HIA practices in Nigeria

Pages 207-213 | Received 18 Jul 2011, Accepted 18 Jan 2012, Published online: 24 Jul 2012

Abstract

Health impact assessment (HIA) provides useful information on existing health services, their capabilities and the health status of the local communities, which is otherwise often unavailable. In Nigeria, HIA is usually applied to projects and, by exposing existing health inequities in project communities, provides the necessary tool for development proponents to act to provide or improve health services and to implement health promotion activities. Based on HIA experience in Nigeria, this paper highlights the deficiencies in national legislation with regards to HIA/EIA (environmental impact assessment) integration and a number of learning points are discussed. First, a complete health baseline is critical to the understanding of project impacts; analysis must be broad-based, considering existing health determinants. Second, community stakeholders and proponents may modify the implementation of health mitigation measures and should be seen as collaborators in the assessment process. Third, strong HIA recommendations can influence project design. A greater participation of the health sector in EIA is required to enhance HIA utilization.

Introduction

Health impact assessment (HIA) is a key decision-making tool in development and health planning (Bos Citation2006). For HIA to achieve its full potential as a tool for promoting public health, particularly in developing countries, there is the need for enabling legislation, adequate health information (baseline) and a complete analysis of health determinants.

Development projects at all levels have a potential impact on health. A pointer to the magnitude of the influence of environmental factors on the health of human populations is the recent data from the World Health Organization (WHO), which estimated that over 25% of the burden of human illnesses worldwide can be attributed to modifiable environmental conditions (Frumkin et al. Citation2004, Pruss-Ustun and Corvalan Citation2006). Evidence in the literature has shown consistently that major development projects can have far-reaching and long-term impacts not only on the physical environment but also on the health and well-being of the surrounding communities (Birley 1992, Hunter et al. 1993, Birley et al. Citation1998, Abah Citation2003, Bos Citation2009).

Environmental impact assessment (EIA), a tool that ensures a systematic approach for identifying and managing the effects of development, is used by many governments all over the world to safeguard the environment (Kwiatkowski and Ooi Citation2003). In Nigeria it is a mainstream and statutory requirement used as a tool to balance environmental considerations with sustainable development (Federal Ministry of Environment, Citation1999). Another tool that is gaining wide acceptance as a planning tool to address health concerns of development projects is the HIA (Birley Citation2002, Abah Citation2003). It seeks to assess the health effects of development projects and to safeguard and enhance human health.

There are two essential characteristics of an HIA: it seeks to predict the effects of a specific action on human health and to inform policy and decision-making for the prevention or mitigation of negative health effects (Parry and Stevens Citation2001, Kemm 2003). HIA is therefore a critical tool for effectively integrating health impact concerns in the environmental assessment process.

In Nigeria and many poor countries in Sub-Saharan Africa, major development projects are taking place in areas of low socio-economic development and less than optimum health status (United Nations Development Program Citation2010). These projects, many of which are subjected to EIA, influence not only the physical environment but also lifestyles, culture, employment, income, access to housing, sanitation and social organization, all of which are important determinants of health and well-being. Integration of health concerns in the EIA process is thus a key tool to harness public health benefits that present themselves at project planning, design and implementation stages (Bos Citation2009). One of the greatest challenges of the Nigerian Government today is therefore to find ways of supporting economic development that enhance health and well-being without adversely impacting the environment (National Planning Commission Citation2004, UNEP Citation2011).

This paper demonstrates that the HIA provides a unique opportunity for the generation of useful health indicators and exposes health inequities, particularly in poor economies where the health information necessary as a planning tool is largely lacking. It also highlights opportunities for the enhancement of the positive aspects of development projects by incorporating practical and realistic health goals into the project environmental management plan beyond mere project impact mitigation.

The paper reviews the regulatory framework for EIA in Nigeria and the challenges of integrating health into EIA. Drawing on the author's experiences of integrated EIA studies in Nigeria, it also demonstrates the role of HIA as a tool for addressing health concerns in projects. Finally the lessons learnt from practice are discussed to highlight the value of adequate baseline data acquisition and its utilization in impact assessment (and impact mitigation) to solve health problems.

EIA statutes and process in Nigeria

The main legal instrument for HIA in Nigeria is the Nigerian National Policy on the Environment. One strategy proposed by this policy is to ‘ensure that health impacts constitute a major component of environmental impact assessment of development projects’ (Federal Ministry of Environment Citation1999). In the author's experience, however, this policy appears to be only advisory. Human health assessment is regulated within the larger EIA planning and permit schemes (Federal Ministry of Environment Citation1999).

