Lean thinking for a maintenance process

, , , &
Pages 236-272 | Received 26 Jan 2015, Accepted 15 Jul 2015, Published online: 14 Aug 2015

Abstract

The maintenance process shares significant operating costs in an organisation. Lean thinking can be incorporated into maintenance activities through applying its principles and practices/tools. Lean maintenance (LM) is a prerequisite for lean manufacturing systems. This research proposes a new structure for LM process based on a systematic literature review of a significant number of related articles that were published on LM. The process structure is designed based on the five lean principles to guide and support organisations to pursue maintenance excellence. This study establishes a scheme for LM tools that are structured into 2 level 4 bundles and 26 lean practices/tools and develops a House of Waste (HoW) to demonstrate the association between maintenance wastes and the LM tools. With a successful accomplishment of the proposed scheme, the performance of a maintenance department can create more improvement opportunities over time to reach the maintenance excellence status.

1. Introduction

Maintenance function becomes a significant contributor towards to achieve strategic objectives of an organisation in today’s competitive markets (Fraser, Citation2014). The maintenance process is to serve the production facilities of high productivity. It comprises planned and unplanned actions carried out to retain a physical asset to the acceptable operating conditions (Faccio, Persona, Sgarbossa, & Zanin, Citation2014). Maintenance aims at increasing the value of the reliability, safety, availability, and quality of an asset (e.g. production plant, equipment, or building) with acceptable economical costs (Márquez, Citation2007). Over the last decades, the maintenance has been considered as a necessary evil from the organisational management as the maintenance operation is limited to corrective functions that are usually executed under the emergency situations such as machine breakdown. However, this practice is no longer acceptable since the role of maintenance has been recognised as a strategic element of revenue generation for organisations. The maintenance with role creates a significant impact on some critical elements in production plants such as product quality, safety requirements, and operating budget levels (Khazraei & Deuse, Citation2011).

The cost of maintenance activities could be ranged from 15 to 70% of the total production costs (Fraser, Citation2014; Pinjala, Pintelon, & Vereecke, Citation2006). This is the second largest part, after energy costs, of the operational budget. In the United States, the estimated cost of maintenance increased from $200 billion in 1979 to $600 billion in 1989 (Bevilacqua & Braglia, Citation2000). Maintenance activities account for an average 28 per cent of the total cost of finished goods (Blanchard, Citation1997). One of the reasons for such significant portion of maintenance of the total operation cost is that the machinery has become highly automated and technologically very complex. For example, usually, the modern operation systems depend on sensor-driven management systems that provide alerts, alarms, and indicators. Consequently, maintenance costs are expected to be even higher in future. Generally, the maintenance costs are proportional to the downtime (DT). The DT is the time interval when equipment/system is down for maintenance until it is back to the normal working conditions (Tinga, Citation2013). The increased DT is caused by the non-value added (NVA) activities or wastes within the entire maintenance process. One of waste elimination strategies is the application of lean thinking in all activities between suppliers and customers (value stream). Integrating lean thinking in maintenance is known as lean maintenance (LM). Baluch, Abdullah, and Mohtar (Citation2012) emphasised that LM is prerequisite for success of a lean manufacturer as it provides a holistic approach to the function of maintenance. In general, the lean integration in any process is carried through adopting lean principles which begins with specifying the customer value (Bhasin, Citation2015). In the maintenance environment, any maintenance service could be considered as a final intangible product. The service is provided to a customer which, in this case, could be assumed as an asset (e.g. production line). Therefore, it is essential to identify the value from the asset perspective which can be improving its availability and reliability through efficient maintenance. Then, mapping the maintenance value stream which fundamentally consists of all the collective activities to deliver the maintenance service. Later, improving the maintenance value stream by abolishing the waste which assist in minimising the lead time (in this case is DT).

Investigation into the applicability of lean principles in maintenance in the existing research is still at a marginal level. Davies and Greenough (Citation2010) emphasis on the necessity for more researches to apply lean principles to maintenance operations. Ghayebloo and Shahanaghi (Citation2010) formulate a multi-objective decision-making (MODM) model that can determine the minimal level of maintenance requirements (i.e. labour and spare parts) which satisfies expected reliability level with the use of the lean concept. Tendayi and Fourie (Citation2013) use a combined approach of quality function deployment (QFD) and analytic hierarchy process (AHP) to evaluate the importance of a set of maintenance excellence criteria and prioritise the lean tools against these criteria. Soltan and Mostafa (Citation2014) introduce a framework for measuring maintenance strategies based on lean and agile components, i.e. waste removal and responsiveness. The study of McCarthy and Rich (Citation2004) discussed lean total productive maintenance system (or lean TPM) which conceptualises the application of lean-specific techniques in TPM. The system is focused on maintaining equipment in its optimal operational state and continually improving its productivity. However, an integrative structure of lean thinking or lean TPM (e.g. principles, practices/tools, waste identification, and value stream mapping (VSM)) within the maintenance activities has not been fully established. This provides an opportunity for this study to develop and propose a process for lean thinking to be integrated to the maintenance operation. The process is formulated according to the hypothesis of Womack and Jones (Citation2003) stating that lean principles can be applied to any sector.

This study carried out a systematic literature review following Denyer and Tranfield (Citation2009) approach. The review was conducted to identify and understand the existing literature on LM and evaluate contributions and summarise knowledge, thereby, identifying potential directions of future research. The grand electronic databases were explored to gather the literature on LM. A total of 43 related articles published between 2000 and 2014 have been included in this study.

This study is organised as follows. Section 2 provides an overview on maintenance and lean manufacturing concepts. Sections 3 and 4 demonstrate the aim, objectives, and methodology of the proposed research. Section 5 discusses the LM and LM practices/tools. In Section 6, a LM process is proposed with the discussion of the five stages of the lean process in maintenance and introduction of the LM scheme including four bundles and 26 lean tools. The section also demonstrates the relationships between maintenance wastes and lean tools using House of Waste (HoW). Section 7 highlights benefits of the proposed LM process and Section 8 concludes the study with some directions of future research.

2. Maintenance and lean manufacturing

2.1. Lean manufacturing

The word lean in manufacturing means the efficient use of the available resources by cutting the NVA activities or wastes (Carrasqueira & Machado, Citation2008). Lean manufacturing represents a collection of tools that work together synergistically to create a streamlined, high-quality system that produces finished products at the same pace of the customer demand (Shah & Ward, Citation2007). Waste in lean manufacturing is defined as any activities that add cost to a product/service without adding values from a customer’s perspective. It may be classified to three major types: unobvious waste, less obvious waste, and obvious waste (Hopp & Spearman, Citation2004). De Treville and Antonakis (Citation2006) list examples of obvious waste as unnecessary inventory, unneeded processes, excessive set-up times, unreliable machines, and rework. They also argue that the less obvious waste occurs due to the various reasons such as process times, delivery times, yield rates, staffing levels, and demand rates.

In recent decades, lean system is gaining a momentum across different industrial sectors. It has been originally started as Toyota production system which describes the manufacturing philosophy of Toyota Motor Corporation (Dombrowski & Malorny, Citation2014; Holweg, Citation2007; Womack & Jones, Citation2003). This lean system has been successfully extended to service industries, such as maintenance service, retail banking, airlines, restaurants, public sector, education, food, and hospitals (Burgess & Radnor, Citation2013; George, Citation2003; Pedersen & Huniche, Citation2011; Resta, Powell, Gaiardelli, & Dotti, Citation2015; Smith & Hawkins, Citation2004; Thirkell & Ashman, Citation2014; Zarei, Fakhrzad, & Jamali Paghaleh, Citation2011). As an example, in the health care sector, hospitals achieved high-quality health care outcomes (e.g. recorded lower 30-day mortality rates) by applying lean management practices (McConnell, Lindrooth, Wholey, Maddox, & Bloom, Citation2013). Clearly, the implementation of lean concept in diverse sectors proves to be true Womack and Jones (Citation2003) hypothesis stating that lean principles can be transferred to any organisation. They coined this process as lean thinking which refers to the thinking process of lean inside an organisation and its extended supply chain. This means that within the same organisation, lean thinking should be extended from the shop floor or production level to other areas such as maintenance department. The key behind this lean thinking is that service/maintenance departments and production processes are inseparable and complement each other to sustain the competitive edge of an organisation.

