4,227
Views
1
CrossRef citations to date
0
Altmetric
Articles

Risks affecting the performance of Ethiopian domestic road construction contractors

, &

Abstract

The government of Ethiopia (GOE) has been working to enhance the capacity of Ethiopian domestic contractors (EDCs) over the past three decades. This has enabled the development of several private and public construction firms. However, the performance of EDCs is still a matter of concern. The aim of this paper is, therefore, to identify and prioritize risks of EDCs operating in the federal road construction projects. Forty-seven risk events were identified through an in-depth literature review. A questionnaire survey was conducted with professionals from the three main contracting parties (contractors, consultants, and the client) to prioritize the identified risk events in terms of their relative significance. The study outlined the ten most significant risk events namely, shortage of cash, inadequate planning, lack of access to foreign currency, delay in possession of site, frequent breakdown of equipment, delay in delivery of material and equipment, financial failure, inflation, delay in payments and poor commitment and coordination within the contractors’ team. This study provides an insight into contractors’ risks with a focus on domestic contractors engaged in the road sector. The findings of this study will be helpful to construction firms to develop an appropriate risk management system to effectively mitigate their risks.

Introduction

Sustainable, affordable, safe and well-maintained road infrastructure is critical to connecting people to goods, services, and advancing social and economic opportunities. It is particularly important for Ethiopia, where the road is the dominant mode of transport accounting for 90 to 95 percent of the motorized inter-urban freight and passenger movements. Nevertheless, the road network of the country in the early 1990s was among the lowest in Africa and other developing nations. Ethiopia’s road network density in 1990 was just 0.21 km per 1000 sq. km and 0.43 per 1000 population compare to the African average of 0.50 km per 100 sq. m and 0.61 km per 1000 population (ERA Citation1996). Further, the condition of the road network was in very poor condition, resulting in high road user costs (ERA Citation1996; MOFED Citation2002). What is more, the overall institutional capacity of the sector was a bottleneck in the effort to improve the road conditions of the country (ERA Citation1996; MOFED Citation2002).

In recognition of this, the GOE has been implementing a series of road sector development programmes (RSDPs) since 1997 (ERA Citation2011, Citation2016). Building the road sector institutional capacity has been one of the core strategic objectives of the RSDP.

In connection with institutional capacity building, the government has been undertaking various activities to attract private sector investment and improve the capacity of existing construction companies. This has enabled the creation of a large number of Ethiopian origin contractors (ERA Citation2011, Citation2016) against the handful of low capacity contractors that had existed before the implementation of the RSDP initiatives (MOFED Citation2002).

Nevertheless, the road construction business of the nation is still dominated by international companies. As detailed in the 19-year RSDP performance assessment report (ERA Citation2016), 599 road construction contracts were funded from 1997 to 2015 worth Ethiopian Birr (ETB) 180.5 billion (> $20 bl). Among these, 476 (79%) projects were awarded to EDCs with a value of ETB 82.7bl (45% of the total contract amount), while the remaining 123 projects worth ETB 102.8bl (55%) were awarded to foreign contractors. Further, of the 83 different projects, worth ETB 63.65bl, implemented in collaboration with development partners (World Bank, African Development Bank, European Union, China Exim Bank, etc.), only three projects with a total value of ETB 0.60bl (1%) were awarded to EDCs. This coincides with the recent report by the United Nations Economic Commission for Africa (UNECA Citation2015) that in most African countries domestic sector construction companies have difficulty competing with large international organizations - even in their own markets.

Several factors contribute to the limited participation of domestic contractors in the road sector. The first factor is the poor performance of EDCs to complete projects as specified in contracts (MOFED Citation2014; ERA Citation2016; Koshe and Jha Citation2016; Siraw Citation2016; Zewdu Citation2016; AfDB Citation2018). That is, projects awarded to local contractors are characterized by excessive delays (Koshe and Jha Citation2016; Zewdu Citation2016; Siraw Citation2016), and substantial cost overrun (Nega Citation2008; Zewdu and Getachew Citation2015). Since contractors’ monthly performance is one of the fundamental qualification criteria in tenders, such low performance appears to be a limiting factor for contractors to participate in bids.

The other is the overall limited capacity of domestic contractors to meet the bidding requirements in mega road projects. According to Desta (Citation2015), domestic contractors have limited capacity to meet the requirements of development partners, which has severely limited their competitiveness in projects implemented in collaboration with development partners.