The implementation of EIA in Nigeria is facilitated through publication of EIA procedural guidelines that contain a systematic and semi-comprehensive approach to the conduct of EIA and details about the stages of the EIA process, including categorization of projects into classes I II and III (FEPA Citation1995). This guideline neither mentions health nor describes any procedure for integrating health in the EIA. As a consequence HIA is not fully understood and thus not fully utilized by development companies, regulators and policy-makers in Nigeria. It is therefore unlikely that the important role that HIA and the integrated EIA process will play in the economic, social and health development of the local population, particularly as a mechanism to institutionalize a cross-sectoral approach to addressing health concerns in national policy and project management, has been fully realized (Bos Citation2009, Bhatia and Wernham Citation2008). This point is particularly important given the huge challenges associated with meeting basic requirements for healthcare (National Population Commission Citation2008) and the health Millennium Development Goals (United Nations Development Program Citation2011), and the fact that Nigeria is currently ranked 156 on the UNDP Human Development Index (United Nations Development Program Citation2010), a composite scale that is used to rank countries by their level of human development and is computed based on life expectancy at birth, adult literacy rate, mean years of schooling and income.

Integrated impact assessment

The need to integrate health into EIA has been proposed by several notable HIA authorities for about 20 years (Birley and Peralta 1992, Birley et al. Citation1998). An integrated EIA, which combines health, social, economic, cultural and psychological well-being as well as the physical, biological and geochemical environments, provides a holistic understanding of the complex interrelationships between humans and the natural environments (Kwiatkowski and Ooi Citation2003).

The experience with integrated impact assessment in Nigeria is largely limited by the absence of an integrated impact assessment framework – a tool that gives national guidance on the integration of health and socio-economic impact assessment within an EIA (Kwiatowski and Ooi, 2003). Notwithstanding, multinational corporations such as the Shell Group have completed a number of integrated EIAs since the publication of minimum health standards (Shell Petroleum Development Company of Nigeria Citation2002). Although this may seem to suggest that regulation by itself may not be the only strategy for good EIA practice to emerge, it can be argued that good legislation is more likely to engender wider use of HIA by industry as it is well known that the motivation by development proponents to conduct EIA stems from ‘litigation, fear of litigation and fear of adverse publicity’ (Steinemann Citation2000).

Initial challenges with integrated impact assessments in Nigeria include the use of models that tend to suggest three separate assessments (Birley Citation2003; Birely, Citation2007) with the major disadvantages of huge time resource requirement and difficulties with the alignment of three overlapping but fundamentally and methodologically different data sets. A better approach (because it is simpler to use) is illustrated in Figure . Here it can be seen that the individual components of the assessment were centrally coordinated beginning at the stage of scoping. At this initial stage decisions were made regarding data requirements to be considered in the respective baseline assessments. By way of an example, would indoor air quality be assessed by the health team or by the bio-physical team, or would housing conditions be assessed by the social (SIA) or health team? The outputs of the bio-physical and social baseline studies were often inputs to the health baseline, and so there are likely to be cross references that must be taken into consideration. All three teams should preferably work together in a workshop setting at the end of field data acquisition and the results of the baseline studies should form a core ingredient for the impact analysis. A good approach is for all of the sub-teams to come together prior to impact assessment and define the environmental sensitivities that are likely to be impacted by the project based on their understanding of the baseline environment. This has the advantage of ease of interpretation of impacts and cross-cutting issues can be dealt with in a common way (Federal Ministry of Environment Citation2005).

Figure 1 Model for integrated EIA based on field experiences in Nigeria. Source: author's field experience.

Figure 1 Model for integrated EIA based on field experiences in Nigeria. Source: author's field experience.

Integrated HIA/EIA: examples from practice

Guidance for integrated HIA/EIA in Nigeria has largely been provided by oil companies, particularly the Shell Petroleum Development Company (Citation2002). The application of HIA methods and procedures and how health is dealt with in the larger EIA is thus largely influenced by this historical perspective. An important benefit of the Shell approach is the overcoming of the shallowness of health issues in EIA and the broadening of the perspectives according to which relevant health issues are addressed, bearing in mind the shortcomings with data reliability and competence (personal observation). It is important to note that in Nigeria EIA/HIA is primarily focused on projects rather than policies of the government, and thus generally industry-driven, particularly the oil and gas sector. For instance, according to K. Odusanya (personal communication, 6 May 2006), of the 218 EIAs processed by the FMENV between 1995 and 2006, 164 (75.2%) were in the oil and gas sector.