2.2. Maintenance strategies

Maintenance includes all activities required to keep an asset at maximum operating condition. The activities are usually carried out according to a certain maintenance strategy. The maintenance strategies may have developed accordingly with the development of manufacturing systems (Shahin, Shirouyehzad, & Pourjavad, Citation2012). In the early days, maintenance had been mainly concentrated around corrective maintenance, for example, repairs and replacements were conducted when needed with no optimisation strategy and there was no or little consideration of the DT. More recently, maintenance became a full-scale function, instead of a sub-function of the whole production operation. Today, maintenance management becomes a complex function, encompassing technical and management skills, while still requiring flexibility to cope with the dynamic business environment (Lee & Wang, Citation2008). Maintenance strategies have gradually changed from preventive maintenance (PM) (including condition-based maintenance (CBM) and time-based maintenance (TBM) to design-out maintenance (DOM) and total productive maintenance (TPM) as demonstrated in Figure .

Figure 1. Types of maintenance strategies.

Figure 1. Types of maintenance strategies.

The classification of the maintenance strategies shown in Figure is based on the time of maintenance activities and failure that requires maintenance (Potes Ruiz, Kamsu Foguem, & Grabot, Citation2014). The maintenance activities are only performed after the failure occurrence in the corrective maintenance strategy. Whereas, in the PM, the intervention of maintenance activities is conducted before the failure occurrence. Maintenance strategies have been diversely used in the existing literature using similar terms such as preventive, predictive, planned, corrective, and TPM. The most common three maintenance strategies are discussed below.

2.2.1. Corrective maintenance

Corrective maintenance is known as failure-based maintenance, emergency maintenance, fire-fighting maintenance, or breakdown maintenance as the concept of corrective maintenance strategy is based on fix-it when broke (Márquez, Citation2007). Corrective maintenance is a conventional maintenance strategy appeared early in the industry. It has been employed in maintenance operations due to knowledge shortage on the equipment failure behaviours (Waeyenbergh & Pintelon, Citation2002). Corrective maintenance can be carried out immediately or deferred by appropriate maintenance technicians whom are contracted to assess the situation and fix the repairs. In situations where the failure is not critical (i.e. plenty of DT is available) and the values of the assets are not of a great concern, the corrective mode of maintenance may prove to be an acceptable option. However, the market competition, environmental and safety issues force the maintenance managers to search for more efficient maintenance strategies besides the corrective maintenance (Shahin et al., Citation2012).

2.2.2. Preventive maintenance

PM is carried out according to prescribed criteria. It intends to reduce the probability of failure or the degradation of the functioning of an item (Fouladgar, Yazdani-Chamzini, Lashgari, Zavadskas, & Turskis, Citation2012). PM can be divided into TBM and CBM. In TBM, the maintenance activities are performed based on fixed operating time interval or number of output units without considering the current condition state of the item. On the other hand, CBM is based on performance and/or parameter monitoring (e.g. corrosion and electric current monitoring, lubricant and vibration analysis, leak and crack detection, and ultrasonic testing) (Al-Najjar & Alsyouf, Citation2003; Khazraei & Deuse, Citation2011). CBM could be described as a process that integrates technology and human skills using a combination of all available diagnostic and performance data, maintenance history, operator logs, and design data to determine the likelihood of a potential failure. As a result, CBM requires a high initial cost to acquire and install the necessary sensors as well as to monitor technology (Hellingrath & Cordes, Citation2014; Nezami & Yildirim, Citation2013).

2.2.3. Design-out maintenance

DOM focuses on improving the design of a product in order to eliminate the cause to maintenance. DOM makes maintenance easier during the life cycle of a product (Waeyenbergh & Pintelon, Citation2004). DOM is based on the successive design corrections derived from the maintenance knowledge. It is appropriate for items with high maintenance cost, which arises because of defective design or operation outside design specifications. The DOM concept is used in some parts of motor vehicles such as permanent bearing (bearing using solid lubricant and permanently sealed) (Gopalakrishnan & banerji, Citation2013).

2.3. TPM and lean thinking

TPM is a concept developed in Japan, which could be defined as a productive maintenance that involves total participations meaning all employees across the whole levels of the operational hierarchy (Cua, McKone, & Schroeder, Citation2001; Jasiulewicz-Kaczmarek, Citation2013). It attempts to eliminate any losses in equipment and production efficiency through active team-based participation. Waeyenbergh and Pintelon (Citation2002) identified the six categories of losses in TPM: (1) breakdown losses; (2) set-up and adjustment losses; (3) minor stoppage/idling losses; (4) reduced speed losses; (5) defects/rework losses; (6) start-up losses. The first two losses refer to time losses and influence equipment availability. The third and fourth losses denote speed losses and measure the equipment performance efficiency. The last two losses designate the quality of production process and are used to calculate the quality rate of the equipment (Chan, Lau, Ip, Chan, & Kong, Citation2005). The effectiveness of TPM strategy with regard to these six losses is measured using overall equipment effectiveness (OEE). The measurement of OEE is a function of the availability, performance efficiency, and quality. TPM entails eight main elements/pillars that can be considered as principles/tools of TPM in an organisation.

Autonomous maintenance

Performance improvement

Early equipment management

Planned maintenance

Environment health and safety

Office TPM

Education and training

Quality maintenance

The detailed description of these pillars mentioned above is presented in Ahmed, Hassan, and Taha (Citation2005) and Chong, Chin, and Hamzah (Citation2012). The TPM pillars can be collectively used to improve equipment availability and reliability. However, according to Baluch et al. (Citation2012), removing or missing application of any pillars could lead to unattainable results. Likewise, the lack of comprehensive approach for the TPM implementation has resulted in a decrease of 50% TPM initiatives in US. Moreover, there are some deficiencies related to the TPM strategy. TPM concerns the operational issues that handle equipment failures rather than long‐term strategic business issues. Levitt (Citation2008) stated that TPM is no longer lean as it focuses primarily on the operational issues of equipment and it would take a long time to implement. Moreover, EPA (Citation2015) highlighted that TPM failed to consider the environmental aspects during equipment efficiency improvement. This leaves potential waste minimisation and pollution prevention opportunities to be more researched.

While referring to major literature on TPM, it was observed that there is a link between TPM and lean as well as LM emerged as an effective maintenance strategy. Levitt (Citation2008) mentioned that TPM and lean are broadly linked. This is clear in some of the literature that considered TPM as a subsection of lean system which mainly focused on enhancing the efficiency and availability of the manufacturing facilities. For instance, Shah and Ward (Citation2003) postulated 21 manufacturing practices as the key features of lean system. They grouped the inter-related and internally consistent practices into bundles. TPM was one bundle which contained four practices: PM, maintenance optimisation, new process equipment, and safety improvement. These four practices sound very generic and not provide practitioners what tools to undertake the maintenance optimisation, or new process equipment. Another study by Mostafa (Citation2011) extended the TPM practices, suggested by Shah and Ward (Citation2003), to include housekeeping, cross-training and teams of maintenance technicians, operator involvement (autonomous maintenance), and information tracking of the work orders. Clearly, these suggested practices indicated another dimension of TPM in lean system by considering human resource perspective. Abdulmalek, Rajgopal, and Needy (Citation2006) gathered 14 lean tools into three areas: quality, production process, and methods. TPM was located under quality area which can be considered as another perspective for TPM in lean environment. It can be concluded that TPM is considered as the foundation for the maintenance process in lean environment which must be supplemented with some lean practices. That is why some studies coined relatively new terms like lean TPM (Georgescu, Citation2010; McCarthy & Rich, Citation2004) and LM (Baluch et al., Citation2012; Okhovat, Ariffin, Nehzati, & Hosseini, Citation2012; Romano, Murino, Asta, & Costagliola, Citation2013; Smith & Hawkins, Citation2004).

