Assessing the causes of project overruns in tunnel construction projects in Pakistan

, , &

References

  • Abd El-Razek M, Bassioni H, Mobarak A. 2008. Causes of delay in building construction projects in Egypt. J Constr Eng Manage. 134(11):831–841.
  • Aibinu AA, Odeyinka HA. 2006. Construction delays and their causative factors in Nigeria. J Constr Eng Manage. 132(7):667–677.
  • Al-Momani AH. 2000. Construction delay: a quantitative analysis. Int J Project Manage. 18(1):51–59.
  • Assaf SA, Al-Hejji S. 2006. Causes of delay in large construction projects. Int J Project Manage. 24(4):349–357.
  • Azhar N, Farooqui RU, Ahmed SM. 2008. Cost overrun factors in construction industry of Pakistan. First International Conference on Construction in Developing Countries (ICCIDC–I), Advancing and Integrating Construction Education, Research and Practice, 499–508.
  • Batool A, Abbas F. 2017. Reasons for delay in selected hydro-power projects in Khyber Pakhtunkhwa (KPK), Pakistan. Renew Sustain Energy Rev. 73:196–204.
  • Brown E, Hoek E. 1980. Underground excavations in rock. Boca Raton: CRC Press.
  • Charoenngam C, Yeh C-Y. 1999. Contractual risk and liability sharing in hydropower construction. Int J Project Manage. 17(1):29–37.
  • Efron N, Read M. 2012. Analysing international tunnel costs. Worcester, MA: Worcester Polytechnic Institute.
  • Elawi GSA, Algahtany M, Kashiwagi D. 2016. Owners’ perspective of factors contributing to project delay: case studies of road and bridge projects in Saudi Arabia. Procedia Eng. 145:1402–1409.
  • Endut IR, Akintoye A, Kelly J. 2009. Cost and time overruns of projects in Malaysia. Retrieved on August 21, 243–252.
  • Famiyeh S, Amoatey CT, Adaku E, Agbenohevi CS. 2017. Major causes of construction time and cost overruns. JEDT. 15(2):181–198.
  • Flyvbjerg B. 2014. What you should know about megaprojects and why: an overview. Project Manage J. 45(2):6–19.
  • Flyvbjerg B, Skamris Holm MK, Buhl SL. 2003. How common and how large are cost overruns in transport infrastructure projects? Transport Rev. 23(1):71–88.
  • Flyvbjerg B, Skamris Holm MK, Buhl SL. 2004. What causes cost overrun in transport infrastructure projects? Transport Rev. 24(1):3–18.
  • Frimpong Y, Oluwoye J, Crawford L. 2003. Causes of delay and cost overruns in construction of groundwater projects in a developing countries: Ghana as a case study. Int J Project Manage. 21(5):321–326.
  • Gündüz M, Nielsen Y, Özdemir M. 2013. Quantification of delay factors using the relative importance index method for construction projects in Turkey. J Manage Eng. 29:133–139.
  • Harrison JP, Hudson JA, Popescu M. 2002. Engineering rock mechanics: Part 2. Illustrative worked examples. Appl Mech Rev. 55(2):B30–B31.
  • Haseeb M, Luxinhai AB, Raqeeb QG. 2012. A case study on: importance of delay causes in construction projects of Pakistan. Asian J Business Manage Sci. 1(1):2047–2528.
  • Hoek E, Palmieri A, Moore D, Hungr O. 1998. Geotechnical risks on large civil engineering projects. Proceedings of the 8th Congres IAEG, p. 79–88.
  • Isaksson T. 2002. Model for estimation of time and cost based on risk evaluation applied on tunnel projects. Stockholm, Sweden: Byggvetenskap.
  • Kamal A, Abas M, Khan D, Azfar RW. 2019. Risk factors influencing the building projects in Pakistan: from perspective of contractors, clients and consultants. Int J Construct Manage. https://doi.org/10.1080/15623599.2019.1683693.
  • Karunakaran P, Abdullah A, Nagapan S, Sohu S, Kasvar K. 2018. Categorization of potential project cost overrun factors in construction industry. IOP Conf Ser: Earth Environ Sci. 140:012098.
  • Khabisi J, Aigbavboa C, Thwala W. 2017. Causes of cost overruns in public sector construction projects in South Africa. In: ICCREM 2016: BIM Application and Off-Site Construction. Reston, VA: American Society of Civil Engineers; p. 1311–1317.
  • Khalfan M. 2013. Perception of procurement on successful infrastructure project outcomes in Pakistan. In CIB World Building Congress 2013: Construction and Society, Queensland University of Technology, p. 424–424.
  • Lee J-K. 2008. Cost overrun and cause in Korean social overhead capital projects: Roads, rails, airports, and ports. J Urban Plann Dev. 134(2):59–62.
  • Long ND, Ogunlana S, Quang T, Lam KC. 2004. Large construction projects in developing countries: a case study from Vietnam. Int J Project Manage. 22(7):553–561.
  • Love PE, Wang X, Sing C-P, Tiong RL. 2013. Determining the probability of project cost overruns. J Constr Eng Manage. 139(3):321–330.
  • Lundin RA, Tryggestad K, Amoatey CT, Ameyaw YA, Adaku E, Famiyeh S. 2015. Analysing delay causes and effects in Ghanaian state housing construction projects. Int J Manag Project Business. 8(1):198–214.
  • Membah J, Asa E. 2015. Estimating cost for transportation tunnel projects: a systematic literature review. Int J Construct Manage. 15(3):196–218.
  • Mohajan HK. 2017. Two criteria for good measurements in research: validity and reliability. Ashu-Es. 17(4):59–82.
  • Muhwezi L, Acai J, Otim G. 2014. An assessment of the factors causing delays on building construction projects in Uganda. Int J Construct Eng Manage. 3:13–23.