This contrasts with the situation in many European Union nations where independent HIA may be conducted to ensure healthy public policy or programmes (Department of Health Citation2003, European Commission Citation1999). Therefore contrary to the assertion in the literature that HIA of projects is uncommon and that few people or organizations have the competence to carry out HIA for capital projects (Satin and Stock Citation2010), on the ground in Nigeria the existing competencies are mainly in the context of project HIA. As stated earlier, these projects are located mainly in poor communities with inadequate healthcare. Proper application of the HIA/EIA will thus serve as a powerful tool to address health problems whose burden may otherwise be worsened by the project.

This paper draws on the author's experiences from the three projects (case studies) described below to demonstrate that integrated EIA with a competent HIA component provides a mechanism for the improvements in public health in the project area. These case studies were selected as early examples of integrated EIA and do not necessarily represent EIA/HIA practice in Nigeria. They were assessed on the basis of the key HIA findings such as the application of a broad-based health baseline in the analysis of health impacts and mitigation measures and the way in which these findings were utilized by the project to promote public health goals (Table ).

Table 1 How integrated HIA/EIA can promote public health: examples from practice.

Case study 1: seismic data acquisition and exploratory appraisal of OPL 276

This project, located in Mbo local government of Akwa Ibom state, Nigeria (Federal Ministry of Environment Citation2008), demonstrates a number of ways by which an integrated EIA can promote public health goals. The proponents of the project carried out an integrated impact assessment prior to the commencement of the project. The main findings from the HIA included destruction of vegetation that served as medicinal plants, a source of household energy (firewood) and income. These findings corroborated concerns expressed by stakeholders during consultation and EIA scoping. The baseline study also indicated that malaria was responsible for the highest number of morbidities in both adults and children. The lifestyle of the people was characterized by having multiple sexual partners in about 47% of the study population and condom uptake was relatively poor. The project proponents implemented the recommendations of the HIA: to provide insecticide-treated nets to its workers and organize HIV/AIDS awareness campaigns in collaboration with the State AIDS Control Agency. These measures contributed to the enhancement of public health in the project area and reflect the role of HIA in addressing health problems, particularly in developing countries where health indices remain less than desirable.

Case study 2: Eremor Field Development Project

The EIA for this project, which is the drilling of an oil well, predicted that the project was likely to result in significant levels of turbidity of the main river in the project area owing to dredging of the slot leading to the oil well head (Table ). The locals depend on this river for their water supplies. Other health impacts identified in the EIA included a significant increase in morbidity from communicable diseases such as malaria and sexually transmitted diseases, mainly from the anticipated influx of oil workers and camp followers (Federal Ministry of Environment Citation2006).

The recommended mitigation measures are summarized in Table . Mitigation measures for potential infectious disease transmission between oil workers and villagers were mainly limited to prompt treatment of malaria and provision of support services for malaria and the HIV control programme of the Government. Implementation of these measures will contribute to improvements in public health.

Case study 3: Eneka Landfill Project

The upgrading of a waste dump site in Eneka, Port-Harcourt, Rivers state, Nigeria (Federal Ministry of Environment Citation2007) elicited serious health concerns from nearby communities and stakeholders, particularly on issues related to odour, fire outbreak and methane emission. As a result, the EIA scope required the assessment of these aspects leading to project design modification (Table ).

The project proponents were asked by regulatory authorities to modify two key components of the project design: the leachate collection system and the location of the proposed compost facilities. These project modifications were a direct consequence of the detailed health assessment that was fully integrated into the EIA.

Conclusions and lessons from practice

By way of conclusion, the following lessons from Nigerian practice are advanced.

Complete baseline data are valuable

A key component of the HIA is the determination of the baseline health status of the people affected by the project, which comprises two key inter-related components: surveys for baseline health data and surveys for determinants of health. Generating useful data to adequately articulate the baseline health status of communities impacted by major projects has remained a major challenge in Nigeria (Abah Citation2003, Abah et al. Citation2006). This is mainly due to the absence or paucity of reliable health and surveillance data and the problem of low capability amongst existing health services, further diminishing the reliability of available health data. To overcome these challenges it is necessary to carry out comprehensive health surveys and cross sectional studies, as depicted in Figure .

Figure 2 Generic model for the determination of baseline health status.

Figure 2 Generic model for the determination of baseline health status.

As a special survey, this approach not only provides key information gaps to the project proponent but also ensures access to health data that might have been otherwise unavailable. By complementing available health data, the HIA serves as a valuable resource and planning tool for project managers and public health administrators. The utility of the integrated EIA as a health-promotion tool will be greatly enhanced if public health authorities play a statutory role and thus are encouraged to own the outcome and apply same process to their planning and policies.