LM principles take its lead from lean manufacturing through applying some new techniques to TPM concepts to render a more structured implementation path (Levitt, Citation2008; McCarthy & Rich, Citation2004; Romano et al., Citation2013; Smith & Hawkins, Citation2004). It is a prerequisite for success as a lean manufacturer that provides a holistic approach to the function of maintenance (Baluch et al., Citation2012; Soltan & Mostafa, Citation2014). As lean concept has been taking hold in the manufacturing sector, there is an increasing insight that maintenance must not be seen only from narrow operational perspective dealing with equipment failures and their consequences. Instead, maintenance must be viewed in the long-term strategic perspective and must integrate the different technical and commercial issues in an effective manner. However, LM approach cannot just be a mirror image of a lean manufacturing approach because the business dynamics of asset maintenance and those of production are fundamentally different (Baluch et al., Citation2012; Brown, Collins, & McCombs, Citation2006; Clarke, Mulryan, & Liggan, Citation2010). Therefore, it is clear that there is a need to develop an effective process to collectively integrate lean thinking into the maintenance with long-term strategic perspective. This study addresses such an issue to cover the major deficiencies in the existing literature.

3. Research aim and objectives

This research aims to adopt lean principles and practices/tools and collectively integrate them into the maintenance process. It has adopted recommendations of previous research works such as a study of Davies and Greenough (Citation2010) that emphasised on the necessity of conducting more research in application of lean manufacturing principles in maintenance operations. To achieve the main aim of this research, four main objectives have been established:

(1)

To review the LM concept.

(2)

To develop a process for adopting lean principles into maintenance processes.

(3)

To document the maintenance wastes and establish a scheme of lean practices/tools applied to maintenance.

(4)

To develop the HoW that demonstrates the association of lean tools with the maintenance wastes.

4. Research methodology

To achieve the research objectives, this study employed a systematic review of the literature in order to explore major publications related to lean manufacturing and maintenance concepts, especially research works published from 2001 to 2014. Okoli and Schabram (Citation2010) indicate that a systematic literature review is a systematic, explicit, comprehensive, and reproducible method for identifying, evaluating, and synthesising the existing body of completed and recorded work produced by researchers, scholars, and practitioners. According to Denyer and Tranfield (Citation2009), the systematic literature review has become an essential scientific activity.

From the literature review, it has been found that exploration of the applicability of lean principles in maintenance in the existing research works is minimal. Davies and Greenough (Citation2010) and Soltan and Mostafa (Citation2014) state the necessity of conducting more research on applying lean principles in maintenance operations. As an initial step of this research, a seven-step systematic literature is conducted as summarised in Figure to demonstrate development of the proposed LM process. It is noted that these research steps are adapted from several academic sources, such as Joffe (Citation2011), Okoli and Schabram (Citation2010), and Tranfield, Denyer, and Smart (Citation2003).

Figure 2. Research methodology framework.

Figure 2. Research methodology framework.

4.1. Research selection criteria

The research inclusion and exclusion criteria are very critical to the quality assessment of papers (Booth, Papaioannou, & Sutton, Citation2012). Okoli and Schabram (Citation2010) indicated that simplifying research using these criteria (by reviewing the title and then the abstract when needed) saves the researcher time and effort. In this study, the authors examined research articles by title and then abstracts. In the systematic review of this study, the criteria were addressed in order to clarify the selection of the research-related articles. The following criteria have been considered to include/ exclude the articles:

Articles published between 2001 and 2014 as the rational for considering the year 2001 is that LM as a field of research was firstly addressed by Davies and Greenough (Citation2001)

Search for articles published in peer-reviewed scientific journals or conference proceedings

Ensure essential relevance by requiring that selected articles contain at least one of the search keywords in the title or abstract (see Table )

Search well-known online databases which are Taylor & Francis, EBSCO, Emerald, IEEE, Inderscience, ProQuest, Sage, Science Direct, and Springer Link

Table 1. Research primary and secondary keywords.

5. Development of LM in the literature

The screened LM studies are dated from 2001 to 2014 with the total number of 43 retrievable publications as shown in Table .

Table 2. Review of existing literature on lean maintenance.

The selection of published LM studies shows that most of the studies were published in the year 2014 and focused on three aspects, namely LM implementation initiative, suggested lean tools, and interrelationship within LM application as illustrated in Figure .

Figure 3. Distribution of lean maintenance studies.

Figure 3. Distribution of lean maintenance studies.

From the review of 43 publications, the focus on the LM implementation has been continuously growing since 2011 for general practice and specific industries. The suggested lean tools and interrelationship within the LM initiatives were not in parallel with the LM implementation. The LM tools were found in 18 publications. None of these publications provided a complete set of lean tools. Only two publications in 2012 and 2013 demonstrated the interrelationship within LM application. The low volume of publications indicates that more research in LM is crucially needed, especially in establishing a logical interrelationship between LM concepts and implementation and a complete set of LM tools.

5.1. Lean maintenance

LM term was coined in the last decade of the twentieth century. Smith (Citation2004) defines LM as a proactive maintenance operation employing planned and scheduled maintenance activities through TPM practices using maintenance strategies developed through application of reliability-centred maintenance (RCM) decision logic and practiced by empowered (self-directed) action teams. LM generates a desirable outcome by minimising consumption of inputs (Smith & Hawkins, Citation2004). LM represents adopting lean principles into the maintenance, repair, and overhaul (MRO) operations. It could reduce unscheduled DT through optimising maintenance support activities and maintenance overhead. The lean tools are representing the lean principles for the implementation process (Mostafa, Dumrak, & Soltan, Citation2013). To achieve LM improvement effectively, key lean tools such as VSM, 5S, and visual management need to be employed (Smith, Citation2004; Smith & Hawkins, Citation2004). A comprehensive lean tools developed for maintenance activities within an organisation include 5S, TPM, OEE, Kaizen, Poka-Yoke, process activity mapping, Kanban, computer managed maintenance system (CMMS), enterprise asset management (EAM) system, and Takt time (Davies & Greenough, Citation2010; Smith, Citation2004).

Despite the benefits of LM mentioned earlier, the review of previous studies conducted in this study found that the investigation on the applicability of lean principles into maintenance is marginal. The existing research works have been largely limited to the manufacturing environment where LM is practised as a prerequisite for lean manufacturing (Tendayi, Citation2013). This proposition has been mentioned in Davies and Greenough (Citation2010) emphasising on the necessity of conducting more research on practical application of lean manufacturing principles in maintenance operations. It was discovered that the previous studies mainly focused on ranking the maintenance strategies based on some specific scope. Moreover, few initiatives have included comprehensive frameworks or models that can integrate lean thinking in operational maintenance environments outside of the manufacturing context. Ghayebloo and Shahanaghi (Citation2010) formulate a model for determining the minimal level of maintenance requirements and satisfying reliability level through the use of the lean concept. Tendayi and Fourie (Citation2013) use a combined approach between QFD and AHP to evaluate the importance of maintenance excellence criteria and prioritise the lean tools upon these criteria. The recent study of Soltan and Mostafa (Citation2014) introduces a framework for measuring maintenance strategies based on lean and agile components, i.e. waste removal and responsiveness. However, the study cannot provide sufficient practical application of lean concept in the maintenance process. Romano et al. (Citation2013) formulate lean root cause and defect analysis (LRCDA) to reduce scraps and work-in-process in manufacturing system. Nevertheless, the LRCDA model introduced is based on RCDA (not lean principles) as well as contains limited lean practice within the model. The paucity of practical application in the existing LM studies provides an opportunity for this study to expand the prevailing knowledge into a new framework for lean integration in the maintenance process.