Recent studies have shown that risk management is one of the most important but overlooked issues to ensure the success of road construction projects in Ethiopia (Yimam Citation2011; Ayalew et al. Citation2016; Zewdu Citation2016). However, to date, little research has been done to examine Ethiopian contractors' risk management capabilities. Hence, this paper aims to identify and assess the risk events pertinent to the EDCs engaged in federal road construction projects. A detailed literature review was carried out to identify the relevant risk events of the Ethiopian road sector. A questionnaire survey was conducted with the prime contracting parties, namely, contractors, consultants, and the client to determine the magnitude of each risk event and eventually to identify the top ten most critical risk events. Analysing data using appropriate techniques, the results are interpreted in light of previous findings in the literature. The paper concludes by highlighting the novelty and significance of the findings and discussed the limitations of the study.

Literature review

Risk and risk management

Risk has been expressed in different forms. Yet some key attributes, such as uncertainty, probability, effect/impact, and so on, consistently appear in many of these definitions. The ISO definition is one of the frequently referred definitions and stated as ‘risk is the effect of uncertainty on objectives’ (ISO Citation2018). The other common definition is that offered by PMI stated it in association with a project as ‘risk is an uncertain event or condition that, if it occurs, has a positive or negative effect on one or more project objectives’ (PMI Citation2013).

Many risks faced by businesses cannot be eliminated (Enshassi et al. Citation2006; Smith et al. Citation2006), hence, success is measured in terms of the effectiveness of the risk management (RM) approach adopted (Hillson Citation2012). RM, according to IRM (2002), is the process in which organisations methodically address the risks attaching to their activities to achieve sustained benefit within each activity and across the portfolio of all activities.

Although different approaches are used to describe RM steps, several of the RM frameworks involve some common basic stages. Upon reviewing the risk management processes provided in diverse literature, Goh and Abdul-Rahman (Citation2013) declared that risk planning, risk identification, risk analysis, risk response and risk monitoring and control are the well-accepted steps in the RM process. According to Zhao et al. (Citation2015) and Low et al. (Citation2009), the fundamental stages are risk identification, risk analysis, and risk response. Hence, this paper focuses on the three risk management steps, namely, the identification, analysis, and evaluation of risk events that may affect the performance of the EDCs.

Risk identification

Risk identification involves finding, recognizing, and recording risks that could affect the achievement of an organization’s objectives (BSI Citation2010; ISO Citation2018). According to FHWA (Citation2006), risk identification is conducted for two specific objectives: (i) to identify and categorize risks and (ii) to document the identified risks. Yet it is also important to note that, trying to identify all the risks, according to El-Sayegh (Citation2008), is time-consuming and counterproductive. As a result, literature, such as APM (Citation2008), suggests avoiding wasting time and resources on dealing with uncertainties that are of relatively low importance in terms of their effect on objectives. Subsequently, El-Sayegh (Citation2008) and Barkley (2004) have suggested focussing on identifying and dealing with the most significant risk events among all others.

Different tools and techniques are included in the literature to identify risks (APM Citation2008; BSI Citation2010; PMI Citation2013). Brainstorming, scenario planning, and expert interviews are among the many different approaches.

Risk analysis

Once the potential risk events are produced, the risk analysis follows, which examines each identified risk and determines risk scores. A probability – impact matrix is the most common and familiar risk analysis techniques (APM Citation2008) used to determine the relative risk scores (values) by multiplying the measures of probability and impact of the event (BSI Citation2010; Elmontsri Citation2013).

It is also commonly suggested to avoid wasting time and resources on analysis of uncertainties that are of relatively less importance in terms of their impact on the set objectives. The ultimate goal of risk analysis is, therefore, to prioritize risks (APM Citation2008; Ehsanifar and Hemesy Citation2019) that helps to extricate risks that matter most. Besides the APM (Citation2008) guideline has outlined two essential reasons for prioritizing risk: (1) to inform stakeholders of the range of outcomes arising from uncertainty, and (2) to prioritize risk responses for the effective management of risks.

Common risk events of construction companies in developing countries

In general, the construction industry is subject to a greater number of risk events with a higher impact on business operations than many other industries (Wang and Chou Citation2003; Enshassi et al. Citation2006; El-Sayegh Citation2008; Abd Karim et al. Citation2012). As discussed above, on one hand, many of these risks cannot be eliminated (Enshassi et al. Citation2006; Smith et al. Citation2006); on the other hand, trying to identify all risks, is time-consuming and counterproductive (El-Sayegh Citation2008). Hence, as suggested by El-Sayegh (Citation2008) and Barkley (2004), this study tries to identify the most significant risk events involved in the construction sector.