A broad view on impacts is required

Assessment of impacts entails the identification of the project's likely effects on health and well-being. Direct effects are often work-related and include injuries to the workforce, noise, air and water pollution, while indirect effects are mainly due to the influx of people and labour migration, leading to the creation of squatter settlements and their associated water and sanitation problems along with myriad other social problems, such as an increase in social vices (crime and prostitution), inflation, etc. In resource-poor communities, there already exist a gap in terms of social amenities and availability of health services. An additional burden from these indirect impacts attributable to the project may thus potentially worsen an already compromised health status. On the other hand, employment opportunities created by the project could improve the standard of living and the ability to pay for food and health services, thus serving as an indirect investment in healthcare.

Mitigation measures and their implementation

From the case studies above, two key areas readily come to mind: the extent and context within which the impacts were considered by the HIA/EIA team and the level of implementation of mitigation measures by the proponents (Table ). Implementation of mitigation measures to address health effects based on a strict definition of health impacts arising from the index project may not adequately address stakeholder concerns, and can often lead to conflicts. This is largely because, as pointed out earlier, most oil and gas developments in Nigeria are taking place in resource-poor communities, particularly in the Niger Delta region where long-term deprivation, environmental degradation and poverty pre-exist (UNEP Citation2011). Implementation of mitigation measures must therefore not assume this narrow perspective otherwise it may be difficult to secure the much desired social licence to operate, which is the acceptance and goodwill of the local communities.

Implementation of mitigation is influenced by existing health determinants, and community stakeholders

Project proponents may not always implement HIA mitigation as prescribed in the EIA. The case of Eremor FDP provides useful practical lessons. Critical analysis will show that, although the EIA recommendations for the mitigation of water pollution appear to be adequate in ‘legally’ mitigating the project impact, which is essentially limited to the duration of the dredging works, the approach adopted by the project, which was influenced by community stakeholders, theoretically guarantees sustainability of water supplies beyond the project impact.

Furthermore, if community members are involved in the restoration of the broken-down borehole, then some level of economic enhancement and promotion of community ownership of the project is to be expected, both of which are driving forces for sustainability. Another issue is the choice by the proponents to build a doctor's quarters as mitigation for infectious diseases. The HIA had reported that the only healthcare centre in the community did not have a doctor, which the locals attributed to the absence of a suitable accommodation. The absence of a doctor and the state of the doctor's quarters were clearly not direct project impacts, but nonetheless critical health determinants.

Two vital lessons can be learnt here. The first is the high level of rigorous and practical considerations required in making recommendations, which underscores the need for expertise and experience. In line with earlier arguments, this is only possible with a more complete baseline health assessment. The second lesson is the power of communities and stakeholders to ‘negotiate’ the implementation of mitigation measures. Project proponents and community stakeholders must therefore be viewed as collaborators in integrated HIA/EIA for a successful outcome.

Concluding remarks

In summary, HIA provides a unique tool for the health sector to positively influence developments and to utilize the opportunities provided by projects for the reduction of disease burden in developing countries. Its utilization in Nigeria is likely to be enhanced by statutory provision for integrated EIA that guarantees the full involvement of the health sector with the requisite training and experience. A greater participation of the health sector is required to promote the utilization of HIA as a tool for achieving health goals in resource-poor countries.