5.2. Lean tools for maintenance activities

Reducing the NVA within maintenance activities can be accomplished through implementing lean tools (Jasiulewicz-Kaczmarek, Citation2013). The lean tools that suit the maintenance activities have been stated in previous studies. Smith and Hawkins (Citation2004) identify the key lean tools including VSM, 5S, and visual management. Davies and Greenough (Citation2010) develop a comprehensive lean tools template that represents possible lean activities within the maintenance process within an organisation. The tools are 5S, TPM, OEE, standards, mapping, inventory management, and visual management. Okhovat et al. (Citation2012) suggest six lean tools that fit the maintenance processes of an organisation. These tools include visual control, 5S, seven wastes, single minute exchange of die (SMED), and Poka-Yoke (mistake proofing). Clarke et al. (Citation2010) target eight LM practices as a preparation for delivering lean project objectives in a pharmaceutical organisation. A list of the references including LM tools is demonstrated in Table .

Table 3. Lean maintenance practices/tools reported in previous studies.

6. A proposed LM process

This section demonstrates an attempt to propose a process for adopting lean thinking into the maintenance activities. The process adopts the hypothesis of Womack and Jones (Citation2003) that lean principles can be deployed to all organisations and sectors. Lean principles have being increasingly extended for industrial and service sectors. This is known as lean thinking which refers to the thinking process of lean (Holweg, Citation2007). The process proposed in this study is designed on the basis of the five lean manufacturing principles stated by Womack and Jones (Citation2003). Some authors including Karim and Arif-Uz-Zaman (Citation2013) develop lean implementation methodology based on the five lean principles for a manufacturing environment. Mostafa et al. (Citation2013) state that lean practices/tools represent lean principles in the implementation process.

The process introduced in this study could be considered as an attempt to pave the way of applying or adopting lean principles to maintenance activities (Figure ). The process provides guidance and support towards maintenance excellence for an organisation pursuing to extend lean practice to its maintenance department or other organisations starting introducing lean thinking to maintenance department. The process was developed through conceptual integration of five lean principles as they are the backbones of any lean initiatives (Womack & Jones, Citation2003). The principles specify the value, identify the value stream, flow the value, pull the value, and pursuing perfection. In addition, analysing and addressing limitations of the existing initiatives assist in developing the comprehensive LM process proposed in this study. The process is more flexible and can be adjusted according to any maintenance strategy. It could work simultaneously and complementary with previous framework developed for shop floor area as it is inclusive for the maintenance processes. The proposed process entails five stages and detailed steps within each stage.

Figure 4. Proposed lean maintenance process.

Figure 4. Proposed lean maintenance process.

6.1. Stage one: specify the value

The first stage focuses on defining an organisational maintenance system including activities, maintenance planning, strategies, and maintenance crew. In this stage, the employees training on LM wastes are assigned. Furthermore, identifying the types of wastes in maintenance processes is included. The core concept of lean manufacturing is eliminating the seven cardinal forms of waste. The seven cardinal types of waste in the maintenance process can be discussed in the same manner as in the eight waste types identified in the production system (Baluch et al., Citation2012; Clarke et al., Citation2010; Davies & Greenough, Citation2010).

(1)

Too much maintenance: performing PM and predictive maintenance (PdM) tasks at intervals more often than optimal which results in the overproduction of maintenance work.

(2)

Waiting for maintenance resources: production department is waiting for maintenance personnel to perform the maintenance service. It involves waiting for tools, parts documentation, and buys extra tools and stores them near the job location.

(3)

Centralised maintenance: the centralisation of the MRO stores that are far from the job, commonly used repetitive parts that have not been kitted, documentation that must be hunted down, and work orders for machines that are not available all cause excess transportation. Therefore, maintenance personnel spend more time in motion and transportation which do not add value to the process.

(4)

Non-standard maintenance: maintenance operations are normally conducted to achieve operation as soon as possible with no standard guidelines. This sometimes eliminates an opportunity to perform a higher quality repair.

(5)

Excessive stock: the MRO inventory contains needed materials and spares. Additionally, work-in-process inventories may be used to ensure availability of required materials. Inventory for a maintenance operation also includes the work order backlog. Excessive maintenance work inventory results in slow response, unexpected breakdowns, and a high reactive labour percentage.

(6)

Double handling: the wasted motion is usually concentrated around PM tasks. Doing inspection monthly on a pump that has not changed status in three years should be extended longer to quarterly, semi-annually, or annually depending upon the criticality of that piece of equipment.

(7)

Poor maintenance: performing incorrect repair is a source of poor maintenance. Incorrect maintenance requires several repeated times to complete the repair job correctly. This affects the maintenance cost and the quality of the product. Applying proper training and detailed procedures can assist in poor maintenance elimination.

(8)

Under-utilisation of maintenance crew: maintenance technicians do NVA work or do not perform as required/at the best interest of the organisation.

6.2. Stage two: identify the value stream

This stage includes all maintenance-related activities and processes. The stage starts by mapping the maintenance value stream then locating the wastes sources. This stage ends with setting equipment performance measures such as availability, OEE, and meantime between failures. VSM is used for visualising the flows of information and materials within a supply chain. VSM primarily helps an organisational management to recognise different forms of waste and its sources. One key metric of VSM is value added (VA) time percentage which measures VA activities against NVA activities (Monden, Citation1998). Standard icons for drawing the current and future VSM are available in Sullivan, McDonald, and Van Aken (Citation2002). These icons should be modified to fit the maintenance activities. In this study, a new set of VSM icons fitting all the maintenance activities was introduced (see Figure ). The new icons were designed using Edraw Max™ professional software package. The discussion of each activity is displayed in Table . An example of mapping the maintenance process using these icons for visualising a general current state is displayed in Figure .

Figure 5. VSM symbols for maintenance activities (developed from Edraw Max software).

Figure 5. VSM symbols for maintenance activities (developed from Edraw Max software).

Table 4. Maintenance VSM symbol description.

Figure 6. Example of general maintenance state map (developed from Edraw Max software).

Figure 6. Example of general maintenance state map (developed from Edraw Max software).

6.3. Stage three: flow the value

The process of ‘flowing the value’ starts from waste network and waste/practices analyses before the results of the analyses are documented at the current state gap of maintenance using the calculation of OEE within an organisation. The documentation of lean practices for maintenance was conducted through the literature presented in Table through marking out the most frequently suggested practices in these studies and then constructed the hierarchical scheme for LM practices as demonstrated in Figure . The structure is similar to Shah and Ward (Citation2003), however, for the use of this structure is dedicated to the maintenance process not the manufacturing process. The structure consists of two levels and four bundles: just-in-time (JIT), total quality management (TQM), human resource management (HRM), and TPM and practices assigned under each bundle. The scheme can be used to indicate the association between the eight types of maintenance waste and the LM practices. The success of the LM depends on the application of each bundle. Each practice provides some benefits within the maintenance process. As a result, the performance of a whole maintenance department can be improved. The four LM bundles are briefly explained below.

Figure 7. Scheme for lean maintenance practices.

Figure 7. Scheme for lean maintenance practices.

6.3.1. JIT bundle

The JIT bundle encompasses all practices which are designed to reducing and eliminating unnecessary inventory and waiting in maintenance activities. These practices are Kanban, SMED, work standardisation, Takt Time, visual control, distributed MRO storeroom, and CMMS.

6.3.2. TQM bundle

The TQM bundle aims at continuously improving and sustaining the quality of products and processes through the participation of management, workforce, suppliers, and customers, in order to meet or exceed customer expectations (Cua et al., Citation2001). The practices of TQM are customer focus, leadership, strategic quality planning, use of information and analysis, management of people (participation and partnership), and continuous improvement (Chin, Rao Tummala, & Chan, Citation2002). This ensures higher customer satisfaction, better quality of products, and higher market share; improving the competitiveness, effectiveness, and flexibility of the whole organisation (Pheng & Chuan, Citation2001). In this study, the TQM bundle consists of Kaizen, 5S, maintenance process mapping, Poka-Yoke, benchmarking, Jidoka, and FMFA.

