for Lusaka site.

shows the techno-economic parameters at a 130 m hub height for the Lusaka site using Zambia’s average electricity tariff of 0.07 USD/kWh.
Figure 7. Wind turbine economics at 0.07 USD/kWh electricity tariff for Lusaka site.

Figure 8. Average electricity tariff (0.07 USD/kWh) and (0.482 USD/kWh) sensitivity analysis for Lusaka.

shows the sensitivity analysis results for the Lusaka plant. The highest value of LCOE was 0.482 USD/kWh, while the lowest was 0.182 USD/kWh.
Figure 8. Average electricity tariff (0.07 USD/kWh) and (0.482 USD/kWh) sensitivity analysis for Lusaka.

Figure 9. Wind turbine economics at 0.07 USD/kWh electricity tariff for Mpika site.

displays the techno-economic parameters at a 130 m hub height for the Mpika site using Zambia’s average electricity tariff of 0.07 USD/kWh. The model re-sults showed negative NPV values for the 20 years. The LCOE was at a minimum towards the end of the turbine lifetime.
Figure 9. Wind turbine economics at 0.07 USD/kWh electricity tariff for Mpika site.

Figure 10. Average electricity tariff (0.07 USD/kWh) and (0.487 USD/kWh) sensitivity analysis for Mpika.

shows the sensitivity analysis results for the Mpika plant. The highest value of LCOE is USD 0.487 USD/kWh, and the lowest is USD 0.487 USD/kWh.
Figure 10. Average electricity tariff (0.07 USD/kWh) and (0.487 USD/kWh) sensitivity analysis for Mpika.

Figure 11. Wind turbine economics at 0.07 USD/kWh electricity tariff for Chanka site.

shows the techno-economic parameters at a 130 m hub height for the Chanka site using Zambia’s average electricity tariff of 0.07 USD/kWh. The results of the model showed negative NPV values for the 20 years. The LCOE was at a minimum towards the end of the turbine lifetime.
Figure 11. Wind turbine economics at 0.07 USD/kWh electricity tariff for Chanka site.

Figure 12. Average electricity tariff (0.07 USD/kWh) and (0.547 USD/kWh) sensitivity analysis for Chanka.

shows the sensitivity analysis results for the chanka plant. The highest LCOE value was 0.547 USD/kWh, whereas the lowest was 0.206 USD/kWh.
Figure 12. Average electricity tariff (0.07 USD/kWh) and (0.547 USD/kWh) sensitivity analysis for Chanka.

Figure 13. Wind turbine economics at 0.07 USD/kWh electricity tariff for Petauke site.

displays the techno-economic parameters at a 130 m hub height for the Petauke site using Zambia’s average electricity tariff of USD 0.07/kWh. The LCOE was at a minimum towards the end of the turbine lifetime.
Figure 13. Wind turbine economics at 0.07 USD/kWh electricity tariff for Petauke site.

Figure 14. Average electricity tariff (0.07 USD/kWh) and (0.542 USD/kWh) sensitivity analysis for Petauke.

shows the sensitivity analysis results for the Petauke plant. The highest LCOE value was 0.542 USD/kWh, whereas the lowest was 0.204 USD/kWh.
Figure 14. Average electricity tariff (0.07 USD/kWh) and (0.542 USD/kWh) sensitivity analysis for Petauke.

Figure 15. Wind turbine economics at 0.07 USD/kWh electricity tariff for Mansa site.

displays the techno-economic parameters at a 130 m hub height for the Mansa site using Zambia’s average electricity tariff of 0.07 USD/kWh. The results of the model showed negative NPV values for the 20 years. The LCOE was at a minimum towards the end of the turbine lifetime.
Figure 15. Wind turbine economics at 0.07 USD/kWh electricity tariff for Mansa site.

Figure 16. Average electricity tariff (0.07 USD/kWh) and (0.599 USD/kWh) sensitivity analysis for Mansa.

shows the sensitivity analysis results for the Mansa plant. The highest and lowest values of LCOE were 0.599 USD/kWh and 0.226 USD/kWh.
Figure 16. Average electricity tariff (0.07 USD/kWh) and (0.599 USD/kWh) sensitivity analysis for Mansa.

Figure 17. Wind turbine economics at 0.07 USD/kWh electricity tariff for Malawi site.

displays the techno-economic parameters at a 130 m hub height for the Malawi site using Zambia’s average electricity tariff of 0.07 USD/kWh. The results of the model showed negative NPV values for the 20 years. The LCOE was at a minimum towards the end of the turbine lifetime.
Figure 17. Wind turbine economics at 0.07 USD/kWh electricity tariff for Malawi site.

Figure 18. Average electricity tariff (0.07 USD/kWh) and (0.617 USD/kWh) sensitivity analysis for Malawi.

shows the sensitivity analysis results for the Malawi plant. The highest value of LCOE was 0.617 USD/kWh, and the lowest was 0.233 USD/kWh.
Figure 18. Average electricity tariff (0.07 USD/kWh) and (0.617 USD/kWh) sensitivity analysis for Malawi.

Table 8. Techno-economic parameters using the average electricity tariff of 0.182 USD/kWh.

Figure 19. Parameter estimations of the sites: (a) EYA and wind speed; (b) EYA and CF; (c) SPP and IRR; (d) IRR and PBP.

illustrates parameter estimations of the sites. Initially, a site-specific analysis of wind characteristics was conducted. Subsequently, the selection of wind turbines was examined by considering the mechanical configuration suitable for the site.
Figure 19. Parameter estimations of the sites: (a) EYA and wind speed; (b) EYA and CF; (c) SPP and IRR; (d) IRR and PBP.

Data availability statement

The data that support the findings of this study are available from the corresponding author, S.M, upon reasonable request.