Risks events are commonly extracted from literature and experts’ opinions (Ehsanifar and Hemesy Citation2019). Thus, in a detailed review of 21 relevant studies conducted in 13 developing countries, risks involved in the construction industry were identified. Then, the identified risks were evaluated in the context of Ethiopia’s road sector. Ultimately, the 47 risk events summarized in were considered relevant for the EDCs involved in federal road construction projects.

Table 1. Summary of risk events.

As an integral part of risk identification, risk classification attempts to group the identified events (Zou, et al. Citation2007). A wide range of approaches has been employed for categorizing risk events in the construction industry. PMI (Citation2013), Yoon et al. (Citation2015), and Mishra and Mishra (Citation2016), for instance, categorized risks broadly as internal and external. More detailed and diverse classification approaches have been employed by other scholars as summarized in .

Table 2. Risk event taxonomy.

Taking this into account and through a review of multiple risk taxonomy frameworks, the identified risk events were categorised into three main groups, i.e. business environment, construction/operational, and site-related events. These categories were further broken down into subgroups as demonstrated in . Accordingly, the 47 risk events were grouped illustrated in .

Figure 1. Categories of risk events.

Figure 1. Categories of risk events.

Table 3. Risk events by category.

Methodology

The research was carried out in five distinct stages illustrated in . These are (1) identification and categorization of risk events by a detailed literature review; (2) determination of the probability of occurrence (P) of the identified risk events and their impact (I) using a questionnaire survey; (3) determination of the relative risk scores by combining the measures of probability and impact obtained in 2; (4) prioritization of the risk events based on the values obtained in 3; and (5) discussion of the ten most significant risk events obtained in 4.

Figure 2. Research Framework [Authors’].

Figure 2. Research Framework [Authors’].

As discussed above, 47 risk events were identified and categorized through a detailed literature review. Then, a questionnaire was developed to prioritise the identified risk events. This questionnaire was sent to professionals who have been directly involving in the implementation of federal road construction projects, namely, contractors (CNT), the client (CLT) (Ethiopian Roads Authority), and supervision consultants (CNS). The questionnaire contained two parts. The first part was aimed to gather information on the respondents’ profile whereas the second section was designed to evaluate the rates of the probability of occurrence (P) of each risk event and the severity of its impact (I) on the overall performance of domestic contractors. Participants were requested to rate the P and I using the five-level Likert scales (i.e. 1 for very low and 5 for very high). The respondents to be approached were obtained from ERA and the questionnaires were distributed by email to a total of 280 employees of these organizations. To get a more reliable date based on their adequate experience, professionals of five years and more experience were approached.

Using the responses received from questionnaires, risk scores, RSij assessed by respondent j for risk event i, were determined using EquationEquation (1). (1) RSji=Pj i× Iji (1)

Where, Pij = the probability of occurrence of a risk event i assessed by respondent j; and Iij = degree of impact of a risk event i (i = 1, 2, 3, 4 or 5), assessed by respondent j.

To determine the relative significance of each risk event, the approach advocated by Shen et al. (Citation2001); El-Sayegh (Citation2008); El-Sayegh and Mansour (Citation2015) was adopted. This risk ranking involves calculating a Relative Importance Index (RII) of each risk event, using EquationEquation (2). (2)  RIIi=j=1nRSjiV*N(2)

Where, V is the highest possible score available (i.e. V = 25, when Pij = Iij = 5) and N is the number of respondents. The above notwithstanding, it should be recognized that risks are dynamic in nature (FHWA Citation2006). Therefore, risk management is a continuous process, and it is advisable to frequently assess and risk ranks and to revise the mitigation measures accordingly.

A one-way between-group Analysis of Variance (ANOVA) was conducted on the information obtained from the questionnaires to test the hypothesis that there is no significant difference between respondents’ perceptions regarding the likelihood of occurrence and severity of risk events in the performance of EDCs. Following Chileshe and Yirenkyi-Fianko (Citation2011), the significance level (p-value) of the analysis was chosen to be 0.05. As suggested in Enshassi et al. (Citation2009), Kendall’s coefficient of concordance was also employed to measure the degree of agreement among the three parties, i.e. CNT, CNS, and CLT.

Result and discussion

Responses

As shown in , fully completed questionnaires were received from 137 participants (a return rate of 55%). This compares favourably with the findings of the study by Baruch and Holtom who attempt to analyse the response rate of 463 different studies performed using questionnaire surveys (Baruch and Holtom Citation2008). The study indicated an average response rate of 53% for studies conducted at the individual level and 37% for those performed at the organizational level.

Table 4. Breakdown of responses received.

As shown in , the highest number of responses (57, i.e. 41.6%) was received from experts with 10-15 years of experience in the road sector and 69.3% (95 of 137) of the partakers had the experience of ten years or more.