6.3.3. TPM bundle

The TPM bundle incorporates all practices that are designed to maximise the equipment effectiveness. The bundle contains autonomous maintenance, planned maintenance, root cause analysis (RCA) and problem solving, safety improvement, OEE, and work order system. The concept of TPM was developed in Japan by Seichii Nakajima aiming at achieving zero losses (e.g. zero breakdowns, zero defects, zero accidents) and attaining the Takt time through improving and maintaining equipment to its highest performance level (Brown et al., Citation2006). TPM can be integrated with lean in order to distinguishing and attacking six big losses which are reducing the effectiveness of equipment (Rodrigues & Hatakeyama, Citation2006). These six categories of losses are (1) breakdown losses, (2) set-up losses, (3) minor stoppage/idle losses, (4) reduced speed losses (equipment speed is slow than the designed speed), (5) rework losses, and (6) start-up losses (start-up after periodic repair, start-up after holidays, start-up after lunch breaks, and start-up after suspension) (Waeyenbergh & Pintelon, Citation2002).

6.3.4. HRM bundle

The HRM bundle encompasses all the practices to ensure that the human resources of an organisation are used in such a way that the employer obtains the greatest possible benefit from their abilities. At the same time, the employees obtain both material and psychological rewards from their work (Hiltrop, Citation1996). The HRM practices form an organisation performance through increase employees’ knowledge, skills, and abilities (KSAs), motivate employees to leverage their KSAs for the firm’s benefit and employees empowerment. In addition, work teams, performance appraisal, and information sharing have been recommended to enhance an organisation performance (Huemann, Keegan, & Turner, Citation2007). In this study, the HRM bundle includes work teams, training and development, employee involvement, openness information sharing, maintenance and reliability group, and multi-skilled maintenance technician.

6.4. Stage four: pulling the value

The fourth stage is to confirm that an equipment (i.e. considered as the customer in the maintenance process) is pulling the value through all maintenance processes. The execution of lean principles takes place at this stage. The stage involves steps in reconfiguring the VSM or designing the future stream map, selecting LM practices, developing the lean transformation strategy, and evaluating the OEE.

6.4.1. Association between maintenance wastes and LM practices

Selecting LM tools is the next step after identifying and discussing the types of waste and lean tools. It assists an organisation to achieve LM targets by associating suitable tools to tackle the spotted waste types. The QFD is suggested in this study to develop the association between these tools and wastes. Mostafa (Citation2011) suggested using QFD to assign the lean practices for each waste. Nonetheless, the study was in a general manufacturing environment rather than a maintenance process. Likewise, Tendayi (Citation2013) applies QFD coupled with AHP to rank the maintenance excellence criteria with some lean tools. The study focused only on a certain case study of rolling stock maintenance. It used limited lean tools and did not include the maintenance wastes. In contrast to Tendayi (Citation2013), this study has identified 26 lean tools for maintenance (see, Figure ) and eight types of maintenance wastes (discussed in Section 6.1). QFD is a structured tool that identifies important customer expectations and translates them into appropriate technical characteristics which are operational in design, verification, and production. QFD enables resources to be focused on meeting major customer demands. Figure displays the structure of QFD which is frequently called a house of quality (HOQ) because of the shape presented (Bottani & Rizzi, Citation2006).

Figure 8. House of quality.

Figure 8. House of quality.

The HOQ comprises customer requirements (horizontal axis) and technical characteristics (vertical axis). The customer axis designates what customers require, importance of the requirements, and competitive performance. The customer requirements are often referred as what’s. The technical axis describes the technical characteristics that affect customer satisfaction directly for one or more customer expectations. Moreover, on the technical axis are the correlations, importance, and targets of the technical characteristics and technical competitive benchmarking. The technical characteristics are denoted as How’s, meaning how to address what’s. The technical targets are accordingly called How Much. The interrelationships between customer wants and technical characteristics are evaluated in the relationship matrix.

6.4.2. House of Waste

The HoW is developed in this study to demonstrate the maintenance wastes/lean tools association. HoW identifies the importance of each LM tool in the elimination of each waste type as demonstrated in Table . It has two main parts: the horizontal part ‘What’s’ which contains information relevant to the waste types and the vertical part ‘How’s’ which comprises corresponding LM tools. The basic process underlying ‘How’ resides in the centre of the matrix where intersect of maintenance waste types and lean tools provides an opportunity to examine each waste type versus each tool.

Table 5. House of Waste.

Five steps in developing the wastes/tool association using HoW are briefly described as follows:

(1)

List the waste types within the maintenance process in the horizontal axis.

(2)

Determine each waste priority (Pi), which rates the significance of each waste to the maintenance performance. Otherwise, it can be based on the waste occurrence or cost of removal. A scale of 1 to 9 can be used, where 9 is given to extremely important, 7 strongly important, 5 to very important, 3 to important, and 1 to not important.

(3)

List LM tools on the vertical axis. An organisation can state suitable LM tools for their own maintenance process in terms of the application cost of LM tools.

(4)

Identify the interrelationships between wastes and tools (wij). The strength of relationship may be classified into three levels, where a rating of 9 is assigned to a strong relation, 3 to a medium relation, and 1 to a weak relation. Each tool must be interrelated to at least one waste; one waste must also be addressed by at least one tool. This ensures that all wastes are concerned in the maintenance removal planning, and all tools are properly established.

(5)

Calculate the score (Sj) and (RSj) to rank each LM tool. The following formula can be used to calculate the score

(1) (2)

where

Pi=

relative priority of ith waste

i=

type of maintenance waste,

Tj=

LM tool,

wij=

numerical VA to position (ij) of the HoW matrix. This refers to the weight of eliminating waste ith by tool jth. Numerical scale can be (9, 3, 1)

Sj=

score of tool jth over the total types of waste

RSj=

relative score of tool jth over the total score of tools

The score Sj represents the absolute importance of tool jth over all types of wastes. The relative score RSj refers to the importance of the tool jth over all tools. According to Bottani and Rizzi (Citation2006), the technical characteristics are usually ranked based on relative importance rather than absolute importance. Therefore, LM tools should be prioritised based on RSj. The higher the , the more important the LM tool that should be incorporated in order to eliminate the waste.

6.5. Stage five: pursue perfection

The last stage is to pursue the complete waste elimination from maintenance processes. This could be achieved through auditing the LM results, standardise the lean tools and procedures, teams and employees developments and expand the lean practice.

7. Implications of proposed LM process

Most of literature works on lean implementations fall into the manufacturing environment albeit LM is essential part for the lean manufacturing system (Soltan & Mostafa, Citation2014; Tendayi & Fourie, Citation2013). Plethora of studies included and mentioned lean and maintenance concepts (see Table ). Nevertheless, the integration of lean principles into the maintenance environment has not evidently received full attention. The common aspects among the previous studies were (1) introducing partial lean tools to be applied in the maintenance process; (2) developing diagrammatic structures (model, pyramid, or scheme) with unspecified sequence of LM implementation; and (3) lack of proper structure. Consequently, some researchers including Davies and Greenough (Citation2010) and Soltan and Mostafa (Citation2014) have proposed more research on incorporating lean principles in the maintenance activities. Therefore, this study proposed a LM process to cover most of the limitations or deficiencies of the existing suggested LM initiatives.

The proposed LM process is a straight forward, comprehensive, and easy to understand for maintenance practitioners and maintenance strategy decision makers. The benefits of the proposed process can be summarised as:

(1)

The process is straightforward and easy to comprehend. This is because of the simple structure that is combined in the process.

(2)

A systematic procedure of applying the five lean principles into maintenance activities can result in better understanding from an organisation’s management view.

(3)

All advantages of lean are kept as the process focus. These advantages are integrated and systemised in the steps of the process.

(4)

Application of the process establishes pursuing a perfectionist culture in an organisation. This is done through auditing the LM results, standardisation, team’s development, and expansion of the practice. Hence, with every iteration of the process, an organisation maintenance activities move a further step towards maintenance excellence.

(5)

Aligning the human resource aspects (maintenance employees training and development) with other steps can bring high potential for a comprehensive and sustainable LM implementation process as well as overall process improvement in an organisation.

(6)

The process promotes the teamwork and problem solving cultures to ensure high-quality outcomes of the implementation process.

(7)

The maintenance process can be converted to be a predictive and proactive system that provides the reliable process using lean principles. As a result, it enhances the maintenance excellence and world-class manufacturing as maintenance and manufacturing are inseparable (i.e. reliability and availability of manufacturing facilities).