References

  • Abah , S. 2003 . Promoting a balance between hydrocarbon resource exploitation and human health: health impact assessment and environmental policy formulation . Journal of Nigerian Environmental Society , 1 ( 1 ) : 41 – 49 .
  • Abah , S.O. , Ilevbare , U. and Asogun , A. D. 2006 . Environmental impact assessment as a tool for promoting public health in resource poor communities . Journal of Applied and Basic Sciences , 4 : 67 – 75 .
  • Bhatia , R. and Wernham , A. 2008 . Integrating human health into environmental impact assessment: an unrealized opportunity for environmental health and justice . Environmental Health Perspectives , 116 ( 8 ) : 991 – 1000 .
  • Birely, M.H., and Peralta, G.L., 1992. Guidelines for the health impact assessment of development projects, Asian Development Bank Environmental Paper no 11.
  • Birley , M.H. 2002 . Review of trends in Health Impact Assessment and the nature of the evidence used . Environmental Management and Health , 13 ( 1 ) : 21 – 29 .
  • Birley , M. 2003 . A fault analysis for health impact assessment: procurement, competence, expectations and jurisdictions . Impact Assessment and Project Appraisal , 25 ( 4 ) : 313 – 321 .
  • Birley , M. 2007 . Health impact assessment, integration and critical Appraisal . Impact Assessment and Project Appraisal , 21 ( 4 ) : 281 – 289 .
  • Birley , M.H. 1998 . Health and environmental impact assessment: an integrated approach , London : Earthscan/British Medical Association .
  • Bos , R. 2006 . Health impact assessment and health promotion . Bulletin of the World Health Organization , 84 ( 11 ) : 914 – 915 .
  • Bos, R., 2009. Environmental health impact assessment – principles and practice [online], International Conference on Environmental Health, Abu Dhabi. Available from: http://www.wpro.who.int/NR/rdonlyres/56AAEFB8-529C-494B-82FB-E10FD1B62,510/0/MicrosoftPowerPointEHIAPrinciplesandpraticeRobertBos.pdf. [Assessed 20 October 2011].
  • Department of Health . 2003 . Tackling health inequalities: a program for action , London : Department of Health .
  • European Commission . 1999 . Fourth report on the integration of health protection requirements in community policies, V/99/408-EN , Brussels : European Commission .
  • Federal Ministry of Environment . 1999 . National policy on the environment , Revised ed. , Abuja, Nigeria : Federal Ministry of Environment .
  • Federal Ministry of Environment . 2005 . Environmental impact assessment of Afam Power Project , Abuja, Nigeria : Federal Ministry of Environment .
  • Federal Ministry of Environment . 2006 . Environmental impact assessment of Eremor Field Development Project , Abuja, Nigeria : Federal Ministry of Environment .
  • Federal Ministry of Environment . 2007 . Environmental impact assessment (EIA) of engineered landfill of Eneka Waste Dump Project , Abuja, Nigeria : Federal Ministry of Environment .
  • Federal Ministry of Environment . 2008 . Environmental impact assessment of seismic data acquisition and exploratory appraisal of OPL 276 , Abuja, Nigeria : Federal Ministry of Environment .
  • FEPA . 1995 . Guidelines for environmental impact assessment: sectoral guidelines for oil and gas industry exploration and production Lagos, Nigeria
  • Frumkin , H. , Frank , L. and Jackson , R. 2004 . Urban sprawl and public health: designing, planning, and building for healthy communities , Washington, DC : Island Press .
  • Kemm , J. and Parry , J. (Eds), 2004 . Health Impact Assessment: Concepts, Techniques and Applications , Oxford, UK : Oxford University Press .
  • Kwiatkowski , E.R. and Ooi , M. 2003 . Integrated environmental impact assessment: a Canadian example . Bulletin of the World Health Organisation , 81 : 434 – 438 .
  • National Planning Commission . 2004 . Abuja, Nigeria . National Economic Empowerment and Development Strategy (NEEDS)
  • National Population Commission . 2008 . ND ORC Macro. Nigeria demographic and health survey , Calverton, MD : Nigeria National Population Commission and ORC .
  • Parry , J. and Stevens , A. 2001 . Prospective Health Impact Assessment: Pitfalls, problems, and possible ways possible . BMJ , 323 : 1177 – 1182 .
  • Pruss-Ustun , A. and Corvalan , C. 2006 . Preventing disease through healthy environments – towards an estimate of the environmental burden of disease , Geneva : World Health Organization .
  • Satin, K., and Stock, A., 2010. Conducting effective health impact assessments in the oil and gas industry. SPE International Conference on Health, Safety and Environment in Oil and Gas Exploration and Production, 12–14 April 2010, Rio de Janeiro.
  • Shell Petroleum Development Company of Nigeria, 2002. Impact assessment guidance on integrated impact assessment, EP95-0378.
  • Steinemann , A. 2000 . Rethinking human health impact assessment . Environmental Impact Assessment Review , 20 : 627 – 643 .
  • United Nations Development Program, 2010. Human development reports [online]. Available from: http://hdr.undp.org/en/reports/global/hdr2010/ [Accessed 11 November 2011].
  • United Nations Development Program, 2011. Nigeria millennium development goals 2010 report [online]. Available from: http://www.ng.undp.org/mdgs/Final-MDG-report-2010.pdf [Accessed 10 November 2011].
  • UNEP, 2011. Environmental assessment of Ogoni Land [online]. Available from: http://www.unep.org/dnc/CountryOperations/Nigeria/EnvironmentalAssessmentofOgonilandreport/tabid/54,419/Default.aspx [Accessed 20 October 2011].

Reprints and Corporate Permissions

Please note: Selecting permissions does not provide access to the full text of the article, please see our help page How do I view content?

To request a reprint or corporate permissions for this article, please click on the relevant link below:

Academic Permissions

Please note: Selecting permissions does not provide access to the full text of the article, please see our help page How do I view content?

Obtain permissions instantly via Rightslink by clicking on the button below:

If you are unable to obtain permissions via Rightslink, please complete and submit this Permissions form. For more information, please visit our Permissions help page.