Table 5. Respondents by experience.

In terms of the position of the respondents, as shown in , the majority of respondents were engaged in decision making positions that would enable them to appreciate risks experienced within EDCs. For instance, of the professionals from the contractors’ side, 77.4% were project managers and 9.7% were technical managers who involve in project and company major decisions, respectively. Further, seven general managers and 44 project resident engineers were engaged from consultancy accounting for about 86.7% of the total professional. Similarly, 59.6% of the participants from the client-side were directors (19.2%) and project team leaders (40.4%).

Table 6. Respondents by position.

Relative significance and rank of risk events

Risk prioritization enables the identification of risks that matter most (Ehsanifar and Hemesy Citation2019). Accordingly, the RII values of risk events determined based on Equationequation 2 above, are shown in and along with their corresponding ranking. A range of literature (El-Sayegh and Mansour Citation2015; Iqbal et al. Citation2015; Jaber Citation2015) has regarded the first ten ranked risk events as the most critical risks that matter most. Accordingly, the ten top critical events listed in and are discussed herein below.

Table 7. Results of Relative Importance Index (RII) and ranks.

Table 8. Top 10 significant risk events.

Shortage of cash/cash flow problem

According to the prioritized results presented in and , the most significant risk event is a shortage of finance/cash flow problems (RII = 0.822). While professionals from the contractors ranked it as the fourth, experts both in the consultant and client part made it the first critical event. Since finance is a principal constraint in the construction industry, this finding could not be a surprise. Besides, this concurs with the findings reported by Koshe and Jha (Citation2016) and Mahamid (Citation2013) of the Ethiopian and Palestinian construction industries, respectively. Further Iqbal et al. (Citation2015) indicated that finance was the second significant risk event in Pakistani construction projects, while it was ranked the third critical event in the Ghanaian CI (Chileshe and Yirenkyi-Fianko Citation2011). Another study by Zewdu and Getachew (Citation2015) as well showed that this event is the fifth major risk event contributing to cost overruns in the Ethiopian CI.

Yet, the unavailability of affordable credit in developing countries reported in the UNECA (Citation2015) indicates that contractors have no alternatives that would enable them to address such financial shortcomings. Hence as suggested in UNECA (Citation2015), to be competitive domestically or internationally, construction firms need to have adequate access to finance.

Inadequate planning

Inadequate planning (RII = 0.804) was ranked as the second most critical risk event. This finding agrees with the study by El-Sayegh and Mansour (Citation2015) that showed that insufficient planning is the most critical risk factor in the UAE highway construction industry. It also supports the findings reported in Zewdu and Getachew (Citation2015) and Nega (Citation2008) of the Ethiopian building sector.

The time overrun experienced in the Ethiopian construction projects ranging from 61 − 80% reported by Ayalew et al. (Citation2016) might also be associated with the impracticability of project schedules. Besides, delay in delivery of materials, ranked as the sixth most critical risk event in this research, would have a direct association with poor planning (see below). The low level of use of planning techniques indicated by Zewdu (Citation2016), may contribute to the growing concern about planning insufficiency.

Lack of access to foreign currency

The third most critical risk event was found to be a lack of access to foreign currency (RII= 0.785) This event has been recognized by the Ethiopian government (NPC Citation2016) as a critical constraint to the socio-economic development of the nation. Unlike many of their international counterparts, domestic companies find it difficult to earn the foreign exchange needed to import construction equipment and materials. Such unavailability of access to foreign currency will put domestic contractors at a competitive disadvantage.

Delay in possession of the construction site

The fourth-ranked risk event is the delay in possession of the construction site (R = 0.766). In the Ethiopian federal road construction contracts, the responsibility to provide the construction site and burrow pits to the contractor is imposed upon the client. Nevertheless, the RSDP reports and other strategic documents (ERA Citation2011, Citation2015; NPC Citation2016) indicate that delay in removing obstructions from construction sites remains a common challenge for infrastructure development projects, including the road projects.

Whereas time is of the essence for the completion of projects. As a consequence, a delay in the removal of obstructions from construction sites would result in contractual implications among the contracting parties, majorly between the contractor and the client. Recognizing the impact of the event on the overall infrastructure developments, the National Planning Commission considers resolving the ROW problem amongst the core strategic objectives of the nation (NPC Citation2016). This study as well suggests that parties, the client, in particular, take corrective measures to mitigate this risk.