(8)

The process can be applied to all manufacturing and non-manufacturing organisations that are pursuing the world-class status in their maintenance function. The process suits those organisations either in pursuing to transfer lean thinking to their maintenance departments or starting lean transformation from the maintenance department.

(9)

Hitherto, some initiatives have been developed for specific larger size organisations such as shipbuilding and military (see Table ). However, the proposed process can be accepted within all level of skills and organisational sizes. This is due to the fact that the process is more flexible and can be adjusted according to any maintenance strategies.

(10)

The proposed process is precisely documented and discusses the maintenance wastes and LM tools. It is to enhance the understanding the waste elimination and lead to successful LM implementation.

(11)

The process presented wastes/tools association to assign LM tools for each waste type. This leads to an effective waste elimination process and sustainable outcomes.

8. Conclusion

Maintenance is a critical contributor to progressing towards world-class manufacturing of an organisation. It has rapidly grown into a very complex undertaking as technologies, competition, and product characteristics have evolved. In order to achieve world-class performance, the maintenance strategies should be linked to manufacturing strategies such as the lean concept. Applying an effective maintenance strategy can ensure a high degree of utilisation, reliability, and availability of manufacturing facilities especially in a continuous production process. This study has introduced a process to adopt lean into maintenance activities. The process highlights types of NVA maintenance activities, a package of VSM symbols to capture the maintenance activities, LM tools scheme, and tools/wastes association. Moreover, it promotes the culture of continuous improvement aiming at maintenance excellence. In general, any improvements attained from implementing the suggested process might take time to transform maintenance activities into LM. Nevertheless, commitment and direct involvement of an organisational management along with employee training and teamwork development can be a catalyst to accelerate the transformation process. The proposed LM process can be applied in real conditions to test its validity and reliability of the process. This can be considered as a further suggestion to the proposed process in this research. Hence, application of the process in different industrial sectors and a wide range of manufacturing companies can contribute to additional empirical evidence.

Acknowledgements

The authors would like to express their gratitude to the anonymous reviewers for their constructive comments and suggestions to improve the quality of the paper.

Disclosure statement

No potential conflict of interest was reported by the authors.

