This case study of the Dasu Hydropower Project in Pakistan investigates the impacts of delays in resettlement on project-affected people. The analyses presented here suggest that delays in the implementation of resettlement plans lead to additional socio-economic, environmental and psychological impacts on local communities. In addition, temporary resettlement of some households prior to relocation and resettlement at the planned sites aggravated these impacts, further complicating planned resettlement. The authors argue in favour of resettlement ahead of any civil works to reduce negative project impacts.