Frequent breakdown of equipment

Despite continuous monitoring and preventive equipment maintenance enable better use of available equipment (WEF Citation2016), frequent breakdown of construction equipment has been identified as the fifth major risk event (RII = 0.765). The major cause of the frequent breakdown of equipment according to Yoon et al. (Citation2015) is associated with poor equipment management. In the Ethiopian context, beyond the internal equipment management capability of firms, contractors’ financial capacity, and the availability of hard currency discussed above would also contribute to such problems. This suggests comprehensive and integrated action by the respective stakeholders in the sector.

The above top-five ranked risk events identified from the survey are followed by a delay in delivery of material and equipment (RII= 0.746), financial failure (RII = 0.734), inflation (RII = 0.670), delay in payments (RII = 0.632) and poor commitment and coordination within contracting teams (RII = 0.616). Yet it is important to keep in mind that some risk events that are found less significant in this study were reported as the top critical events in other studies.

Delay in delivery of materials and equipment

Delay in the delivery of materials and equipment/supply constraints is ranked as the sixth significant risk event. This was also recognized as impeding events in studies in Nigeria (Helen et al. Citation2015) and Ghana (Chileshe and Yirenkyi-Fianko Citation2011). While effective and efficient supply chain management enhances the construction performance (Gor and Pitroda Citation2015; Al-Werikat Citation2017), conversely, delays in supply have a considerable impact on companies’ success (Yoon et al. Citation2015). This suggests that construction companies take supply management as their key strategic tasks.

Financial failure

The risk event ranked seventh from the survey was a financial failure. Financial failure is the case in which a firm goes bankrupt as a consequence of not be able to fulfil its current liabilities (Zeytınoglu and Akarım Citation2013). Although this event appears to be at the bottom of the top ten risk events, it has been identified as one of the three major risk factors in studies conducted in some other countries. To name a few, a financial failure was reported as the third most important event in the Ghanaian construction industry (Chileshe and Yirenkyi-Fianko Citation2011). Mohammed (Citation2016) as well reported it the third most significant contractors’ related event in the Indian construction projects.

The first significant risk event identified in this study, i.e. shortage of finance, might attribute to such financial distresses. As advocated in (Mbachu Citation2011) the delay in payment, which is found to be the ninth-most critical risk event in this study (see below), might also contribute to such a problem. This suggests adopting an effective cash flow management strategy to address the risk.

Inflation

While inflation continues to be a major challenge in the country’s development (MOFED Citation2014; NPC Citation2016), it is perhaps a surprise that it is the eighth-most significant event for EDCs engaged in the road sector. Further, inflation has been reported as one of the major factors for the rise in construction costs in Ethiopia (MOFED Citation2014). Similar studies in Malaysian (Goh and Abdul-Rahman Citation2013), Indian (Kishan et al. Citation2014; Mohammed Citation2016), Ghanaian (Chileshe and Yirenkyi-Fianko Citation2011), Indonesian (Wiguna and Scott Citation2005) and Nigerian (Helen et al. Citation2015) construction industries reported inflation as the foremost ranked risk event. This may indicate that the price adjustment provisions included in the Ethiopian federal road construction contracts are adequate to compensate for the cost fluctuations that may affect contractors.

Delay in payment

Payment delay was ranked as the ninth significant event while it has been ranked as the most critical event in many other countries. For instance, it was found to be the second most critical event in Pakistan (Iqbal et al. Citation2015) and Ghana (Chileshe and Yirenkyi-Fianko Citation2011). Unlike other countries, the client's efforts to give priority in making payments to local contractors may be one of the many reasons why payment delay has fallen into the bottom of the top ten risk events of the road sector.

Lack of proper coordination and commitment within the contractors’ team

The tenth-ranked event is the lack of proper coordination and commitment within the contractors’ team. This threat has also been found as a critical risk in several other construction industries, including, Ghana (Ofori Citation2013) and India (Mishra and Mishra Citation2016). Despite this event appears to be the tenth risk factor, the important message is that there is still a large gap within the contractors’ respective team. A well-committed team ensures that they follow-through and stick with their projects to generate momentum and finish the job as intended, hence, contractors should work to create a sense of commitment and responsibility among employees.

Risks events with category

As can be seen from of the ten critical risk events, two are related to the business environment (i.e. strategic level) and the other eight to construction (i.e. the operational level) related events. Risk events classified under the third category (site condition related events) were found to be of lower significance. This suggests the need for risk management strategies to focus on strategic and operational risk events.

Significance of between groups

Analysis of Variance (ANOVA) was used to test whether any of the differences between the means are statistically significant. As illustrated in , the one-way ANOVA test gives F = 2.66 which is less than the critical value, Fcrit (3.06) at α of 0.05. Hence, the mean value is the same for all the three groups, i. e., there is no significant difference between the means of the groups and thus, the null hypothesis can be accepted.