References

  • Abdulmalek, F. A., Rajgopal, J., & Needy, K. L. (2006). A classification scheme for the process industry to guide the implementation of lean. Engineering Management Journal, 18, 15–25.10.1080/10429247.2006.11431690
  • Ahmed, S., Hassan, M. H., & Taha, Z. (2005). TPM can go beyond maintenance: Excerpt from a case implementation. Journal of Quality in Maintenance Engineering, 11, 19–42. doi:10.1108/13552510510589352
  • Al-Najjar, B., & Alsyouf, I. (2003). Selecting the most efficient maintenance approach using fuzzy multiple criteria decision making. International Journal of Production Economics, 84, 85–100. doi:10.1016/S0925-5273(02)00380-8
  • Ayeni, P., Baines, T. S., Lightfoot, H., & Ball, P. (2011). State-of-the-art of ‘Lean’ in the aviation maintenance, repair, and overhaul industry. Proceedings of the Institution of Mechanical Engineers, Part B: Journal of Engineering Manufacture, 1–16. doi:10.1177/0954405411407122
  • Baluch, N., Abdullah, C. S., & Mohtar, S. (2012). TPM and lean maintenance – A critical review. Interdisciplinary Journal of Contemporary Research In Business, 4, 850–857.
  • Bevilacqua, M., & Braglia, M. (2000). The analytic hierarchy process applied to maintenance strategy selection. Reliability Engineering & System Safety, 70, 71–83. doi:10.1016/S0951-8320(00)00047-8
  • Bhasin, S. (2015). Lean management beyond manufacturing. New York, NY: Springer International Publishing.10.1007/978-3-319-17410-5
  • Blanchard, B. S. (1997). An enhanced approach for implementing total productive maintenance in the manufacturing environment. Journal of Quality in Maintenance Engineering, 3, 69–80. doi:10.1108/13552519710167692
  • Booth, A., Papaioannou, D., & Sutton, A. (2012). Systematic approaches to a successful literature review. Thousand Oaks, CA: Sage.
  • Bottani, E., & Rizzi, A. (2006). Strategic management of logistics service: A fuzzy QFD approach. International Journal of Production Economics, 103, 585–599. doi:10.1016/j.ijpe.2005.11.006
  • Brown, C. B., Collins, T. R., & McCombs, E. L. (2006). Transformation from batch to lean manufacturing: The performance issues. Engineering Management Journal, 18, 3–14.10.1080/10429247.2006.11431689
  • Bulatovic, M., & Djurovic, D. (2014). Lean concept in the maintenance. Journal of Trends in the Development of Machinery and Associated Technology, 18, 135–138. Retrieved from http://tmt.unze.ba/zbornik/TMT2014Journal/30_Journal_TMT_2014.pdf
  • Burgess, N., & Radnor, Z. (2013). Evaluating lean in healthcare. International Journal of Health Care Quality Assurance, 26, 220–235. doi:10.1108/09526861311311418
  • Carrasqueira, M., & Machado, V. C. (2008). Strategic logistics: Re-designing companies in accordance with Lean Principles. International Journal of Management Science and Engineering Management, 3, 294–302. doi:10.1080/17509653.2008.10671056
  • Chan, F. T. S., Lau, H. C. W., Ip, R. W. L., Chan, H. K., & Kong, S. (2005). Implementation of total productive maintenance: A case study. International Journal of Production Economics, 95, 71–94. doi:10.1016/j.ijpe.2003.10.021
  • Chin, K. S., Rao Tummala, V. M., & Chan, K. M. (2002). Quality management practices based on seven core elements in Hong Kong manufacturing industries. Technovation, 22, 213–230. doi:10.1016/S0166-4972(01)00020-7
  • Chong, M. Y., Chin, J. F., & Hamzah, H. S. (2012). Transfer of total productive maintenance practice to supply chain. Total Quality Management & Business Excellence, 23, 467–488. doi:10.1080/14783363.2011.637788
  • Clarke, G., Mulryan, G., & Liggan, P. (2010). Lean maintenance – A risk-based approach. Pharmaceutical Engineering, 30(5), 1–6.
  • Colbert, F. (2008). The benefits of integrating “lean thinking” concepts into the management of infrared predictive maintenance programs. Cinde Journal, 29, 5–12.
  • Cua, K. O., McKone, K. E., & Schroeder, R. G. (2001). Relationships between implementation of TQM, JIT, and TPM and manufacturing performance. Journal of Operations Management, 19, 675–694. doi:10.1016/S0272-6963(01)00066-3
  • Davies, C. (2003). The contribution of lean thinking to the maintenance of manufacturing systems ( PhD Thesis). Cranfield University, Cranfield, UK.
  • Davies, C., & Greenough, R. (2001). Maintenance survey – Identification of lean thinking within maintenance. Paper presented at the Proceedings of the 17th National conference on manufacturing research: Advances in manufacturing technology XV, Cardiff, UK.
  • Davies, C., & Greenough, R. M. (2003). Testing performance measures within maintenance, through case study research into lean thinking activities. Retrieved March 24, 2014, from www.plant-maintenance.com/articles/Testing_Performance_Measures.pdf
  • Davies, C., & Greenough, R. M. (2010). Measuring the effectiveness of lean thinking activities within maintenance. Retrieved June 24, 2013, from http://www.plant-maintenance.com/articles/Lean_Maintenance.pdf
  • De Silva, N., Ranasinghe, M., & De Silva, C. R. (2012). Maintainability approach for lean maintenance. Paper presented at the World Construction Conference 2012 – Global Challenges in Construction Industry, Colombo, Sri Lanka. Retrieved from http://www.irbnet.de/daten/iconda/CIB_DC25109.pdf
  • De Treville, S., & Antonakis, J. (2006). Could lean production job design be intrinsically motivating? Contextual, configurational, and levels-of-analysis issues. Journal of Operations Management, 24, 99–123. doi:10.1016/j.jom.2005.04.001
  • Denyer, D., & Tranfield, D. (2009). Producing a systematic review. In D. A. Buchanan & A. Bryman (Eds.), The Sage handbook of organizational research methods (pp. 671–689). Thousand Oaks, CA: Sage.
  • Djurovic, D., & Bulatovic, M. (2014). “5 S” as a tool lean concept in the maintenance. Paper presented at the 8th International Quality Conference, Center for Quality, Faculty of Engineering, University of Kragujevac, Serbia.
  • Dombrowski, U., & Malorny, C. (2014). Lean after sales service – An opportunity for OEMs to ensure profits. In B. Grabot, B. Vallespir, S. Gomes, A. Bouras, & D. Kiritsis (Eds.), Advances in production management systems innovative and knowledge-based production management in a global-local world (Vol. 439, pp. 618–625). Berlin: Springer.
  • Dunn, S. (2014). 5 keys to lean maintenance and improving maintenance. Asset Management & Maintenance Journal, 27, 8–10.
  • EPA. (2015, 2 February). Lean thinking and methods: TPM. Retrieved January 4, 2015, from http://www.epa.gov/lean/environment/methods/tpm.htm
  • Faccio, M., Persona, A., Sgarbossa, F., & Zanin, G. (2014). Industrial maintenance policy development: A quantitative framework. International Journal of Production Economics, 147, 85–93. doi:10.1016/j.ijpe.2012.08.018
  • Fouladgar, M. M., Yazdani-Chamzini, A., Lashgari, A., Zavadskas, E. K., & Turskis, Z. (2012). Maintenance strategy selection using AHP and COPRAS under fuzzy environment. International Journal of Strategic Property Management, 16, 85–104. doi:10.3846/1648715X.2012.666657
  • Fraser, K. (2014). Facilities management: The strategic selection of a maintenance system. Journal of Facilities Management, 12, 18–37. doi:10.1108/JFM-02-2013-0010
  • George, M. (2003). Lean six sigma for service: How to use lean speed and six sigma quality to improve services and transactions. New York, NY: McGraw-Hill.
  • Georgescu, D. (2010). The maintenance management for lean organization. Economia. Seria Management, 13, 437–446.
  • Georgescu, D., & Militaru, C. (2009, 12–13 November). 7s’s System foundation of total productive maintenance house for lean organization. Paper presented at the The 4th International Conference of the Interdisciplinarity in Engineering, Targu Mures, Romania.
  • Ghayebloo, S., & Shahanaghi, K. (2010). Determining maintenance system requirements by viewpoint of reliability and lean thinking: A MODM approach. Journal of Quality in Maintenance Engineering, 16, 89–106. doi:10.1108/13552511011030345
  • Gopalakrishnan, P., & banerji, A. (2013). Maintenance and spare parts management (2nd ed.). New Delhi: PHI Learning Private Ltd.
  • Heisler, R. (2003). Planning and scheduling in a lean maintenance environment. Retrieved December 20, 2014, from http://www.reliabilityweb.com/index.php/search/results/?q=Randy+Heisler&sa=Go&cx=008700119099951100649%3A5ndeqiorkim&cof=FORID%3A10&ie=UTF-8
  • Hellingrath, B., & Cordes, A.-K. (2014). Conceptual approach for integrating condition monitoring information and spare parts forecasting methods. Production & Manufacturing Research, 2, 725–737. doi:10.1080/21693277.2014.943431
  • Hiltrop, J.-M. (1996). A framework for diagnosing human resource management practices. European Management Journal, 14, 243–254. doi:10.1016/0263-2373(96)00004-7
  • Holweg, M. (2007). The genealogy of lean production. Journal of Operations Management, 25, 420–437. doi:10.1016/j.jom.2006.04.001
  • Hopp, W. J., & Spearman, M. L. (2004). Commissioned paper to pull or not to pull: What is the question? Manufacturing & Service Operations Management, 6, 133–148.
  • Hou, Y.-H., Zhao, H.-F., Meng, X.-K., & Ma, Y.-X. (2013). Research on lean maintenance system of hydroelectric station equipment. Industrial Engineering and Management, 3, 117–121.
  • Huang, J., Bian, Y., & Cai, W. (2012, 15–18 June). Weapon equipment lean maintenance strategy research. Paper presented at the International Conference on Quality, Reliability, Risk, Maintenance, and Safety Engineering (ICQR2MSE), Chengdu, China.
  • Huemann, M., Keegan, A., & Turner, J. R. (2007). Human resource management in the project-oriented company: A review. International Journal of Project Management, 25, 315–323. doi:10.1016/j.ijproman.2006.10.001
  • Irajpour, A., Fallahian-Najafabadi, A., Mahbod, M. A., & Karimi, M. (2014). A framework to determine the effectiveness of maintenance strategies lean thinking approach. Mathematical Problems in Engineering, 2014, 1–11.
  • Jahanbakhsh, M., Moghaddam, N., & Samaie, H. M. (2013). Lean maintenance (case study: Teen Dairy Industry Co.). International Research Journal of Applied and Basic Sciences, 4, 2033–2040.
