Construction of reinforced concrete multi‐storey office buildings: A simulation model for time/cost calculations

First stage computer simulation model for the duration and cost estimation of the construction of a typical multi‐storey concrete framed office building providing rapid response to changes in input values and their effect on the duration and cost of the project

, &
Pages 227-233 | Published online: 08 May 2007
 

Abstract

The current model is confined to multi‐storey concrete framed office buildings with particular types of foundations and roof and choices within the building envelope, but it has the potential for further development to include wider choice. The flexibility provided by Leonardo will allow, claim the authors, a staged development without affecting the structure of the model.

Le modèle actuel est limité aux immeubles de bureaux à étages, à ossature béton, dotés de certains types de fondations, de toitures et d'éléments d'enveloppe. Mais il présente un intéressant potentiel de développement pour la prise en compte de choix beaucoup plus variés. Les auteurs estiment que la souplesse d'exploitation inhérente au Leonardo permettre un développement phasé sans atteinte à la structure même du modèle.

Reprints and Corporate Permissions

Please note: Selecting permissions does not provide access to the full text of the article, please see our help page How do I view content?

To request a reprint or corporate permissions for this article, please click on the relevant link below:

Academic Permissions

Please note: Selecting permissions does not provide access to the full text of the article, please see our help page How do I view content?

Obtain permissions instantly via Rightslink by clicking on the button below:

If you are unable to obtain permissions via Rightslink, please complete and submit this Permissions form. For more information, please visit our Permissions help page.