Degree of agreement among responding groups

Kendall’s coefficient of concordance, W, was determined to measure the level of agreement among the three responding groups, namely contractors, consultants, and the client. And the calculated W = 0.93. Since n = 47 is too large for the tables of critical values of Kendall’s, the chi-square approximation of sample distribution of W is computed with EquationEquation (3). (3)  X2=m(n1)W(3)

Where, m = number of judges, n = the number of attributes being ranked. From the data of m = 3 and n = 47, X2 =128.4 which is greater than the critical chi value from the critical table for n = 47 and α = 0.05. Hence, the null hypothesis is rejected and the alternative hypothesis is accepted, i.e. there is a significant agreement among the three responding groups (contractors, consultants, and the client) to rank the 47 risk events.

Conclusions and recommendations

The objective of this paper was to identify and rank risk events that have a potential impact on the performance of Ethiopian domestic contractors working on federal road construction projects. From a detailed review of the literature, 47 possible events were identified and categorized into three groups, namely, (i) business environment, (ii) construction, and (iii) site related events. Using a questionnaire survey, this paper sought the perception of three primary parties (the client, contractors, and supervision consultants) that are involved in Ethiopian federal road construction projects. A total of 137 completed responses were received from the 248 distributed questionnaires with a response rate of 55.2%.

A Relative Importance Index (RII) was developed to assess the results of the survey and prioritise the identified risk events. Upon prioritizing the identified risk events in terms of their level of significance, the ten most important risk events were identified. These are cash flow problem, inadequate planning, lack of access to foreign currency, delay in possession of site (ROW), frequent breakdown of equipment, delay in delivery of material and equipment, financial failure, inflation, delay in payments and poor commitment and coordination within the contractors’ team. These findings are broadly in agreement with other similar studies conducted in other developing countries, although the survey suggested that delays in payment and inflation risk events were considered to be less important in the Ethiopian context than in other countries. A statistical analysis of the results as well showed that there is no significant difference between the three groups and there is a strong agreement among the parties in ranking risk events.

Since the majority of the significant risk events are related to the business environment and operational issues, this research highlights the need for broad-based measures from all stakeholders in the sector. Of greatest importance, is that the government creates a conducive business environment for local contractors. The client should also work to meet its contractual obligations, including to provide access to site and effect payments in a timely manner. Contractors should strive to adopt and implement appropriate risk management systems to effectively mitigate their risks.

Whilst efforts have been spent on designing and carrying out the research, there are some limitations associated with the study. First, since risks are dynamic, ranking of risks provided herein may vary over time. Furthermore, since the risk identification and analysis was conducted for contractors working in the road sector as a whole, hence, the level of significance of risks may vary from contractor to contractor. Consequently each contractor should regularly assess its own risk and adopt appropriate mitigation measures. Whilst the research has focused on Ethiopia, the findings are relevant to domestic construction firms working in other developing countries, and highlight in particular the challenges and risks that such companies face.

Acknowledgements

The authors are most grateful for the practical and financial support of the Ethiopian Roads Authority, the World Bank, the European Union, and the Africa Development Bank. We also thank the professionals who responded to the questionnaires. The Department of Civil Engineering at the University of Birmingham which facilitated the work is acknowledged with gratitude.

Disclosure statement

No potential conflict of interest was reported by the authors.

Additional information

Funding

This work was funded by African Development Bank Group; European Commission; World Bank Group.