  • Jasiulewicz-Kaczmarek, M. (2013). Sustainability: Orientation in maintenance management: Case study. In P. Golinska (Ed.), EcoProduction and logistics (pp. 135–154). London: Springer.10.1007/978-3-642-23553-5
  • Joffe, H. (2011). Thematic analysis. In D. Harper & A. R. Thompson (Eds.), Qualitative research methods in mental health and psychotherapy (pp. 209–223). West Sussex: Wiley.10.1002/9781119973249
  • Karim, A., & Arif-Uz-Zaman, K. (2013). A methodology for effective implementation of lean strategies and its performance evaluation in manufacturing organizations. Business Process Management Journal, 19, 169–196. doi:10.1108/14637151311294912
  • Khazraei, K., & Deuse, J. (2011). A strategic standpoint on maintenance taxonomy. Journal of Facilities Management, 9, 96–113. doi:10.1108/14725961111128452
  • Kolanjiappan, S., & Maran, D. K. (2011). Lean practices in aircraft maintenance. Software Engineering and Technology, 3, 450–457.
  • Lee, J., & Wang, H. (2008). New Technologies for Maintenance. In K. A. H. Kobbacy & D. N. P. Murthy (Eds.), Complex System Maintenance Handbook (pp. 49–78). London: Springer (eBook).
  • Levitt, J. (2008). Lean maintenance. New York, NY: Industrial Press.
  • Marks, A. (2008). Effective rotable plant management in a lean maintenance culture. Asset Management and Maintenance Journal, 21, 36–43.
  • Márquez, C. A. (2007). The maintenance management framework: Models and methods for complex systems maintenance. London: Springer-Verlag.
  • McCarthy, D., & Rich, N. (2004). Lean TPM. Oxford: Elsevier.10.1016/B978-075065857-7/50005-6
  • McConnell, K., Lindrooth, R. C., Wholey, D. R., Maddox, T. M., & Bloom, N. (2013). Management practices and the quality of care in cardiac units. JAMA Internal Medicine, 173, 684–692. doi:10.1001/jamainternmed.2013.3577
  • Monden, Y. (1998). Toyota production system: An integrated approach to just-in-time. Norcross, GA: Engineering & Management Press.
  • Mostafa, S. (2011). A lean framework for maintenance decisions ( Master of Industrial Engineering). Mansoura University, Egypt.
  • Mostafa, S., Dumrak, J., & Soltan, H. (2013). A framework for lean manufacturing implementation. Production & Manufacturing Research, 1, 44–64. doi:10.1080/21693277.2013.862159
  • Nezami, F. G., & Yildirim, M. B. (2013). A sustainability approach for selecting maintenance strategy. International Journal of Sustainable Engineering, 6, 332–343. doi:10.1080/19397038.2013.765928
  • Nima, R., Hesamodin, N., & Alireza, R. (2014). Presenting an optimal lean maintenance strategy using fuzzy MADM. International Journal of Management, IT and Engineering, 4, 263–278.
  • Okhovat, M. A., Ariffin, M. K. A. M., Nehzati, T., & Hosseini, S. A. (2012). Development of world class manufacturing framework by using six-sigma, total productive maintenance and lean. Scientific Research and Essays, 7, 4230–4241. doi:10.5897/SRE11.368
  • Okoli, C., & Schabram, K. (2010). A guide to conducting a systematic literature review of information systems research. Sprouts: Working Papers on Information Systems, 10, 1–50. Retrieved form http://sprouts.aisnet.org/10-26
  • Önder, M. (2014). Maintenance as a contributor in green production systems: Interviews with Volvo, Scania, and Dynamate ( Master Thesis). Mälardalen University, Mälardalen, Sweden.
  • Pedersen, E. R. G., & Huniche, M. (2011). Determinants of lean success and failure in the Danish public sector. International Journal of Public Sector Management, 24, 403–420. doi:10.1108/09513551111147141
  • Pheng, L., & Chuan, C. (2001). Just-in-time management of precast concrete components. Journal of Construction Engineering and Management, 127, 494–501. doi:10.1061/(ASCE)0733-9364(2001)127:6(494)
  • Pinjala, S. K., Pintelon, L., & Vereecke, A. (2006). An empirical investigation on the relationship between business and maintenance strategies. International Journal of Production Economics, 104, 214–229. doi:10.1016/j.ijpe.2004.12.024
  • Potes Ruiz, P., Kamsu Foguem, B., & Grabot, B. (2014). Generating knowledge in maintenance from experience feedback. Knowledge-Based Systems, 68, 4–20. doi:10.1016/j.knosys.2014.02.002
  • Qiang, T., Zhu, B., & Li, L. (2011). A study on military equipment lean maintenance. Paper presented at the International Conference on Quality, Reliability, Risk, Maintenance, and Safety Engineering, Xi’an.
  • Rastegari, A. (2012). Strategic maintenance management in lean environment ( Master Thesis). Mälardalen University, Västerås, Sweden.
  • Resta, B., Powell, D., Gaiardelli, P., & Dotti, S. (2015). Towards a framework for lean operations in product-oriented product service systems. CIRP Journal of Manufacturing Science and Technology, 9, 12–22. doi:10.1016/j.cirpj.2015.01.008
  • Rodrigues, M., & Hatakeyama, K. (2006). Analysis of the fall of TPM in companies. Journal of Materials Processing Technology, 179, 276–279. doi:10.1016/j.jmatprotec.2006.03.102
  • Romano, E., Murino, T., Asta, F., & Costagliola, P. (2013). Lean Maintenance model to reduce scraps and WIP in manufacturing system: Case study in power cables factory. WSEAS Transactions on Systems, 12, 650–666.
  • Shah, R., & Ward, P. (2003). Lean manufacturing: Context, practice bundles, and performance. Journal of Operations Management, 21, 129–149. doi:10.1016/s0272-6963(02)00108-0
  • Shah, R., & Ward, P. T. (2007). Defining and developing measures of lean production. Journal of Operations Management, 25, 785–805. doi:10.1016/j.jom.2007.01.019
  • Shahin, A., Shirouyehzad, H., & Pourjavad, E. (2012). Optimum maintenance strategy: A case study in the mining industry. International Journal of Services and Operations Management, 12, 368–386. doi:10.1504/IJSOM.2012.047626
  • Sheng, T. L., & Tofoya, J. (2010, 18–20 October). The secret of manufacturing excellence: Lean maintenance. Paper presented at the International Symposium on Semiconductor Manufacturing (ISSM), Tokyo.
  • Shou, W., Wang, X., Wang, J., Hou, L., & Truijens, M. (2014). Integration of BIM and lean concepts to improve maintenance efficiency: A case study. Computing in Civil and Building Engineering, 2014, 373–380.
  • Smith, R. (2004). What is lean maintenance? Elements that need to be in place for success. Maintenance Technology, 17, 15–21.
  • Smith, R., & Hawkins, B. (2004). Lean maintenance: Reduce costs, improve quality, and increase market share. Burlington, MA: Elsevier.
  • Soltan, H., & Mostafa, S. (2014). Leanness and agility within maintenance process. International Journal of Engineering Research and Technology, 3, 553–555.
  • Stuchly, V., & Jasiulewicz-Kaczmarek, M. (2014). Maintenance in sustainable manufacturing. Scientific Journal of Logistics, 10, 273–284. Retrieved from http://www.logforum.net/vol10/issue3/no4
  • Sullivan, W. G., McDonald, T. N., & Van Aken, E. M. (2002). Equipment replacement decisions and lean manufacturing. Robotics and Computer-Integrated Manufacturing, 18, 255–265. doi:10.1016/S0736-5845(02)00016-9
  • Sunjka, B. P., & Murphy, S. F. (2014). Lean implementation within South African aircraft maintenance organisations. International Journal of Lean Enterprise Research, 1, 59–80. doi:10.1504/IJLER.2014.062285
  • Tendayi, T. G. (2013). An investigation into the applicability of lean thinking in an operational maintenance environment ( Master of Science in Engineering). Stellenbosch University, South Africa.
  • Tendayi, T. G., & Fourie, C. J. (2012, July). A lean maintenance supply chain framework for rolling stock maintenance: A case study. Paper presented at The 42nd International Conference on Computers and Industrial Engineering (CIE42), Cape Town, South Africa.
  • Tendayi, T. G., & Fourie, C. J. (2013). The combined AHP-QFD approach and its use in lean maintenance. Paper presented at the 25th Annual Southern African Institute of Industrial Engineering Conference, Stellenbosch.
  • Thirkell, E., & Ashman, I. (2014). Lean towards learning: Connecting Lean Thinking and human resource management in UK higher education. The International Journal of Human Resource Management, 25, 2957–2977. doi:10.1080/09585192.2014.948901
  • Thiruvengadam, A. (2009). A practical method for assessing maintenance factors using a value stream maintenance map ( Master of Science). Wichita State University, Wichita, KS.
  • Tinga, T. (2013). Maintenance concepts. In H. Pham (Ed.), Principles of loads and failure mechanisms (pp. 161–186). London: Springer-Verlag.10.1007/978-1-4471-4917-0
  • Tranfield, D., Denyer, D., & Smart, P. (2003). Towards a methodology for developing evidence-informed management knowledge by means of systematic review. British Journal of Management, 14, 207–222. doi:10.1111/1467-8551.00375
  • Van den Heuvel, M. (2008). Improving maintenance shutdown processes: Reducing delay and increasing work efficiency at Corus’s Direct Sheet Plant ( Master Thesis). University of Technology Delft, Delft, The Netherlands.
  • Verma, A. K., & Ghadmode, A. (2004). An integrated lean implementation model for fleet repair and maintenance. Naval Engineers Journal, 116, 79–90. doi:10.1111/j.1559-3584.2004.tb00306.x
  • Waeyenbergh, G., & Pintelon, L. (2002). A framework for maintenance concept development. International Journal of Production Economics, 77, 299–313. doi:10.1016/S0925-5273(01)00156-6
  • Waeyenbergh, G., & Pintelon, L. (2004). Maintenance concept development: A case study. International Journal of Production Economics, 89, 395–405. doi:10.1016/j.ijpe.2003.09.008
  • Womack, J. P., & Jones, D. T. (2003). Lean thinking: Banish waste and create wealth in your corporation (2nd ed.). New York, NY: Free Press, Simon & Schuster.
  • Yile, L., Hang, X. X., & Lei, Z. (2008). Lean Maintenance framework and its application in clutch maintenance. Paper presented at the International Conference on Information Management, Innovation Management and Industrial Engineering, Taipei.
  • Zarei, M., Fakhrzad, M. B., & Jamali Paghaleh, M. (2011). Food supply chain leanness using a developed QFD model. Journal of Food Engineering, 102, 25–33. doi:10.1016/j.jfoodeng.2010.07.026
  • Zwas, A. (2006). Lean manufacturing techniques in bus and rail maintenance: Study at Chicago Transit Authority in Illinois. Transportation Research Record: Journal of the Transportation Research Board, 1986, 54–58. doi:10.3141/1986-09