  • Ogwueleka A. 2011. The critical success factors influencing project performance in Nigeria. Int J Manage Sci Eng Manage. 6(5):343–349.
  • Olawale YA, Sun M. 2010. Cost and time control of construction projects: inhibiting factors and mitigating measures in practice. Construct Man Econ. 28(5):509–526.
  • Paraskevopoulou C, Boutsis G. 2020. Cost overruns in tunnelling projects: investigating the impact of geological and geotechnical uncertainty using case studies. Infrastructures. 5(9):73.
  • Reilly JJ, Arrigoni GA. 2005. Management and control of cost and risk for tunneling and infrastructure projects. In China perspective, for the South to North Great Western Diversion. 南水北调西线工程深埋, 长大隧道关键技术及掘进机应用国际研讨会论文集.
  • Riedmüller G, Schubert W. 2000. Tunnelling in fault zones-Innovative approaches. 4th North American Rock Mechanics Symposium, American Rock Mechanics Association.
  • Sambasivan M, Deepak T, Salim AN, Ponniah V. 2017. Analysis of delays in Tanzanian construction industry. ECAM. 24(2):308–325.
  • Sambasivan M, Soon YW. 2007. Causes and effects of delays in Malaysian construction industry. Int J Project Manage. 25(5):517–526.
  • Sarkar D, Dutta G. 2011. A framework of project risk management for the underground corridor construction of metro rail. IIMA Working Papers WP2011-02-05, Indian Institute of Management Ahmedabad, Research and Publication Department.
  • Schneider M, Froggatt A, Hazemann J, Katsuta T, Ramana M, Rodriguez JC, Rodinger A, Stienne A. 2016. The world nuclear industry. Status Report.
  • Senent S, Jimenez R. 2015. A tunnel face failure mechanism for layered ground, considering the possibility of partial collapse. Tunnel Underground Space Technol. 47:182–192.
  • Shah RK. 2016. An exploration of causes for delay and cost overrun in construction projects: A case study of Australia, Malaysia & Ghana. J Adv Coll Engin Mgt. 2:41–55.
  • Shaikh FA, Odhano N, Jhatial AA. 2020. Financial issues in project schedule of the construction industry in Pakistan. J Appl Eng Sci. 10(1):89–94.
  • Shrestha PP, Burns LA, Shields DR. 2013. Magnitude of construction cost and schedule overruns in public work projects. J Constr Eng. 2013:1–9.
  • Sinha RS. 2012. Underground structures: design and instrumentation, Amsterdam, The Netherlands: Elsevier.
  • Sohu S, Abdullah AH, Nagapan S, Memon NA, Yunus R, Hasmori MF. 2018. Causative factors of cost overrun in building projects of Pakistan. IJIE. 10(9):22–27.
  • Sohu S, Abdullah A, Nagapan S, Rind T, Jhatial A. 2019. Controlling measures for cost overrun causes in highway projects of Sindh province. Eng Technol Appl Sci Res. 9(3):4276–4280.
  • Sohu S, Abdullah AH, Nagapan S, Fattah A, Ullah K, Kumar K. 2017. Contractors perspective for critical factors of cost overrun in highway projects of Sindh, Pakistan. AIP Conference Proceedings, AIP Publishing LLC, 080002.
  • Sohu S, Memon NA, Abbasi SA, Pahore MA, Ullah K. 2016. Causes of delay in highway projects in Pakistan. 8th International Civil Engineering Congress, Karachi, Pakistan, 35–40.
  • Sovacool BK, Nugent D, Gilbert A. 2014. Construction cost overruns and electricity infrastructure: an unavoidable risk? Electricit J. 27(4):112–120.
  • Stille H, Palmström A. 2008. Ground behaviour and rock mass composition in underground excavations. Tunnel Underground Space Technol. 23(1):46–64.
  • Tafazzoli M, Shrestha PP. 2017. Investigating causes of delay in US Construction Projects.
  • Terwee CB, Bot SD, de Boer MR, van der Windt DA, Knol DL, Dekker J, Bouter LM, de Vet HC. 2007. Quality criteria were proposed for measurement properties of health status questionnaires. J Clin Epidemiol. 60(1):34–42.
  • Toor SUR, Ogunlana SO. 2008. Problems causing delays in major construction projects in Thailand. Construct Man Econ. 26(4):395–408.
  • Venkateswaran CB, Murugasan R. 2017. Time delay and cost overrun of road over bridge (ROB) construction projects in India. JCDC. 22(suppl. 1):79–96.
  • Wang H, Jia Y, Cao L. 2012. Cause analysis and prevention of road tunnel collapse in complex soft strata. Energy Procedia. 16:259–264.
  • Yan-Jun S, Rui-Xin Y, Geng-She Y, Guang-Li X, Shan-Yong W. 2017. Comparisons of evaluation factors and application effects of the new [BQ] GSI system with international rock mass classification systems. Geotech Geol Eng. 35(6):2523–2548.
  • Zafar I, Wuni IY, Shen GQ, Ahmed S, Yousaf T. 2019. A fuzzy synthetic evaluation analysis of time overrun risk factors in highway projects of terrorism-affected countries: the case of Pakistan. Int J Construct Manage. https://doi.org/10.1080/15623599.2019.1647634.

Reprints and Corporate Permissions

Please note: Selecting permissions does not provide access to the full text of the article, please see our help page How do I view content?

To request a reprint or corporate permissions for this article, please click on the relevant link below:

Academic Permissions

Please note: Selecting permissions does not provide access to the full text of the article, please see our help page How do I view content?

Obtain permissions instantly via Rightslink by clicking on the button below:

If you are unable to obtain permissions via Rightslink, please complete and submit this Permissions form. For more information, please visit our Permissions help page.