References

  • Abd Karim NA, Abd Rahman I, Abd Azis AA. 2012. Significant risk factors in construction projects: contractors’ perception. IEEE Colloquium on Humanities, Science & Engineering Research (CHUSER 2012), Kota Kinabalu Sabah, Malaysia, Dec 3–4; IEEE; p. 347–350.
  • AfDB. 2018. African Economic Outlook 2018. Africa Development Bank.
  • Al-Werikat G. 2017. Supply chain management in construction revealed. Int J Sci Technol Res. 6(3):106–110.
  • ANDI. 2006. The importance and allocation of risks in Indonesian Construction Projects. Constr Manage Econ. 8:69–80.
  • APM. 2008. Prioritising project risks: A short guide to useful techniques. Princes Risborough: Association for Project Management.
  • Ayalew T, Dakhlii Z, Lafhaj Z. 2016. Assessment on performance and challenges of Ethiopian construction industry. J Architect Civil Eng. 2(11):11.
  • Baruch Y, Holtom BC. 2008. Survey response rate levels and trends in organizational researches. Hum Rel. 61(8):1139–1160.
  • Befrouei MAR, Taghipour M. 2015. Identification and management of risks in construction projects. Am J Civil Eng. 3(5):170–177.
  • BSI. 2010. Risk management risk assessment techniques: EN31010:2010. UK: British Standards Publication.
  • Chileshe N, Yirenkyi-Fianko AB. 2011. Perceptions of threat risk frequency and impact on construction projects in Ghana: opinion survey findings. J Constr Developing Countries. 16(2):115–149.
  • Desta SS. 2015. The management of construction process in developing countries: a case study of Ethiopian roads authority [PhD thesis]. Cape Town: University of Cape Town.
  • Ehsanifar M, Hemesy M. 2019. A new hybrid multi-criteria decision-making model to prioritize risks in the construction process under fuzzy environment (case study: the Valiasr Street underpass project). Int J Constr Manage. DOI: 10.1080/15623599.2019.1569816.
  • Ekung S, Adeniran L, Adu E. 2015. Theoretical risk identification within the Nigeria East-West Coastal Highway Project. Civil Eng Urban Plan: Int J. 2(1):1–11.
  • El-Sayegh SM. 2008. Risk assessment and allocation in the UAE construction industry. Int J Project Manage. 26(4):431–438.
  • El-Sayegh SM, Mansour MH. 2015. Risk assessment and allocation in highway construction projects in the UAE. J Manage Eng. 31(6):431–438.
  • Elmontsri M. 2013. Review of the strengths and weaknesses of risk matrices. J Risk Anal Crisis Response. 4(1):49–57.
  • Emuze F, Kadangwe S. 2014. Diagnostic view of road projects in Malawi. Proc Inst Civil Eng. 167(1):44–55.
  • Enshassi A, Al-Hallaq K, Mohamed S. 2006. Causes of contractor's business failure in developing countries: the case of Palestine. J Constr Developing Countries. 11(2):1–14.
  • Enshassi A, Mohamed S, Abushaban S. 2009. Factors affecting the performance of construction projects in the Gaza Strip. J Civil Eng Manage. 15(3):269–280.
  • ERA. 1996. Road Sector Development Program (1997-2002) final report. Addis Ababa: The Federal Democratic Republic of Ethiopia, Ethiopian Roads Authority.
  • ERA. 2011. Road Sector Development Programme (RSDP). RSDP 13 years performance and phase IV. Addis Ababa: Ethiopian Roads Authority.
  • ERA. 2015. The Road Sector Development Program Phase IV. Addis Ababa: Ethiopian Roads Authority.
  • ERA. 2016. Road Sector Development Programme 19 years performance assessment report. Addis Ababa: Ethiopian Roads Authority.
  • Fernando CK, Hosseini MR, Zavadskas EK, Perera BAKS, Rameezdeen R. 2017. Managing the financial risks affecting construction contractors: implementing hedging in Sri Lanka. Int J Strat Prop Manage. 21(2):212–224.
  • FHWA. 2006. A guide to risk assessment and allocation for highway construction management. Washington (DC): Federal Highway Administration, U.S. Department of Transportation.
  • Goh CS, Abdul-Rahman H. 2013. The identification and management of major risks in the Malaysian construction industry. J Constr Developing Countries. 18(1):19–32.
  • Gohar AS, Khanzadi M, Farmani M. 2012. Identifying and evaluating risks of construction projects in fuzzy environment: a case study in Iranian construction industry. IJST. 5(11):1–3602.
  • Gor D, Pitroda J. 2015. The impact of supply chain management practice on construction project performance in the central Gujarat. Int J Tech Innov Modern Eng Sci. 4(5):269–275.
  • Helen BI, Emmanuel OO, Lawal A, Elkanah A. 2015. Factors influencing the performance of construction projects in Akure, Nigeria. Int J Civil Eng Constr Estate Manage. 3(4):57–67.
  • Hillson D. 2012. Risk management or risk leadership? PM World J. 1(2):1–3.
  • Iqbal S, Choudhry RM, Holschemacher K, Ali A, Tamošaitienė J. 2015. Risk management in construction projects. Technolog Econ Dev. 21(1):65–78.
  • ISO. 2018. ISO 31000: Risk management - guidelines. 2nd ed. Geneva: International Standards Organization.
