- Baker , K. R. , Introduction to Sequencing and Scheduling , John Wiley ( 1974 ).
- Bruno , J. , and Downey , P. , „ Complexity of Task Sequencing with Deadlines, Setup Times and Changeover Costs ,“ SIAM J. Comput . 7 ( 4 ) ( November , 1978 ).
- Emmons , H. , „ One Machine Sequencing to Minimize Certain Functions of Job Tardiness ,“ Operations Research , 17 ( 4 )( 1969 ).
- Erschler , J. , Fontan , G. , Merce , C. , and Roubellat , F. , „ A New Dominance Concept in Scheduling n Jobs on a Single Machine with Ready Times and Due Dates,“ Operations Research , 31 ( 1 ) ( 1983 ).
- Erschler , J. , Roubellat , F. , and Vernhes , J. P. , „ A Decision Making Process for the Real–Time Control of Production Unit ,“ Int. J. of Prod. Res . 14 ( 2 ) ( 1976 ).
- Erschler , J. , Roubellat , F. , and Vernhes , J. P. , „ Finding Some Essential Characteristics of the Feasible Solutions for a Scheduling Problem ,“ Operations Research , 24 ( 1976 ).
- Erschler , J. , Roubellat , F. , and Vernhes , J. P. , „ Characterizing the Set of Feasible Sequences for n Jobs to be Carried Out on a Single Machine ,„ European Journal of Operational Research , ( 4 ) ( 1980 ).
- Garey , M. R. , and Johnson , D. S. , Computers and Intractability A Guide to the Theory ofNP–Completeness , W. H. Free– man and Company ( 1979 ).
- Lawler , E. L. , Lenstra , J. K. ,Kan, A. H. G. Rinnooy , The Traveling Salesman Problem , John Wiley and Sons , 1985 .
- Monma , C. L. , and Potts , C. N. , „ On the Complexity of Scheduling with Batch Setup Times ,“ Operations Research , 37 ( 5 ) ( 1989 ).
- Posner , M. E. , „ The Deadline Constrained Weighted Compe–tion Time Problem Analysis of a Heuristic ,„ Operations Research , 36 ( 5 ) ( 1988 ).
- Tang , C. S. , „ Scheduling Batches on Parallel Machines with Major and Minor Setups ,“ European Journal of Operational–Research , 46 ( 1990 ).
- Uzsoy , R. , Lee , C. Y. , and Martin–Vega , L. A. , „ Scheduling Semiconductor Test Operations Minimizing Maximum Lateness and Number of Tardy Jobs on a Single Machine ,“ submitted to EJOR ( 1990 ).
- Wittrock , R. J. , „ Scheduling Parallel Machines with Setups ,“ research report , IBM Thomas J. Watson Research Center , York–town Heights . NY ( 1986 ).