Work breakdown structure application for man-hours calculation in hull construction shipbuilding in Malaysia

, ORCID Icon & ORCID Icon | (Reviewing editor)
Article: 1599524 | Received 26 Dec 2018, Accepted 15 Mar 2019, Published online: 19 May 2019

References

  • Abu Husain, M. K., Mohd Zaki, N. I., & Najafian, G. (2017). Prediction of offshore structural response extreme values by three different approaches of efficient time simulation technique. Ships and Offshore Structures, 12(2), 290–25. doi:10.1080/17445302.2016.1139258
  • Andrews, F. (1992). Spon’s fabrication norms for offshore structures: a handbook for the oil, gas & petrochemical industries. London: Taylor & Francis Ltd.
  • Booz, A. & Hamilton Earned Value Management Tutorial Module 2: Work Breakdown Structure, Office of Science, Tools & Resources for Project Management, science.energy.gov. (2011).
  • Brandić, V., & Kolić, D. (2018). PWBS best practice analysis of two shipyards. Pomorski zbornik ISSN 0554-6397 Stručni članak (Professional paper)(2), 47–57.
  • Breiman, L., Friedman, J. H., Olshen, R. A., & Stone, C. J. (1993). Classification and regression trees. New York: New Chapman and Hall.
  • Chou, -C.-C., & Chang, P.-L. (2001). Modeling and analysis of labor cost estimation for shipbuilding: The case of China shipbuilding corporation. Journal of Ship Production, 17(2), 92–96.
  • DoD. (2011). Work breakdown structures for defense materiel items. Washington: DoD.
  • Gordo, J., & Leal, M. (2018). A tool for analysis of costs on the manufacturing of the hull. Maritime transportation and harvesting of sea resources (pp. 743–748). Lisbon: Taylor & Francis Group.
  • Gullander, P., Davidsson, A., Dencker, K., Fasth, Å., Fässberg, T., Harlin, U., & Stahre, J. (2011). Towards a production complexity model that supports operation, re-balancing and man-hour planning. Paper presented at the Proceedings of the 4th Swedish Production Symposium (SPS), Lund, Sweden.
  • Hur, M., Lee, S.-K., Kim, B., Cho, S., Lee, D., & Lee, D. (2015). A study on the man-hour prediction system for shipbuilding. Journal of Intelligent Manufacturing, 26(6), 1267–1279. doi:10.1007/s10845-013-0858-3
  • Islam, A. S., Jameel, M., Jumaat, M. Z., Shirazi, S., & Salman, F. A. (2012). Review of offshore energy in Malaysia and floating Spar platform for sustainable exploration. Renewable and Sustainable Energy Reviews, 16(8), 6268–6284. doi:10.1016/j.rser.2012.07.012
  • Jones, C., Jost, A. C., Perkins, T. K., Fleming, Q. W., Koppelman, J. M., Lipke, W., & Kimmerly, P. (2006). CrossTalk: The Journal of Defense Software Engineering, 19(6). Retrieved from http://medicallibrary.org/
  • Kaiser, M. J., & Snyder, B. F. (2012). Reviewing rig construction cost factors, Center for Energy Studies, Louisiana State University https://www.offshore-mag.com/articles/print/volume-72/issue-7/rig- report/reviewing-rig-construction-cost-factors.html
  • Koenig, P. C., & Christensen, W. L. (1999). Development and implementation of modern work breakdown structures in naval construction: A case study. Journal of Ship Production, 15(3), 136–145.
  • Kolić, D., Brandić, V., Jaki, D., & Novak, L. (2018). Gantt chart analysis to improve shipbuilding panel line assembly. Paper presented at the SOME 2018, the 6th Annual International SOME Symposium (Ship Operations, Management and Economics), Athens, Greece, 20-21 March 2018.
  • Kolić, D., Sladić, S., & Storch, R. L. (2017). Lean IHOP transformation of shipyard erection block construction. Paper presented at the SNAME Maritime Convention 2017, Houston, Texas, 24-28 October 2017.
  • Leal, M., & Gordo, J. M. (2017). Hull’s manufacturing cost structure. Brodogradnja: Teorija I Praksa Brodogradnje I Pomorske Tehnike, 68(3), 1–24. doi:10.21278/brod
  • Liu, B., & Jiang, Z.-H. (2005). The man-hour estimation models & its comparison of interim products assembly for shipbuilding. International Journal of Operations Research, 2(1), 9–14.
  • Madsen, O., Holm, H., Trostmann, E., & Conrad, F. (1993). Cybernetic modelling and control in integrated production systems-a project overview. In The 8th IPS Research Seminar, 22–24 March 1994, Fuglsø, Denmark.
  • Mat Soom, E., Abu Husain, M. K., Mohd Zaki, N. I., Azman, N. U., & Najafian, G. (2016). Reliability-based design and assessment for lifetime extension of ageing offshore structures. OMAE: Proceeding of the ASME 2016 35th International Conference on Ocean, Offshore and Arctic Engineering, June 19–24, Busan, South Korea.