  • Jaber FK. 2015. Establishing risk management factors for construction projects in Iraq. Int J Adv Res Eng Technol. 6(1):35–48.
  • Jayasudha K, Vidivelli B. 2016. Analysis of major risks in construction projects. ARPN J Eng Appl Sci. 11(11):6943–6950.
  • Kishan P, Bhatt R, Bhavsar J. 2014. A study of risk factors affecting building construction projects. Int J Eng Res Technol. 3(12):831–835.
  • Koshe W, Jha KN. 2016. Investigating causes of construction delay in Ethiopian construction industries. J Civil Constr Environ Eng. 1(1):18–29.
  • Low SP, Liu JY, He SQ. 2009. External risk management practices of Chinese construction firms in Singapore. KSCE J Civil Eng. 13:85–95.
  • Mahamid I. 2013. Common risks affecting time overrun in road construction projects in Palestine: contractors’ perspective. CEB. 13(2):45–53.
  • Mbachu J. 2011. Sources of contractor’s payment risks and cash flow problems in the New Zealand construction industry: project team’s perceptions of the risks and mitigation measures. Constr Manage Econ. 29(10):1027–1041.
  • Mishra S, Mishra B. 2016. A study on risk factors involved in the in construction projects. Int J Innov Res Sci Eng Technol. 5(2):1190–1196.
  • MOFED. 2002. Ethiopia: sustainable development and poverty reduction program. Addis Ababa: Federal Democratic Republic of Ethiopia, Ministry of Finance and Economic Development.
  • MOFED. 2014. Growth and transformation plan annual progress report for F.Y 2012/2013. Addis Ababa: Federal Democratic Republic of Ethiopia Ministry of Finance and Economic Development.
  • Mohammed AJ. 2016. A study for significant risks and their effects on construction projects in Erbil City. J Eng Sustain Dev. 20(04):96–115.
  • Nega F. 2008. Causes and effects of cost overrun on public building construction projects in Ethiopia [MSc thesis]. Addis Ababa: Addis Ababa University.
  • NPC. 2016. Growth and Transformation Plan II (GTP II). Addis Ababa: Federal Democratic Republic of Ethiopia, National Planning Commission.
  • Ofori DF. 2013. Project management practices and critical success factors–a developing country perspective. Int J Bus Manage. 8(21):14–31.
  • PMI. 2013. A Guide to the project management body of knowledge. 5th ed. Newtown Square: Project Management Institute.
  • Shen LY, Wu GWC, Ng CSK. 2001. Risk assessment for construction joint ventures in China. J Constr Eng Manage. 127(1):76–81.
  • Siraw YT. 2016. Analysis of factors contributing to time overruns on road construction projects under Addis Ababa City Administration. Int J Sci Res (IJSR). 5(7):2181–2187.
  • Smith NJ, Merna T, Jobling P. 2006. Management risk in construction projects. Oxford: Blackwell Science Ltd.
  • UNECA. 2015. Enhancing domestic private sector development in Africa: construction and energy sectors. Addis Ababa: United Nations Economic Development for Africa.
  • Wang M-T, Chou H-Y. 2003. Risk allocation and risk handling of highway projects in Taiwan. J Manage Eng. 19(2):60–68.
  • Wang SQ, Dulaimi MF, Aguria MY. 2004. Risk management framework for construction projects in developing countries. Constr Manage Econ. 22(3):237–252.
  • WEF. 2016. Shaping the future of construction: a breakthrough in the mindset and technology. Geneva: World Economic Forum.
  • Wiguna IPA, Scott S. 2005. Nature of the critical factors affecting project performance in Indonesia building contracts. In SOAS, September 7–9. University of London. Association of Researchers in Construction. p. 225–235.
  • Yimam AH. 2011. Project management maturity in the construction industry of developing nations (the case of Ethiopian contractors) [MSc thesis]. University of Maryland.
  • Yoon Y, Tamer Z, Hastak M. 2015. Protocol to enhance profitability by managing risks in construction projects. J Manage Eng. 31(5):04090-1_10.
  • Zewdu ZT. 2016. Construction projects delay and their antidotes: the case of Ethiopian construction sector. Int J Bus Econ Res. 5(4):113–122.
  • Zewdu ZT, Getachew TA. 2015. Causes of contractor cost overrun in construction projects: the case of Ethiopian construction sector. Int J Bus Econ Res. 4(4):180–191.
  • Zeytınoglu E, Akarım YD. 2013. Financial failure prediction using financial ratios: an empirical application on Istanbul stock exchange. J Appl Finance Banking. 3(3):107–117.
  • Zhao X, Hwang BG, Low SP. 2015. Enterprise risk management in construction firms: a proposed implementation framework. In: Shen L, Ye K, Mao C, editors. Proceedings of the 19th International Symposium on Advancement of Construction Management and Real Estate. Berlin, Heidelberg: Springer. DOI: 10.1007/978-3-662-46994-1_75.
  • Zou PX, Zhang G, Wang J. 2007. Understanding the key risks in construction projects in China. Int J Project Manage. 25(6):601–614.