  • Mat Soom, E., Abu Husain, M. K., Mohd Zaki, N. I., Mohd Nor, M., . N., . K., Ayob, M. S., & Najafian, G. (2015). Global ultimate strength assessment (GUSA) for lifetime extension of ageing offshore structures. The Twenty-Fifth International Ocean and Polar Engineering Conference, June 21–26, Kona, Hawaii, USA.
  • Mei, Y., Zeng, Z., Feng, D., & Tu, Y. (2015). A method for man hour optimisation and workforce allocation problem with discrete and non-numerical constraints in large-scale one-of-a-kind production. International Journal of Production Research, 54(3), 864–877. doi:10.1080/00207543.2015.1088972
  • Mohd Zaki, N. I., Abu Husain, M. K., & Najafian, G. (2018). Extreme structural responses by nonlinear system identification for fixed offshore platforms. Ships and Offshore Structures, 13(sup1), 251–263. doi:10.1080/17445302.2018.1443377
  • Mukhlas, N. A., Mohd Zaki, N. I., Abu Husain, M. K., & Najafian, G. (2018). Efficient derivation of extreme offshore structural response exposed to random wave loads. Ships and Offshore Structures, 13(7), 719–733. doi:10.1080/17445302.2018.1452474
  • Nam, J.-H., Lee, J. H., & Woo, J. H. (2015). Construction of standardised data structure for simulation of mid-term scheduling of shipbuilding process. International Journal of Computer Integrated Manufacturing, 29(4), 424–437. doi:10.1080/0951192X.2015.1066031
  • Okayama, Y. & Chirillo, L. D. & Todd Pacific Shipyards Corporation & United States. Maritime Administration. Office of Advanced Ship Development & Society of Naval Architects and Marine Engineers (U.S.). Ship Production Committee. (1980). Product work breakdown structure. U.S. Dept. of Commerce, Maritime Administration in cooperation with Todd Pacific Shipyards Corporation, Washington, D.C.
  • Oliveira, A., & Gordo, J. (2018). Model to forecast times and costs of cutting, assembling and welding stages of construction of ship blocks. Paper presented at the Progress in Maritime Technology and Engineering: Proceedings of the 4th International Conference on Maritime Technology and Engineering (MARTECH 2018), May 7–9, 2018, Lisbon, Portugal.
  • Pal, M. (2015). Ship work breakdown structures through different ship lifecycle stages. Paper presented at the International Conference on Computer Applications in Shipbuilding 2015, Bremen, Germany
  • Performance Forum (2017). Offshore structure benchmark for costing. Retrieved from https://www.performance-forum.com/.
  • Potty, N. S., & Akram, M. K. B. M. (2009). Structural integrity management for fixed offshore platforms in Malaysia. Platform, 7(2), 8–20.
  • Rahman, W. A. Z. W. A., Zaki, N. I. M., & Husain, M. K. A. (2019). A review of work breakdown structure and man-hours estimation method used in shipbuilding production. International Journal of Mechanical Engineering and Technology, 10(1), 1141–1158.
  • Rose, K. H. (2013). A guide to the project management body of knowledge (PMBOK® guide); fifth edition. Project Management Journal, 44(3), e1–e1. doi:10.1002/pmj.21345
  • Ross, J. (2002). Forging a real-time link between initial ship design and estimated costs. ICCAS, 2002, 75–88.
  • Ross, J. M. (2004). A practical approach for ship construction cost estimating. COMPIT’04, Siguenza, Spain.
  • Ross, J. M., McNatt, T. R., & Hazen, G. (2002). The project 21 smart product model: A new paradigm for ship design, cost estimation, and production planning. Journal of Ship Production, 18(2), 73–78.
  • Salenm, M. (1997). Multiple linear regression analysis for work measurement of indirect labor. Journal of Industrial Engineering, 18(5), 314–319.
  • Sasaki, Y. (2003). Application of factory simulation to the shipyard. Paper presented at the COMPIT, Hamburg, Germany.
  • Sasaki, Y., Miura, M., Takano, G., Fujita, K., Fujiwara, N., Iida, A., & Sagou, A. (2001). Research on total cost evaluation system for shipyard. 7th International Symposium. Japan Welding Society.
  • Sasaki, Y., & Sonda, M. (2002). A study on 3-D digital mockup systems for shipbuilding. Journal of the Society of Naval Architects of Japan, (192), 707–712. doi:10.2534/jjasnaoe1968.2002.707
  • Shmueli, G., Patel, N. R., & Bruce, P. C. (2011). Data mining for business intelligence: Concepts, techniques, and applications in Microsoft Office Excel with XLMiner. NY: Wiley.
  • Trumbule, J. C., Dougherty, J. J., Deschamps, L., Ewing, R., Greenwell, C. R., & Lamb, T. (2000). Product-oriented design and construction (PODAC) Cost module: An update. Journal of Ship Production, 16(1), 60–68.